EQ programs at Mochovce NPP Severe Accident Cases

  • Slides: 11
Download presentation
EQ programs at Mochovce NPP – Severe Accident Cases Marek Tengler (IEEE SC 2,

EQ programs at Mochovce NPP – Severe Accident Cases Marek Tengler (IEEE SC 2, Orlando) (15 -17 th June, 2011)

1. Brief information - Mochovce NPP (MO 34) Mochovce NPP (utility SE, ENEL) PWR

1. Brief information - Mochovce NPP (MO 34) Mochovce NPP (utility SE, ENEL) PWR plant type VVER 440 model V-213 - Four units with original design electric power output 440 MWe, each - 2 Units in operation - Design Lifetime: 30 year (+10) - Seismic hazard: Design value PGA = 0, 15 g SSE for 1 x 10 E 4 years COMPLETION PHILOSOPHY FOR UNIT 3 AND 4: UPGRADE DESIGN GENERATION II NPP INTO GENERATION III NPP EQ programs at Mochovce NPP – Severe Accident Cases 2

2. SA – Qualification vs Survivability Assesment BASIC ASSUMPTION - Equipment shall be subject

2. SA – Qualification vs Survivability Assesment BASIC ASSUMPTION - Equipment shall be subject to an assessment to demonstrate that its design provides a reasonable level of confidence that it shall operate in the environment under which it is required to perform its functions in Design Extension Conditions and it shall be able to operate over the timespan for which it is needed. - Qualification of components and systems, as required for those coping with Design Basis Conditions, does not necessarily apply. - Demonstration of equipment survivability does not require the same rigorous demonstrations and the same conservatisms as a true qualification process. EQ programs at Mochovce NPP – Severe Accident Cases 3

Design Basis Conditions (LB LOCA) - Thermo-dynamic profiles (temperature, pressure), - Post-accident duration (5

Design Basis Conditions (LB LOCA) - Thermo-dynamic profiles (temperature, pressure), - Post-accident duration (5 h – 100 days), - Radiation conditions: dose, dose rate, TID Design Extension Conditions (SA defined in Basic Design) - Temperature peak (primordial): 139°C (duration < 30 min. ) - Pressure peak (primordial): 350 k. Pa°C (duration < 30 min. ) - Post-accident duration (primordial): 1 year +, - Radiation conditions (primordial): cca 0. 3 MGy - Humidity: 100% EQ programs at Mochovce NPP – Severe Accident Cases 4

Alternative parameters of SA DEC for MO 34 Variant 1 - H 2 burning

Alternative parameters of SA DEC for MO 34 Variant 1 - H 2 burning - Peak temperature 1600 °C - Pressure wave Variant 2 - Permanent temperature 139°C – 1 year Variant n+1 SCIENTIST‘S APPROACH VS ENGINEER‘S APPROCH DECISION SHALL BE BASED ON ENGINEERIG JUDGMENT EQ programs at Mochovce NPP – Severe Accident Cases 5

3. Applied approach for equipment evaluation/assessment for SA conditions Distinction of accordingly environmental zones

3. Applied approach for equipment evaluation/assessment for SA conditions Distinction of accordingly environmental zones - MILD environmental zone HARSH environmental zone RULES FOR HARSH ZONE - Applied for equipment with existing qualification documentation - Not combine DEC (SA) with DBC (LB LOCA) - Definition of target values: TD environmental extreme peak - SA radiation dose is considered as contribution to TID (accident dose) - No margins are considered EQ programs at Mochovce NPP – Severe Accident Cases 6

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) EQ programs at Mochovce

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) EQ programs at Mochovce NPP – Severe Accident Cases 7

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) RULES FOR MILD ZONE

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) RULES FOR MILD ZONE - Applied for equipment with existing qualification documentation and equipment to be tested - SA ageing is not considered in line equipment conditioning followed by simulation of postulated event (seismic, accident …) - SA is considered as design requirements (radiation resistance, degree of protection – IP, anti-explosion design etc. ) - No margins are considered EQ programs at Mochovce NPP – Severe Accident Cases 8

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) Distinction of accordingly environmental

3. Applied approach for equipment evaluation/assessment for SA conditions (cont‘d) Distinction of accordingly environmental zones - MILD environmental zone HARSH environmental zone RULES FOR HARSH ZONE - Applied for equipment with existing qualification documentation - Not combine DEC (SA) with DBC (LB LOCA) - Definition of target values as environmental extreme peak - No margins are considered EQ programs at Mochovce NPP – Severe Accident Cases 9

3. Specific example – SA Capability of electric motor - Special designed electric motor

3. Specific example – SA Capability of electric motor - Special designed electric motor in accordance of pump performance characteristics - Radiation resistance of winding insulation material – MICALASTIC tested for 1 x 10 E 7 Gy EQ programs at Mochovce NPP – Severe Accident Cases 10

 • Loading moment of the pump exceed the moment of motor, i. e.

• Loading moment of the pump exceed the moment of motor, i. e. at moment equality the start-up of motor is stopped in this point, however the current will be 180 A – 3. 2 times of nominal value • The issue should be the time during standby regimes where is postulated interval of voltage drop to value of 65% Un. • In Technical Specification of the motor is a allowable period of refreshment 7 sec. • What happened if period of voltage refreshment is longer? EQ programs at Mochovce NPP – Severe Accident Cases 11