ELENA Installation follow-up 09/07/2015 • Worksite follow-up E. HARROUCH EN-MEF-EBE
Worksite follow-up • EN-EL-BT works: • Clean Up of the rack area started • Cable trays installation in progress • Grounding of the cable tray in progress • General cleaning of the rack platform to be done before the 20 th of July E. HARROUCH EN-MEF-EBE
Worksite follow-up • Mechanical support installation : – Drilling started : About 40/200 holes drilled – False floor modified for LNS support – Could finish by the end of next week E. HARROUCH EN-MEF-EBE
Worksite follow-up • Mechanical support installation : – Installation of LNS support and septa support will start on Monday. – Vacuum support drilling? E. HARROUCH EN-MEF-EBE
Worksite follow-up • Source tests : Damaged insulator replaced by new one. E. HARROUCH EN-MEF-EBE
General information : - Worksite follow-up The crane cannot be reinstalled as it is : Reduce the maximum load or the length of the crane. Calculation in the hands of HSE, drilling will be done by J. Sakkinen team. The path to BASE has been cleared. It should remain like this in the future E. HARROUCH EN-MEF-EBE
Updated schedule for the coming weeks E. HARROUCH EN-MEF-EBE
Worksite follow-up • Activities for the week 29: – Cleaning of GBAR area – E. Harrouch (EN-MEF) – Drilling for the mechanical supports – Antti Kolehmainen (EN-MEF) – Installation of the ion switch, source and septum support – Antti Kolehmainen (EN-MEF) – Cable trays installation– R. Necca (EN-EL) E. HARROUCH EN-MEF-EBE