EASTERN CAPE DEPARTMENT OF HOUSING PRESENTATION TO SELECT COMMITTEE ON FINANCE 13/02/08 HOUSING EXPENDITURE

EASTERN CAPE DEPARTMENT OF HOUSING PRESENTATION TO SELECT COMMITTEE ON FINANCE 13/02/08 HOUSING EXPENDITURE FOR THE FIRST 9 MONTHS 2007/08 FINANCIAL YEAR MEC : HLTA: Mrs. T Xasa

Key challenges Practical realities on the ground STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION

Key challenges Practical realities on the ground STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION

 Poor planning Approval of projects that are not ready Land issues 14/02/2022 STRICTLY

Poor planning Approval of projects that are not ready Land issues 14/02/2022 STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION 3

 Lean pool of established contractors attracted to low cost housing resulting in retendering

Lean pool of established contractors attracted to low cost housing resulting in retendering Inability of bidders to produce NHBRC certificates Slow NHBRC project and home enrollment Material Supplies 4

 Slow take off of the established contractor construction Re tendering for the emergency

Slow take off of the established contractor construction Re tendering for the emergency housing NHBRC slow start on the rectification programme EIA 5

HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENT 1 st 9 MONTHS OF 2007/08 6

HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENT 1 st 9 MONTHS OF 2007/08 6

CASH FLOW FORECASTS vs. EXPENDITURE IRO PROJECTS PER DISTRICT - THE 1 ST 9

CASH FLOW FORECASTS vs. EXPENDITURE IRO PROJECTS PER DISTRICT - THE 1 ST 9 MONTHS OF 2007/8

ACTUAL OUTCOME HOUSING CONDITIONAL GRANT 2007/08 HOUSING ALLOCATION 2007/08 R 1, 052 , 554

ACTUAL OUTCOME HOUSING CONDITIONAL GRANT 2007/08 HOUSING ALLOCATION 2007/08 R 1, 052 , 554 LESS: FUNDS SURRENDERED REVISED ALLOCATION 2007/08 R R 543, 078 509, 476 R R 155, 219 354, 257 LESS: EXP. AS AT END DECEMBER 2007 BALANCE OF FUNDS – 31 Dec. 2007 8

HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENT NOV & DEC - 2007/08 (AFTER REVISION) 9

HOUSING EXPENDITURE - PER SUBSIDY INSTRUMENT NOV & DEC - 2007/08 (AFTER REVISION) 9

 Alternative Military sanitation and energy Veterans Programme Inclusionary Delivery housing Intensify on social

Alternative Military sanitation and energy Veterans Programme Inclusionary Delivery housing Intensify on social housing rural housing AREAS TO BENEFIT FROM R 500 M 14/02/2022 STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION 10

HOUSING CONDITIONAL GRANT - 2007/08 CASH FLOW FORECAST – 4 TH QUARTER JANUARY 2008

HOUSING CONDITIONAL GRANT - 2007/08 CASH FLOW FORECAST – 4 TH QUARTER JANUARY 2008 FEBRUARY 2008 146, 816 MARCH 2008 136, 042 TOTAL R R 71, 399 R R 354, 257 11

 Land acquisition for inclusive housing ◦ The department is currently busy with Audit

Land acquisition for inclusive housing ◦ The department is currently busy with Audit of well located & suitable land for Housing Development. Negotiations are already in process for land in identified areas e. g. Maletswai & Buffalo City Municipalities 192 units in Amalinda (SOHCO) have had their consents signed and are in the process of taking transfer 2007/8 Non Financial Performance 14/02/2022 STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION 12

 Rural Housing Summit and launch of innovation hub 37 new projects and 16

Rural Housing Summit and launch of innovation hub 37 new projects and 16 385 housing subsidies approves 2 Locrete Technology show houses from Kuwait completed and packaged for shipping 14/02/2022 STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION 13

 6342 sites serviced 4569 houses completed and 3000 at various stages of completion

6342 sites serviced 4569 houses completed and 3000 at various stages of completion 3519 transfers registered 14/02/2022 STRICTLY CONFIDENTIAL - NOT FOR CIRCULATION 14

Progress on the Turn Around Plan : Operation Thunderstorm: n Various Housing Projects Nine

Progress on the Turn Around Plan : Operation Thunderstorm: n Various Housing Projects Nine projects allocated to established contractors n Construction commenced in all nine projects n Expenditure kicked in December 15

Progress on the Turn Around Plan : Proactive Planning for 2008/9 n Department Driven

Progress on the Turn Around Plan : Proactive Planning for 2008/9 n Department Driven projects n Tenders for 14 projects translating into 5191 units now under adjudication n Appointments to be made by end Feb and contracting and site establishment planned for March 16

Progress on the Turn Around Plan : Proactive Planning 2008/9 Municipal Driven projects ◦

Progress on the Turn Around Plan : Proactive Planning 2008/9 Municipal Driven projects ◦ Tender process completed for 15 projects amounting to 8461 housing units with a value of R 329, 082, 134 ◦ Awarding of tender during February 17

Progress on the Turn Around Plan : Capacity Enhancement The appointment of a Rapid

Progress on the Turn Around Plan : Capacity Enhancement The appointment of a Rapid Delivery Team (multi disciplinary) to augment the capacity of the department in various disciplines and assist with fast tracking delivery has been done and the team is in operation. 3 GM and 2 Senior Managers appointed ◦ 39 positions advertised 16 are technical 18