ELENA installation progress F Butin ELENA collaboration ELENA
ELENA installation progress F. Butin / ELENA collaboration
ELENA is on its way… n ELENA installation: two main stages (baseline) 1. 2. 1 Jan 2015 – July 2016: Main ring 1. 1 Infrastructure + source 1. 2 Injection line (from AD) 1. 3 Ring machine elements Dec 2016 – Oct 2017: Transfer lines to experiments + corresponding infrastructure (mainly cabling) 2 F. Butin / ELENA collaboration
Infrastructure installation is nearing completion: ü Extensive cleaning campaign performed, kicker generators relocated to bdg 393 ü Survey network complete ü Metallic support structures complete (central and lateral platforms, racks platform) ü Cooling demineralized water distribution complete ü Compressed air network complete ü AD racks re-organization and re-cabling complete F. Butin / ELENA collaboration
Infrastructure installation (2) Infrastructure installation is nearing completion: ü Signal cables and connectors installation complete ü AC powering to racks and around ring complete ü Machine elements supports installed and aligned ü Injection kicker generator commissioned ü Shielding elements installation started. Optical fibers installation (mid Nov) F. Butin / ELENA collaboration ü IT connections (mid Dec)
Infrastructure installation (3) Infrastructure items remaining to be installed: Ø Access control systems (mid Jan 2016) Ø Racks and services (supports, cooling, magnets DC cabling) in AD power room (Dec 2015 – March 2016) Ø Power converters (March – May 2016) F. Butin / ELENA collaboration
ELENA machine elements Injectio n kicker magnet Longitudinal Pick-up Tune measurement Septu m magnet Ion switc h SEM detector EJECTION Electro n cooler BTV EJEC N RF Cavity TIO Ion e sourc N O TI C JE IN Electrostatic ejection kicker Electrostati c quadrupole Quadrupol e magnets Dipole magnet F. Butin / ELENA collaboration Scrap er
ELENA machine elements Already in place: ü Injection Septum magnet, connections and cooling ü Ion switch (used for injection from ion source) installed and will be tested with source in February ü Ion source hardware including power supply, HV cables and protection hood. F. Butin / ELENA collaboration
ELENA machine elements (2) And much more to come: Ø Injection Kicker magnet tank production complete, being vac tested, HV tests planned, instal mid March Ø Main bending magnets manufactured for Jan 2016, Installation section 3+6 mid Feb, then 1 per month Ø TL bending magnets ready, install 20 Jan Ø All other magnets being manufactured, last install 17 May, except last 2 correctors (mid July) F. Butin / ELENA collaboration Ø BPM’s built, being vacuum tested (1 per
ELENA machine elements (3) Ø LPU’s being assembly being finalized at workshop, install mid May Ø Scraper vacuum tested, final assembly in progress. New tests needed after assembly, install end June Ø BTV (on the ring) being vacuum tested, issues with push-pull… Install April Ø BTV on injection line LNI to be cleaned and vac tested, install end Feb Ø Electron cooler being manufactured, delivery date TBC, vacuum system production starting, install July, commissioning can start with F. Butin / ELENA collaboration
ELENA machine elements (4) Ø Electrostatic fast deflectors NEG coated, install Feb Ø Electrostatic quadrupoles ready, install Feb Ø SEM tank prototype vacuum tested, will be fully equipped and tested with ion source in Feb Ø RF cavity in production, vacuum tests planned in march, install mid April Ø Tune measurement production started, install April. Ø Vacuum components either purchased, procured or being manufactured / tested / F. Butin / ELENA collaboration
Schedule overview Infrastructure F. Butin/ ELENA collaboration Machine. Commissionning
Conclusions Ø Infrastructure installation complete, in time Ø Installation of injection line inside AD shielding being performed during YETS: major milestone Ø Machine elements production and testing is ongoing, some delays but no impact yet Ø Machine elements installation has started, pace will increase as of February F. Butin / ELENA collaboration
Conclusions (2) Ø Planning still in line with ring commissionning in July 2016 Ø Transfer lines installation slot still pending (Dec 2016 – Sept 2017 or LS 2…) Ø Aegis removal ECR awaited… Ø GBAR exp area being re-organized, bunker installation to start in Feb, online monitoring of impact on AD magnets location Ø ALPHA and ASACUSA exp areas enlargement proposed, financing to be secured, participation of EP department expected F. Butin/ ELENA collaboration