East Hall under construction 1962 East Area Renovation
- Slides: 9
East Hall under construction - 1962 East Area Renovation Project #6 EYETS activities Aboubakr Ebn Rahmoun / EN-EA, 23 -09 -2016
Injector & East Area Schedule A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 2
Activities EYETS & run 2017 b. 157 b. 251 • Inventory facade building • Preparation • Cooling pipe, • Cleaning and storage • Extractor H 2, ventilation • Trench inspection • Magnet cables from 263 • Beam Lines • Inventory F 61, done • Primary area, RP survey week 7 • Experimental areas A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 3
Activities during EYETS 8 set • b. 157 Inside • Water cooling system unused, (140 m) • Need to remove manifolds, • Possiblility to close the sector during EYETS • From 17/02 to 11/04, b. 355 water off Action: EN-CV, EN-EA A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 4
Activities during run 2017 b. 157 Outside • Obsolete items • Extractor H 2 • Maintenance structure • Protection Dewar • Gas & water exhaust Action: EN-CV, EN-EA A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 5
Cladding exchange : Inventory • Renovation interferences • Exhaust of Irrad&Charm • Air Inlet, x 8 • Magnet cable from 263 • Used during run • Meeting with SMB, futur contractor & EN-EA to be organized A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 6
Beam lines • F 61’s inventory A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 7
Preparation b. 251 • New integration of power supply building • • TE-EPC • Store and remove old power supply EN-EA • Integration and regrouping b. 263 in b. 251 • SMB-SE • Intervention during LS 2 Now After LS 2 A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 8
Thanks for your attention! A. Ebn Rahmoun, 10 -02 -2017 Project Team #6 9