 East Hall under construction - 1962 East Area Renovation Project team meeting #4

East Hall under construction - 1962 East Area Renovation Project team meeting #4 Sébastien Evrard / EN-EA, 18 -11 -2016

AGENDA • WP meetings • User requirement documents • Feedbacks from LS 2 days

AGENDA • WP meetings • User requirement documents • Feedbacks from LS 2 days • Cost and Schedule review • WBS and PLAN S. Evrard, 18 -11 -2016 Project Team #4 2

WP meetings • Inputs for • EQUIPMENT/SYSTEM CONCERNED: detailed list of items • Schedule

WP meetings • Inputs for • EQUIPMENT/SYSTEM CONCERNED: detailed list of items • Schedule • Cost/Budget • Procurement • Manufacturing ü Thursday 18 August EN-EA ü Thursday 03 November BE-BI/OP ü Thursday 25 August BE-BI ü Thursday 03 November HSE/RP ü Thursday 01 September TE-MSC ü Thursday 03 November EN-EA (III) ü Thursday 15 September TE-EPC ü Thursday 04 November SMB-SE (II) ü Thursday 22 September EN-STI ü Thursday 17 November BE-ICS (II) ü Thursday 29 September EN-CV • Tuesday 22 November BE-CO ü Thursday 29 September SMB-SE Then CSR preparation meeting on Tuesday 29 th November ü Friday 30 September EN-EL • Logistics • Design/integration ü Wednesday 5 October EN-EA (II) • Interfaces: impact on other items (cabling, cooling, control, …), removal, waste. ü Friday 7 October EP-Logistics ü Monday 10 October EN-ACE • Resources (manpower & budget) ü Thursday 20 October BE-ICS • Risk assessment ü Thursday 13 October CLOUD ü Thursday 20 October IT-CS • Safety (hardware, operation, safety file) • AOB S. Evrard, 18 -11 -2016 Project Team #4 3

User requirement documents • Cooling and Ventilation : S. Evrard • Electricity : S.

User requirement documents • Cooling and Ventilation : S. Evrard • Electricity : S. Evrard (DC), M. Lazzaroni (AC) • Magnets : M. Lazzaroni üBeam obstacles & targets: M. Lazzaroni üVacuum : E. Harrouch üNetwork : E. Harrouch • Machine protection: S. Evrard üBeam parameters: J. Bernhard • Documents should be ready by mid-November… S. Evrard, 18 -11 -2016 Project Team #4 4

[EN-EL] AC Power Inventory Template sent to: Group Replies EN-CV BE-BI BE-CO BE-ICS EN-EL

[EN-EL] AC Power Inventory Template sent to: Group Replies EN-CV BE-BI BE-CO BE-ICS EN-EL EN-EA EN-HE EN-STI IT-CS RP ALICE users CHARM users IRRAD users CLOUD users ü

Beam line layout change Primary Beam Parameter Proton beam momentum [Ge. V/c] Maximum flux

Beam line layout change Primary Beam Parameter Proton beam momentum [Ge. V/c] Maximum flux per PS spill Maximum # spills per super-cycle Duration of super-cycle [s] Maximum # protons per second Maximum number of days per year Assumed efficiency Maximum number of super-cycles per year Maximum number of protons per year Minimum spot size [mm RMS] LS 2 Days Value 24 5 1011 6 45. 6 6. 7 1010 200 90% 340, 000 1. 0 1018 ~5 x 5 Head Material 1 Be W 2 Al Be Length (mm) 200 3 100 Diameter (mm) 10 + Al case 10 3 3 Al 200 4 Air - 5 Al 20 10 10 6

LS 2 days: good feedbacks from groups! Talk given: https: //edms. cern. ch/document/1730967/1 BE-BI

LS 2 days: good feedbacks from groups! Talk given: https: //edms. cern. ch/document/1730967/1 BE-BI TE-EPC EN-HE EN-EL S. Evrard, 18 -11 -2016 BE-ICS TE-MPE Project Team #4 SMB-SE EN-ACE 7

Cost & Schedule review: Motivation • The detailed study of the various work packages

