ELENA – Integration and installation Coordination meeting (IIC) VSC activities and sercvices R. Kersevan,

ELENA – Integration and installation Coordination meeting (IIC) VSC activities and sercvices R. Kersevan, G. Riddone 23/04/2015

ELENA 23/04/2015 2

ELENA 23/04/2015 2

ELENA Ring 23/04/2015 3

ELENA Ring 23/04/2015 3

Vacuum system (1) • TE-VSC specification (EDMS: 1470752) • Vacuum level : 4 x

Vacuum system (1) • TE-VSC specification (EDMS: 1470752) • Vacuum level : 4 x 10 -12 mbar (ring) – 10 -10 mbar TLs • Vacuum chambers and supports: • Design approved by TE-VSC • Drawings for LNR 1 under control 1 (VSC internal review held last week and comments integrated) • Fabrication of Dipole-y chambers launched at the main worksho • Pumps and gate/angle valves: order under way supplied by TEVSC • Bellows: VSC vacuum chambers + BTV tank contacted several companies and received few offers (order will be placed soon) raw material for extremities to be supplied by CERN 23/04/2015 4

Vacuum system (2) • Vacuum firing • T ~ 950°C for 2 h (not

Vacuum system (2) • Vacuum firing • T ~ 950°C for 2 h (not done for bellows) • Tramp: 100°C/h • Leak test-acceptance tests (see TE-VSC specification) • Bake-out: most of cases strips and insulation with Kapton and aluminium foil. No jackets are required. • Drawings needed for launching the procurement • In addition, the following parameters, if specific: • T max • Temperature rate • Interlock on Tmax 23/04/2015 5

Drawings and bellows 23/04/2015 6

Drawings and bellows 23/04/2015 6

 • VSC services – Link: G. Riddone • Cleaning • Vacuum firing •

• VSC services – Link: G. Riddone • Cleaning • Vacuum firing • Leak tests • NEG Coating • Bake-out • Acceptance tests (see specification) 1 w 1 w 1 w 2 w 1 w 1 w Typical and indicative Vacuum services 7 w • Installation of bake-out in situ • Bake-out and NEG activation of the sector 23/04/2015 7

Master planning • ELENA master planning • https: //espace 2013. cern. ch/TEVSCgroup/Projects/_layouts/15/start. aspx#/Lists/Master%20 Planning%20

Master planning • ELENA master planning • https: //espace 2013. cern. ch/TEVSCgroup/Projects/_layouts/15/start. aspx#/Lists/Master%20 Planning%20 ELENA/All. Items. aspx • TE-VSC chambers (from design to commissioning • Plus VSC services (not included in WP 2. 5, except for BPM) for: Views for - Leak test - NEG coating - Acceptance tests • BTV • Ion-switch • Kicker tank • LNE quadrupoles ZQNA • BPMs • E-cooler • Fast deflector End dated corresponds to ready for installation Needed confirmation of link person per equipment • Scraper • BIPM (not approved) 23/04/2015 8

Next steps • Several tasks at the same time: • To be duly planned;

Next steps • Several tasks at the same time: • To be duly planned; VSC sharepoint sites for • surface treatment, • NEG coating and • acceptance tests • For non-VSC components, confirmation of dates “ready for installation” and priorities from management are needed • Regular report to IIC meeting 23/04/2015 9