East Hall under construction - 1962 Planning East Area : Closure Simulations B. Raë

East Hall under construction - 1962 Planning East Area : Closure Simulations B. Raë

Simulation introduction • 2 Scenarios • Back in June (most optimistic) • Back in

Simulation introduction • 2 Scenarios • Back in June (most optimistic) • Back in September Last updated planning before closure • Try to finish Primary/mix Area as soon as possible (T 8 priority) • PS wait for information • Full Linear & Project PDF on indico. B. Raë 02. 04. 2020 EAR : Closure Simulation 2

Back in June Scenario • Beam commissioning July 2021 • DC Cabling middle of

Back in June Scenario • Beam commissioning July 2021 • DC Cabling middle of Christmas. • Primary critical Path • Need Split cable tray and signal pulling work • B. 352 as to be seen with PS plan. B. Raë 02. 04. 2020 EAR : Closure Simulation 3

Back in June Scenario • B. 157 • Restart with shielding could be exceptionally

Back in June Scenario • B. 157 • Restart with shielding could be exceptionally anticipate ? • EN-CV and EN-HE very busy move the ventilation installation ? • B. 352 • CR 200 Ready can be install directly • Q 120 what is the delay to have it after the restart ? • B. 251 • Start with installation of Power Converter Zone 1 ok for TE-EPC ? • EN-EL need some delay to restart (AC 1 week & DC some preparation to be done). B. Raë 02. 04. 2020 EAR : Closure Simulation 4

Back in September Scenario • Beam commissioning November 2021 • No Physics for 2021

Back in September Scenario • Beam commissioning November 2021 • No Physics for 2021 • Support levelling in middle of Christmas • B. 352 as to be seen with PS plan. • WIC installation has to be reschedule. B. Raë 02. 04. 2020 EAR : Closure Simulation 5

Back in September Scenario • B. 157 • Restart with shielding could be exceptionally

Back in September Scenario • B. 157 • Restart with shielding could be exceptionally anticipate ? • EN-CV even more busy move the ventilation installation and commissioning installation ? • B. 352 • Will depend a lot of the PS plan. • B. 251 • Start with installation of Power Converter Zone 1 ok for TE-EPC ? • WIC installation has to be postponed later. TE-MPC • EN-EL still need same time after restart B. Raë 02. 04. 2020 EAR : Closure Simulation 6

Summary • June scenario will allow physics in 2021. • B. 352 and B.

Summary • June scenario will allow physics in 2021. • B. 352 and B. 157 critical path • Transport resources to be confirmed during summer. (possible delay). • September scenario will not allow physics in 2021. • More time due to the YETS 2022. • Beam commissioning still can be done in 2021. • CLOUD run without physics in 2021 ? • All scenario reaming point to be discussed. • PS plan after closure. • B. 157 EN-EL activities split. • better time estimation • Magnet readiness. • WIC installation • Please have a look to the two scenarios and let me know if there is issues. B. Raë 02. 04. 2020 EAR : Closure Simulation 7

Questions ? B. Raë 02. 04. 2020 EAR : Closure Simulation 8