ELENA Project E. Harrouch Transfer line installation during LS 2 Erwan Harrouch EN-EA-EC October

ELENA Project E. Harrouch Transfer line installation during LS 2 Erwan Harrouch EN-EA-EC October 06, 2016

Documentation � The following planning is an extrapolation from the planning initially foreseen in

Documentation � The following planning is an extrapolation from the planning initially foreseen in 2017 � Planning proposal on EDMS for comments : EDMS 1725168 Erwan Harrouch EN-EA-EC October 06, 2016

TL LS 2 Installation planning : Proposal Start ASAP in LS 2 to maximize

TL LS 2 Installation planning : Proposal Start ASAP in LS 2 to maximize commissioning time • EN-EL : ~ 2 months, TE-MSC : ~ 2 wks, • EN-HE : ~ 2, 5 month (Supervision from TEMSC, TE-VSC, EN-MME, HSE-RP • measurements) EN-HE : ~ 2, 5 months, EN-ACE-SU : ~1, 25 month, EN-MME : ~1, 5 month, TE-VSC : ~1, 75 month (Supervision from TE-ABT, BE-BI) • EN-EL-EIC & FC : ~ 2 months, EN-EL-BT : ~ 3 wks • TE-VSC : ~2, 5 months • 4 weeks for hardware commissioning : TE-ABT, TE-EPC, BE-BI • Beam commissioning with the H+/Source: BE-OP : ~4 months Start : 07/01/2016 De-cabling activities and services dismantling Dismantling of the beamlines 27 May '19 Installation of the new transfer lines elements 21 Aug '19 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 20 Beam Commisionning Will be fed into PLAN very soon ! Extracted from detailed schedule: 11 Mar‘ 19 Finish : 11/05/2020 11 May '20

Start : 07/01/2016 Installation strategy � De-cabling activities and services dismantling Cables already identified

Start : 07/01/2016 Installation strategy � De-cabling activities and services dismantling Cables already identified and ready for disconnection by users (EDMS 1707056) Dismantling of the accessible equipment (ENHE, TE-MSC, EN-MME) 1 wk � Flexible cooling pipes removal (TE-MSC) 2 wks � Decabling activities (EN-EL) 8 wks � Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � De-cabling activities and services dismantling Beamline dismantling (TE-MSC,

Start : 07/01/2016 Installation strategy � De-cabling activities and services dismantling Beamline dismantling (TE-MSC, BE-BI, EN-HE, TEVSC) : � 1 month to remove all the equipment (BASE, ALPHA, ATRAP and ASACUSA TLs) Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � Re-organization of the shielding: � � De-cabling activities

Start : 07/01/2016 Installation strategy � Re-organization of the shielding: � � De-cabling activities and services dismantling Dismantling of the beamlines Clean-up of the stochastic cooling platform (BE-RF) : to be done in the first semester of 2019 and removal of the cooling pipes by EN-CV (0, 5 wk) Installation of the new Shielding removal (1 wk), dismantling of the lines(1 wk), transfer lines elements shielding installation (2, 5 wk), cooling pipes reinstallation (1 wk) : Total 1, 5 month Cable pulling and Low Voltage installation 11 Mar‘ 1 27 May '1 21 Aug '1 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � Installation of beamlines: � � De-cabling activities and

Start : 07/01/2016 Installation strategy � Installation of beamlines: � � De-cabling activities and services dismantling Same strategy as ELENA : Ground marking by the survey, Support installation by MME, equipment installation Total implication of the groups : in between 27/05 and 21/08 � ~ 2, 5 months, EN-ACE-SU : ~1, 25 month, EN-MME : ~1, 5 month, TE-VSC : ~1, 75 month, Support from EN-HE the whole time (Supervision from TE-ABT, BE-BI) Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 E 01 LNE 00 LN HW tests LNE 02 07 Feb ‘ 2 E 0 3 6 E 0 LN LNE 07 LN LN E 0 LNE 05 4 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � Cabling and low voltage installation done once all

Start : 07/01/2016 Installation strategy � Cabling and low voltage installation done once all the equipment are installed : 2 month work period De-cabling activities and services dismantling Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � ELENA strategy copied for the bake-out of the

Start : 07/01/2016 Installation strategy � ELENA strategy copied for the bake-out of the line : � 7 sectors to be baked-out : 2, 5 month De-cabling activities and services dismantling Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2

Start : 07/01/2016 Installation strategy � 4 wks of Hardware tests and 4 month

Start : 07/01/2016 Installation strategy � 4 wks of Hardware tests and 4 month of beam commissioning with the source De-cabling activities and services dismantling Dismantling of the beamlines 11 Mar‘ 1 27 May '1 Installation of the new transfer lines elements 21 Aug '1 Cable pulling and Low Voltage installation 23 Oct '19 Bake-out of the lines 10 Jan ‘ 20 HW tests 07 Feb ‘ 2 Beam Commisionning Finish : 11/05/2020 Erwan Harrouch EN-EA-EC October 06, 2016 11 May '2