ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF September 23, 2021

ELENA Project Installation follow-up 1 Erwan Harrouch EN-MEF September 23, 2021

Worksite follow-up � Mechanical support installation � Sealing done Alignment tables installed : 6/6

Worksite follow-up � Mechanical support installation � Sealing done Alignment tables installed : 6/6 sectors done! 1 st magnet installed! � BTV and kickers support delivered 2 Erwan Harrouch EN-MEF September 23, 2021

Worksite follow-up � Source re-installation � Issues when starting the source � Preparation for

Worksite follow-up � Source re-installation � Issues when starting the source � Preparation for the installation of LNS temporary set up ongoing 3 Erwan Harrouch EN-MEF September 23, 2021

Worksite follow-up � Cabling activities : � On the 15 th of February, the

Worksite follow-up � Cabling activities : � On the 15 th of February, the second cabling campaign (DC and control) will start. � 4 racks in the power room (Green rack 600 x 800 mm) will be installed 4 Erwan Harrouch EN-MEF September 23, 2021

Worksite follow-up � Optical fiber installation � � Pulling of the optical fiber is

Worksite follow-up � Optical fiber installation � � Pulling of the optical fiber is on-going from the power room to the racks (should finish by the end of the week) LV installation : � � LV Works completed : Tests to be done Start of installation of the power sockets in two weeks � 5 Prototype validated, marking of the position next week on Tuesday Erwan Harrouch EN-MEF September 23, 2021

Worksite follow-up � SMB-SE works Side platform being modified � Reinstallation by next week

Worksite follow-up � SMB-SE works Side platform being modified � Reinstallation by next week � Modification of the false floor by next week � Support of the Btrain magnet : In the hand of the company at the moment. Planned for week 7. � Courtesy to O. Choisnet 6 Erwan Harrouch EN-MEF September 23, 2021

Closure of the shielding wall • The vacuum chamber has been marked on the

Closure of the shielding wall • The vacuum chamber has been marked on the shielding • Integration model has been modified to match reality 7 Erwan Harrouch EN-MEF September 23, 2021

Summary of next week � LNS installation (D. Barna) � Mechanical support installation (A.

Summary of next week � LNS installation (D. Barna) � Mechanical support installation (A. Kolehmainen) � Kicker and BTV Support � LNI installation (E. Harrouch) � Closing of the shielding? � Source Installation (A. Megia) � Completion � LV installation (R. Necca) � Installation 8 of the source installation of the power sockets Erwan Harrouch EN-MEF September 23, 2021

LNI Installation schedule � Delivery � Two of the vacuum chambers by the workshop

LNI Installation schedule � Delivery � Two of the vacuum chambers by the workshop chambers come late : The installation of the bending magnet is already on the critical path and planned for the 22/02/2016 at the moment. 9 Erwan Harrouch EN-MEF September 23, 2021

Latest date of installation for the bending magnet but not realistic at the moment

Latest date of installation for the bending magnet but not realistic at the moment ! LNI Installation update 10 Vacuum sector ready on the 18/03 – No Margin September 23, 2021

Doublet+SEM installation strategy � All the doublets and their supports are delivered for phase

Doublet+SEM installation strategy � All the doublets and their supports are delivered for phase 1. � They come by set of three and are kept pressurized with nitrogen (With pinch off flanges) � 3 of them are NEG coated and need to be kept under nitrogen once installed � Next week : First quadrupole will be installed for the LNS test. � Proposal : Wait for the SEM Tanks to install the assembly to minimize the time of exposure of the NEG coating to ambient air. (when? ) Installation of the supports can already start 11 Erwan Harrouch EN-MEF September 23, 2021

Magnet installation update Correctors delivery schedule Last magnet triggers the start of alignment, vacuum

Magnet installation update Correctors delivery schedule Last magnet triggers the start of alignment, vacuum connections and bake-out (~1, 5 month) Can they be installed around the vacuum chamber after bake-out? Production for LNR + LNI Spare + E-cooler Hi-Lumi 12 +4 weeks / Cumulative 11/02/2016 : 1 29/03/2016 : 3 02/05/2016 : 6 15/06/2016 : 10 29/07/2016 : 14 Erwan Harrouch EN-MEF September 23, 2021

A word on the de-cabling of the transfer lines � The work will be

A word on the de-cabling of the transfer lines � The work will be presented tomorrow at the general de-cabling project meeting https: //indico. cern. ch/event/487654/ � � At the moment the list of cables are ready for distribution (To be expected next week). 13 Erwan Harrouch EN-MEF NB de cable par groupe BE-BI EN-EL TE-MSC TE-MPE TE-EPC EN-STI TE-VSC ASACUSA BE-ICS September 23, 2021 175 19 2 78 99 4 116 7 6 506