ELENA Installation followup 25062015 Worksite followup Scrapers update

  • Slides: 11
Download presentation
ELENA Installation follow-up 25/06/2015 • Worksite follow-up • Scrapers update

ELENA Installation follow-up 25/06/2015 • Worksite follow-up • Scrapers update

Worksite follow-up • EN-EL-BT works: • Clean Up of the rack area started •

Worksite follow-up • EN-EL-BT works: • Clean Up of the rack area started • Cable trays installation in progress (Work due to finish by the end of next week) • Integration of the cable trays in the new platform to be clarified

Worksite follow-up • Installation of concrete block around the rack platform: • Access to

Worksite follow-up • Installation of concrete block around the rack platform: • Access to the rack platform to be done

Worksite follow-up • General cleaning of the rack platform to be done before 13

Worksite follow-up • General cleaning of the rack platform to be done before 13 th of July

Worksite follow-up • Survey : – • Survey completed the ground marking on Thursday

Worksite follow-up • Survey : – • Survey completed the ground marking on Thursday • LNR, LNI, LNS, LNE 00 are marked • LNE 00 line is marked Remaining work : – – Measure of height to be done. Upgrade of the survey network once the surrounding shielding will be installed

Worksite follow-up • Cleaning of Gbar area: Moving of the big ASACUSA equipment planned

Worksite follow-up • Cleaning of Gbar area: Moving of the big ASACUSA equipment planned today

Worksite follow-up • Time Lapse movie : – A webcam is now install on

Worksite follow-up • Time Lapse movie : – A webcam is now install on site – Access can be granted on request to Erwan Harrouch

General information : - Worksite follow-up The crane cannot be reinstalled as it is

General information : - Worksite follow-up The crane cannot be reinstalled as it is : Reduce the maximum load or the length of the crane. The path to BASE has been cleared. It should remain like this in the future Warning : The PR 191 crane will be unavailable from Friday 26 th to Wednesday 1 st of July

Reminder Get in contact with Erwan Harrouch or Francois Butin before installing anything

Reminder Get in contact with Erwan Harrouch or Francois Butin before installing anything

Updated schedule for the coming weeks

Updated schedule for the coming weeks

Worksite follow-up • Activities for the week 27: – Cleaning of GBAR area –

Worksite follow-up • Activities for the week 27: – Cleaning of GBAR area – E. Harrouch (EN-MEF) – Path to the rack platform- F. Bais (EN-MEF)? – Drilling for the mechanical supports – Antti Kolehmainen (EN-MEF) – Installation of the ion switch and source support – Antti Kolehmainen (EN-MEF) – Cable trays installation– R. Necca (EN-EL)