Earned Value Management theory and its application on

  • Slides: 37
Download presentation
Earned Value Management theory and its application on practice at CERN and JINR. Dmitry

Earned Value Management theory and its application on practice at CERN and JINR. Dmitry Kekelidze Software Engineer JINR – LIT/ CERN - GS-AIS

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

What is EVM? EVM is the project management tool. . . Are we there

What is EVM? EVM is the project management tool. . . Are we there yet? How much longer before we’ve arrived? What can we do about it?

EVM is Ø performance measurement how am I doing against my baseline plan? Ø

EVM is Ø performance measurement how am I doing against my baseline plan? Ø performance management what do I need to do to bring the project in on cost and schedule?

Example: making this presentation Ø Preparation • Research Topic • Decide on Structure Ø

Example: making this presentation Ø Preparation • Research Topic • Decide on Structure Ø Make Slides • EVM Basics • EVM Advanced • NICA Intro • Conclusion Ø Finishing up • Trial Presentation • Implement Feedback

Project: making the presentation Research Presentation template Start slides EVM Basics EVM Advanced Agenda

Project: making the presentation Research Presentation template Start slides EVM Basics EVM Advanced Agenda Conclusion NICA Intro Slides ready cost Reshuffle Dry run time

What is this mysterious Earned Value ? What is an honest measure for what

What is this mysterious Earned Value ? What is an honest measure for what is achieved?

Project: making the presentation Research Presentation template Start slides EVM Basics EVM Advanced Agenda

Project: making the presentation Research Presentation template Start slides EVM Basics EVM Advanced Agenda Conclusion NICA Intro cost Slides ready Reshuffle Dry run time

EVM Concepts Main metrics : PV - Planned Value The portion of work expected

EVM Concepts Main metrics : PV - Planned Value The portion of work expected to be completed at a given date, times the authorized budget allocated to carry out that work EV - Earned Value The value of completed work expressed in terms of the budget assigned to that work AC - Actual Cost The costs actually incurred and recorded in accomplishing the work performed

How is our project doing? $ Budget Planned Value Cost Actual Cost Achievement Earned

How is our project doing? $ Budget Planned Value Cost Actual Cost Achievement Earned Value now • Are we ahead or behind schedule? • Are you getting value for money? • Did you spend money on the right things? time

What happens? $ Planned Value Actual Cost Earned Value now Underspending but. . .

What happens? $ Planned Value Actual Cost Earned Value now Underspending but. . . time

What happens ? $ Planned Value Earned Value Actual Cost now Underspending but. .

What happens ? $ Planned Value Earned Value Actual Cost now Underspending but. . . time

EVM Concepts $ BAC: Budget At Complete PMR Project Management Reserve PV SV <

EVM Concepts $ BAC: Budget At Complete PMR Project Management Reserve PV SV < 0 AC CV = EV – AC Cost Variance SV = EV – PV Schedule Variance EV project start now project end SV > 0 CV < 0 CV > 0 time

Earned Value: Cheat Sheet Schedule Variance SV = EV–PV In currency. Negative means delay

Earned Value: Cheat Sheet Schedule Variance SV = EV–PV In currency. Negative means delay Schedule Performance Index SPI = EV/PV < 1 means delay Cost Variance CV = EV-AC In currency. Negative means overcost. Cost Performance Index CPI = EV/AC < 1 means overcost Estimate At Completion EAC = BAC / CPI Forecast final cost To Complete Performance Index TCPIBAC = (BAC-EV)/(BACAC) Can we catch up?

Estimated Cost at Completion $ EAC now time

Estimated Cost at Completion $ EAC now time

Benefits of EVM Ø Requires development of integrated baseline Results in better project definition

Benefits of EVM Ø Requires development of integrated baseline Results in better project definition and planning Ø Early identification of trends and problems Ø Accurate picture of project status Cost, schedule, and technical segregation of schedule and cost variances Ø Projection of final costs Ø Project control by the team Enables project manager to make informed decisions based on facts Ø Results in successful projects On time, on cost

Example: software development Requirement Architecture Design Code Testing 100 h 200 h 100 h

Example: software development Requirement Architecture Design Code Testing 100 h 200 h 100 h

Example: execution plan Task Month 1 Requirements (100 h) S------F Architecture (100 h) Design

