East Hall renovation East Hall Renovation : Civil Engineering works Stewart Mcilwraith – Charly Gasnier (SMB-SE) B. 157 - 28/04/2017 S. Mcilwraith – C. Gasnier

Contents 1. 2. 3. 4. 5. 6. CE works overview C&S review response Constraints Advancement on objectives Budget Conclusions B. 157 - 28/04/2017 SMB-SE

1. CE works overview 1 2 • Work zone 1: • 260 m 2 of glazing • 4600 m 2 of suspended ceiling • Roof waterproofing verification • Work zone 2: B. 157 - 28/04/2017 SMB-SE • 1250 m 2 of glazing • 1200 m 2 of Eternit façade cladding

1. CE works overview Glazing to replace 250 m 2 Ceiling panels to replace 4600 m 2 Roof fixations & gutter integrity checks Suspended scaffolding (~5000 m 2) B. 157 - 28/04/2017 SMB-SE

1. CE works overview Fibre-cement cladding to be replaced (1200 m 2) Glazing to replace(1250 m 2) Note: Possibility to reduce mid-level glazing to be investigated B. 157 - 28/04/2017 SMB-SE

2. 1 Multicriteria analysis Baseline • 2017 (Q 4) to 2019 (Q 1) Alternative : • Facades during 2018 • Under roof works moved after LS 2 B. 157 - 28/04/2017 SMB-SE

2. 1 Multicriteria analysis BASELINE Advantages Disadvantages ALTERNATIVE -Project objectives met 2018: • Thermal insulation improved • Unsafe asbestos removed from building • Building rendered waterproof • Optimisation of natural light -Duration of CE works minimised -Asbestos legislation known -Smaller space needed for worksite installations -Coactivity with Physics (mitigated through zoned planning) -Larger space needed for worksite installations (mitigated through controlled delivery schedule) -Project objectives met (2021? ) -Coactivity with Physics (possibility to mitigate? ) -Risk of asbestos legislation evolution -Cost increase (site mobilisation x 2, demobilisation x 2, etc. ) -Space for worksite installations required twice B. 157 - 28/04/2017 SMB-SE

2. 2 CE project planning B. 157 - 28/04/2017 SMB-SE

3. 1 Worksite Planning and coordination 2 1 Sh ield ed Are a Sh ield 5 6 3 ed Are a 4 Suspended scaffoldings zoned planning Additional safety measures can be taken above sensitive area Shielded area (no co-activity with Physics) Sensitive area (co-activity with Physics) B. 157 - 28/04/2017 SMB-SE

3. 1 Worksite Planning and coordination • Impact on Physics minimised: Optimisation of scaffolding installation and removal above sensitive zones during YETS/LS 2. Co-activities with Physics to coordinate B. 157 - 28/04/2017 SMB-SE

3. 2 Prioritised site zones 750 m 2 available on North Side 750 m 2 available on South Side • One entrance (North or South) to storage building between 156/157 will remain accessible at all time • No superposition of site installations (North/South) • 10 m passage for trucks surrounding south site installations These zones are prioritised but additional space may be required B. 157 - 28/04/2017 SMB-SE

3. 3 Constraints • Facade services inventory established, confirmation required that items will be removed prior to CE works. B. 157 - 28/04/2017 SMB-SE

4. Advancement on objectives • Window optimisation study: Reduction of high windows on south façade – reducing afternoon direct sunlight on CLOUD • False ceiling/Roof - Parallel analyses of: • Ceiling only option (false ceiling panel removal and replacement and roof sheet and gutter waterproofing integrity check) • Roof + Ceiling option (false ceiling panel and roof removal and replacement with single insulated exterior roof) Roof + Only option: Possible advantage to planning and cost neutrality (TBC through architectural studies) • Site optimisation: EA delivery schedule on Wednesday taken into account for site functioning. B. 157 - 28/04/2017 SMB-SE

5. Budget • Total CE budget following SMB preliminary study (no modification since C&S review 08/12/16): 2. 48 MCHF (+/- 30%) Available budget (update 06/04/17): 2. 24 MCHF • Architectural study ongoing: Preliminary design estimation (+/- 20%) : 06/06/17 Tender design estimation (+/- 10%) : xx/08/17 B. 157 - 28/04/2017 SMB-SE

6. Conclusions • From a technical point of view, executing CE works before LS 2 is advantageous • CE advancing in line with Baseline Schedule No contingency in planning until FC 12/17 • Co-activity with Physics minimised through refined zonal planning • Disruption to parking and building access reduced by optimising delivery schedules • Obsolete façade services must be removed prior to CE works. • CE works optimisation studies underway: Cost estimate Planning Site installations Building envelope proposals • Current Cost estimate: 2. 48 MCHF. Refined estimate in the coming months. B. 157 - 28/04/2017 SMB-SE

Questions B. 157 - 28/04/2017 SMB-SE

B 119 B. 157 - 28/04/2017 SMB-SE

B 119 B. 157 - 28/04/2017 SMB-SE

B 119 B. 157 - 28/04/2017 SMB-SE

B 119 B. 157 - 28/04/2017 SMB-SE

Budget & resources Budget global = CHF 2. 4 M (-20%/+25%) • Resources = 2 FTE’s (1. 5 staff / VIA + 0. 5 FSU) • B. 157 - 28/04/2017 SMB-SE
Renovation east youtube
Hblsd
Edsgn 100 psu
Civil rights webquest
Pele unsw
Hse orientation
Civil engineering risk assessment example
Tam grouting
What is formwork in civil engineering
Introduction to civil engineering
Role of civil engineering
Gis applications in civil engineering
Czech technical university in prague civil engineering
House civil engineering drawing
Bisection method application in civil engineering
Umn civil engineering
Kambiz farahmand
Retaining wall in civil engineering
What is roominess in civil engineering
Civil engineering applications of ground penetrating radar
Integrated design project civil engineering
Civil engineering faculty