Energy Gateway Update for Wyoming Infrastructure Authority January
- Slides: 15
Energy Gateway Update for Wyoming Infrastructure Authority January 27, 2009 Darrell Gerrard Vice President Transmission System Planning
Pacifi. Corp Energy Gateway Program Update Pacifi. Corp Overview Energy Gateway Foot Print Energy Gateway Program Overview and Update Energy Gateway Base Case Analyses Key Issues and Next Steps © 2000 PACIFICORP | PAGE 2 – – –
Pacifi. Corp Overview Customers (million) Annual Call Volume (millions) Number of Meters (millions) Retail Energy Sales (TWh) Generating Capacity (MW) Line Miles Substations Number of Employees 1. 7 5. 7 1. 8 53 9, 286 77, 000 900 6, 500 © 2000 PACIFICORP | PAGE 3 – – – –
© 2000 PACIFICORP | PAGE 4 System Load and Resource Balance* * December 18, 2008 public IRP presentation
Energy Gateway Program Overview – 1900+ miles of high voltage transmission – ~$6. 0 B invested over 10 years – Key segments in service by 2014 – Design “hub and spoke” concept – Options to transport Generation 4 4 Wind Thermal New and Existing – Planned to support up to 3000 MWs capacity – Pacifi. Corp’s network allocation targeted at 1500 MWs © 2000 PACIFICORP | PAGE 5 4
Interdependency of 500 k. V facilities 1 2 © 2000 PACIFICORP | PAGE 6 – Current system 230 and 345 k. V – No 500 k. V in footprint – Need “n-1” backup – (1) Energy Gateway West 4 Aeolus to Populus – (2) Energy Gateway South 4 Aeolus to Mona
– Technical 4 Issued Phase 1 rating report for key Energy Gateway segments – 11/21/08 4 Obtained Phase 2 rating approval for Populus-Terminal Line (Segment B) – Commercial 4 Completed revised permitting agreement with Idaho Power 4 Completed equity offering and open access service offering – Siting and permitting 4 Community and landowner events 4 Mona – Oquirrh draft EIS – April 09 4 Energy Gateway West draft EIS – Dec. 09 – Regulatory 4 FERC incentive rate declaratory order – 10/21/08 © 2000 PACIFICORP | PAGE 7 Energy Gateway Progress Update
Energy Gateway Base Case Analysis Gateway West Gateway South © 2000 PACIFICORP | PAGE 8 Gateway Central
Base Case Generation Assumptions – Phase I – WECC Phase I Comprehensive Progress Reports for Gateway West and Gateway South completed - November 21, 2008 – 3 base case scenarios were included in the analysis: 4 Scenario 1 a / 1 b - Evaluated the system under a wide range of thermal vs. wind resource conditions based on the following assumptions: o Wyoming high thermal and moderate wind resources based on the 2007 Pacifi. Corp Integrated Resource Plan. o High wind and moderate thermal resources modeled in (1 b) base case based on OASIS queue requests and projections Scenario 1 c: Developed to evaluate the southern Utah transmission system (TOT 2 C/2 B) and Mona South path under simultaneous S to N flow conditions. – Gateway West (West of Bridger) utilized the Case 1 a base case – Gateway West (East of Bridger) and Gateway South utilized all three base cases. – Ultimately, specific economic and technology evaluations and siting/permitting processes will need to run their course before specific resources that will be served by the Gateway Project are determined. © 2000 PACIFICORP | PAGE 9 4
© 2000 PACIFICORP | PAGE 10 Wyoming Base Cases 1 a vs. 1 b Comparison
© 2000 PACIFICORP | PAGE 11 WY 2015 Case 1 a – High Thermal / Moderate Wind
© 2000 PACIFICORP | PAGE 12 WY 2015 Case 1 b – High Wind / Moderate Thermal
© 2000 PACIFICORP | PAGE 13 WY 2015 Case 1 c – High Southern UT S-N Path Flows
Key Issues and Next Steps Key Issues: • • • System is planned at 3000 MWs; scalable Decision to deliver 1500 MWs needed shortly to maintain engineering and permitting schedules Rigid delivery structure is necessary to maintain schedule Customers and equity partners have declined participation opportunities US Government participation a possibility Resource support (capacity and energy via ancillary services) will be necessary • • Mona – Oquirrh draft EIS – April 2009 CPCNs – July 2009 Gateway West draft EIS – December 2009 Mona – Oquirrh final EIS – December 2009 © 2000 PACIFICORP | PAGE 14 Next Steps:
Questions? © 2000 PACIFICORP | PAGE 15 Energy Gateway website www. pacificorp. com/energygateway
- Wyoming infrastructure authority
- Wyoming pipeline authority
- Database backup and recovery techniques
- Line authority means
- Energy energy transfer and general energy analysis
- Energy energy transfer and general energy analysis
- Ministry of infrastructure and energy albania
- Ceii ferc
- Wyoming medicaid client portal
- Wyoming medicaid providers
- Wyoming egi
- Water rights wyoming
- Wyoming medicaid travel reimbursement
- Atlantic city project wyoming
- Wyoming lottery corporation
- Wyoming counseling association