ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF December 29, 2021

ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF December 29, 2021

Worksite follow-up � Mechanical support installation Installation of the supports and survey done. Sealing

Worksite follow-up � Mechanical support installation Installation of the supports and survey done. Sealing Done � Next: Septum and BTV support. � Alignment tables of the fast deflectors and doublet installed � 2 Erwan Harrouch EN-MEF December 29, 2021

Worksite follow-up � Source re-installation � Relocation of one pipe of the gas panel

Worksite follow-up � Source re-installation � Relocation of one pipe of the gas panel needed to install the protective cover : Planned in the afternoon. HV Test should take place tomorrow 3 Erwan Harrouch EN-MEF December 29, 2021

Worksite follow-up � CV works : RF Cavity manifold re-located (integration checked) � The

Worksite follow-up � CV works : RF Cavity manifold re-located (integration checked) � The pipes on the shielding will be rerouted on the 23 th of November � Visit of AD planed on the 16 th with ENCV � � Impact 4 : 70520 Erwan Harrouch EN-MEF December 29, 2021

Worksite follow-up � Cleaning of the rack storage area : Deadline : 31 th

Worksite follow-up � Cleaning of the rack storage area : Deadline : 31 th of October � RP checks done on the storage : No radioactive material found however. Final check will have to be performed before evacuation. Re-Locate your equipment in the Gbar area for RP checks. 5 Erwan Harrouch EN-MEF December 29, 2021

Will go to storage after RP checks 6 Erwan Harrouch EN-MEF December 29, 2021

Will go to storage after RP checks 6 Erwan Harrouch EN-MEF December 29, 2021

Worksite follow-up � Cable pulling : 85% done. � Installation of connectors : 85%

Worksite follow-up � Cable pulling : 85% done. � Installation of connectors : 85% done � Tests : 85% done � HV 7 Cables : 40% + 1 -2 more weeks of work Erwan Harrouch EN-MEF December 29, 2021

Summary of the work planned next week � Cabling campaign (P. Burdelski) � Cleaning

Summary of the work planned next week � Cabling campaign (P. Burdelski) � Cleaning of the rack storage area (E. Harrouch) � Powering of the new platform (R. Necca) � Source installation (A. Megia) � Mechanical support installation (A. Kolehmainen) 8 Erwan Harrouch EN-MEF December 29, 2021

Planning Update � New planning on EDMS : https: //edms. cern. ch/document/1407912/0. 7 �

Planning Update � New planning on EDMS : https: //edms. cern. ch/document/1407912/0. 7 � Future updates : � The first dipole installed will be in section 6 (18/02/2015) � Update of the installation dates : � Installation of Fast Deflectors will start on the 7 th of December � Scrapers installation will start on the 1 st of April � Installation of the striplines : March (will be adjusted soon) � Delay in the installation of the kicker to be foreseen � IT Installation will take place the first two weeks of December 9 Erwan Harrouch EN-MEF December 29, 2021