Eton Range Realignment Project RAAG Presentation 10 March

  • Slides: 14
Download presentation
Eton Range Realignment Project RAAG Presentation 10 March 2016 1|

Eton Range Realignment Project RAAG Presentation 10 March 2016 1|

Agenda • Deficiencies of Existing Crossing • Safety Improvements • Reinforced Earth Embankment (REE)

Agenda • Deficiencies of Existing Crossing • Safety Improvements • Reinforced Earth Embankment (REE) • Traffic Management • Project Details • Drive-thru Video 2|

Deficiencies of Existing Crossing Site of Fatal Accidents HV Traction Issues (11%) Composite Curve

Deficiencies of Existing Crossing Site of Fatal Accidents HV Traction Issues (11%) Composite Curve Width Constraints Hairpins 50 metre radii High Speed Approaches (Up & Down) 3| Slope Stability Issue

Safety Improvements Breakdown curves to control approach speed 5 x CCTV Cameras for incident

Safety Improvements Breakdown curves to control approach speed 5 x CCTV Cameras for incident management Hairpin radius improvement, 55 m to 75 m RE Embankment 4 lanes Vertical grade 7. 5% 4|

Safety Improvements Alignment follows the crest of ridge Traffic diverted to allow construction of

Safety Improvements Alignment follows the crest of ridge Traffic diverted to allow construction of up alignment Increase speed sooner Sidelong cut/fill profile Traffic change over point for incident management 5|

Reinforced Earth Embankment (REE) Height 10 m – 44 m 6|

Reinforced Earth Embankment (REE) Height 10 m – 44 m 6|

Reinforced Earth Embankment (REE) 7|

Reinforced Earth Embankment (REE) 7|

Reinforced Earth Embankment (REE) 8|

Reinforced Earth Embankment (REE) 8|

Traffic Management Stage 1 A Work Zones Traffic Lanes Duration 2 Months Site Office

Traffic Management Stage 1 A Work Zones Traffic Lanes Duration 2 Months Site Office & Entry Overtaking Lane Closed 9|

Traffic Management Stage 1 B Work Zones Traffic Lanes Duration 15 Months Site Office

Traffic Management Stage 1 B Work Zones Traffic Lanes Duration 15 Months Site Office & Entry Overtaking Lane Closed 10 |

Traffic Management Stage 2 Work Zones Traffic Lanes Duration 12 Months Site Office &

Traffic Management Stage 2 Work Zones Traffic Lanes Duration 12 Months Site Office & Entry Overtaking Lane Closed 11 |

Traffic Management Stage 3 Work Zones Traffic Lanes Duration 1 Months Site Office &

Traffic Management Stage 3 Work Zones Traffic Lanes Duration 1 Months Site Office & Entry 12 |

Traffic Management • Two Lane Operation at All Times except when Blasting All Motorist:

Traffic Management • Two Lane Operation at All Times except when Blasting All Motorist: • VMS Boards used for advanced warning to roadworks • Public notices on TMR website for project updates: www. tmr. qld. gov. au/Projects • Stakeholder email notification group Heavy Vehicles: • Truck pull-off areas maintained – OSOM management performed as normal by Police • OSOM restrictions on TMR website - Advised to contact Fulton Hogan prior to travelling: www. tmr. qld. gov. au/business-industry/Heavyvehicles/Excess-mass-and-dimension-conditions • Stakeholder email notification group heavy haulage • Permit Conditions 13 |

Traffic Management • Contractor: Fulton Hogan Construction Pty Ltd • Project Duration: 16 March

Traffic Management • Contractor: Fulton Hogan Construction Pty Ltd • Project Duration: 16 March 2016 – Late 2018 • If you would like to be added to stakeholder email notification group, please email: Mackay. Office@tmr. qld. gov. au • If you wish to contact the TMR project team, please email: ERRP@tmr. qld. gov. au CC: mark. g. weatherley@tmr. qld. gov. au CC: emma. k. lyons@tmr. qld. gov. au • Project Manager: Mark Weatherley (Ph: 0459 800 467) • Project Engineer: Emma Lyons (Ph: 0467 817 802) 14 |