Cost & Schedule review: Motivation • The detailed study of the various work packages (WPs) has now progressed; the material estimates for the CERN contributions have been iterated in dedicated WP meetings, leading to more precise updates. • This first review is called to assess the situation and to validate the baseline scenario. • Prior official approval of the project baseline, the panel members are kindly asked to review the following issues: Scope - cost – funding scheme – manpower – schedule – risks and uncertainties – additional options/synergies. S. Evrard, 18 -11 -2016 Project Team #4 8

Review panel membership • Date: December 8 th in B. 530/R-030 • CSR mandate

Review panel membership • Date: December 8 th in B. 530/R-030 • CSR mandate available in EDMS 1727829 • Panel membership: • Rende Steerenberg (BE-OP) (Chairman) • Christoph Rembser (EP-ADE), • Henric Wilkens (EP-ADE), • Luigi Serio (EN-DHO), • Luigi Scibile (SMB-SE), • Sylvie Prodon (FAP-RPC), • Jean-Philippe Tock (TE-MSC). S. Evrard, 18 -11 -2016 Project Team #4 9

Organization of the Review • The morning session will review the overall project and

Organization of the Review • The morning session will review the overall project and work package status, as well as include dedicated activity presentations by the group responsible and specialists. • The closed afternoon session will allow the review team to prepare and discuss the draft recommendations that can then be discussed together with the project team at the end of that day, allowing to collect further information if required. • The final recommendations of the Review Panel will be submitted in a written report within two weeks from the review to the EN Department Head and presented to the IEFC in early 2017. S. Evrard, 18 -11 -2016 Project Team #4 10

Agenda (proposal) • 8. 45 -9. 00 Welcome and Introduction • 9. 00 -9.

Agenda (proposal) • 8. 45 -9. 00 Welcome and Introduction • 9. 00 -9. 30 Motivation and physics justification for the renovation • 9. 30 -10. 45 Scope of the renovation • • Power converters Magnets Civil Engineering Other workpackages • 10. 45 -11. 00 Coffee break • 11. 00 -11. 45 Resources • 11. 45 -12. 30 Planning • 12. 30 -14. 00 Lunch break • 14. 00 -16. 30 Closed session (reviewers) • 16. 30 -17. 30 Summary S. Evrard, 18 -11 -2016 Project Team #4 11

CSR preparation • Week 47: each Project Engineer will receive a summary of •

CSR preparation • Week 47: each Project Engineer will receive a summary of • Resources estimates (Staff, FSU, missing) • Budget • Planning • Week 48: one day preparation meeting (Tuesday 29 th November) • Doodle: http: //doodle. com/poll/rhfx 8 xzr 4887 gff 8 • Please book a slot ! • Week 49 : • Monday 05 December AM rehearsal for all speakers • Thursday 08 December : CSR S. Evrard, 18 -11 -2016 Project Team #4 12

WBS and PLAN tool • Extensive WBS available in EDMS 1730966 • Approved activities

WBS and PLAN tool • Extensive WBS available in EDMS 1730966 • Approved activities created in Plan tool S. Evrard, 18 -11 -2016 Project Team #4 13

Next Project Team meetings • The next Project team meetings are going to take

Next Project Team meetings • The next Project team meetings are going to take place on: • Friday 23 September, 15. 00 -16. 30 in B. 30/7 -010 • Friday 21 October, 15. 00 -16. 30 in B. 30/7 -010 • Friday 18 November, 15. 00 -16. 30 in B. 30/7 -010 • Friday 16 December, 15. 00 -16. 30 in B. 30/7 -010 • CSR outcome • CSR date: December 8 th S. Evrard, 18 -11 -2016 Project Team #4 14

Organizational tools • EDMS: https: //edms. cern. ch/project/CERN-0000169544 • Indico: https: //indico. cern. ch/category/8407/

Organizational tools • EDMS: https: //edms. cern. ch/project/CERN-0000169544 • Indico: https: //indico. cern. ch/category/8407/ • E-groups: • East-area-renovation-project-team@cern. ch : members of the Project team. • East-area-renovation-core-team-project@cern. ch: members of the Project core team. • Share. Point: https: //espace. cern. ch/East-Area-Renovation-Project • dfs: https: //dfsweb. cern. ch/dfsweb/Services/DFSBrowser. aspx/ Workspaces/e/East. Area. Renovation/ S. Evrard, 18 -11 -2016 Project Team #4 15

Thanks for your attention! 16