Example: execution plan Task Month 1 Requirements (100 h) S------F Architecture (100 h) Design (100 h) Code (200 h) Testing (100 h) Month 2 Month 3 Month 4 Month 5 Month 6 Status at end of Month 5 Complete, Spent 100 h S----PF Complete, Spent 120 h --F PS-S-PF Complete, Spent 125 h --F PS----S- 25% Complete, Spent 70 h -----PF PS---PF Not yet started

At the end of Calculation Month 5, what is? PV 100 + 200 Answer

At the end of Calculation Month 5, what is? PV 100 + 200 Answer EV 100 + 50 350 h AC 100 + 125 + 70 415 h BAC CV 100 + 200 + 100 350 - 415 600 h -65 h CPI 350 / 415 84% SV 350 - 500 -150 h SPI 35, 000 / 50, 000 70% IEAC 600/0. 84 711 h TCPI (600 -350)/(600 -415) 135% 500 h

PMBOK

PMBOK

Terminology Ø WBS: Work Breakdown Structure, hierarchical list of all the activities to be

Terminology Ø WBS: Work Breakdown Structure, hierarchical list of all the activities to be performed to complete the project. Ø Workunits: The “Leaves” of the WBS tree. Activity small in size/duration, under responsibility of one person. Ø Workunits use Resources (money, people) to produce Deliverables

Where can EVM be Applied? EVM suitable for projects that have: • Clear definition

Where can EVM be Applied? EVM suitable for projects that have: • Clear definition of work scope • Project schedule range from a few months to many years • Small to very large cost

What is a large-scale project? • Technically complex and demanding, i. e. that cannot

What is a large-scale project? • Technically complex and demanding, i. e. that cannot be fully specified in the frontend phase; • Long makespan: economic effects like inflation • Involving many contributors, contractors, suppliers. . . i. e. many activities that are outsourced, resultoriented.

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

NICA

NICA

NICA Is NICA large-scale project? Ø Work planned for period from year 2012 till

NICA Is NICA large-scale project? Ø Work planned for period from year 2012 till 2017 Ø Estimated cost is more than 100 M $ Ø Tasks to complete: • General Infrastructure • Accelerator • MPD Detector Ø All the work have to be well coordinated

LHC Accelerator and Detectors

LHC Accelerator and Detectors

Project audit of 2001 § 18% overspend announcement … only § Technical Coordinator →

Project audit of 2001 § 18% overspend announcement … only § Technical Coordinator → “the project is behind schedule” § Project Administrator → “the project is under-running” § LHC Team: not is position to demonstrate that the project could be completed within allocated budget! Member States asked the LHC Project Management to set up a formal Project Control System

The key requirements §EVM-based project control system §Deliverable-oriented physical progress monitoring §Interfaced to accounting

The key requirements §EVM-based project control system §Deliverable-oriented physical progress monitoring §Interfaced to accounting systems, to get accurate information on actual costs §Excel spreadsheets to interact with DBs §Web-based

Why a D-O EVMS? An activity of the project Activity not started Progress Activity

Why a D-O EVMS? An activity of the project Activity not started Progress Activity half-wayalmost completed? done 0% Progress 50% Progress 90%! 90%-syndrome

Outcome of EVM experience… Ø Re-established trust • Cost and Schedule Review Committee: ‘world

Outcome of EVM experience… Ø Re-established trust • Cost and Schedule Review Committee: ‘world class’ • CERN management was formally congratulated by Member States • Further overruns were discussed in the context of proven project control. Ø Project culture at CERN and cost awareness of project engineers have improved.

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

Agenda Ø EVMS concepts Ø NICA project Ø EVM web-based application

Data Definition WBS Workunits Resources §Personnel §Material Deliverables • Web interface • Excel files

Data Definition WBS Workunits Resources §Personnel §Material Deliverables • Web interface • Excel files

Collaborative tool Reminders for progress reporting

Collaborative tool Reminders for progress reporting

Dynamic Reports Ø Crosstab to drill drown through the WBS structure (or other dimension…)

Dynamic Reports Ø Crosstab to drill drown through the WBS structure (or other dimension…) Ø PV, EV, AC Charts at every WBS level

Conclusion Ø Objectively measures performance of the project as it moves from project initiation

Conclusion Ø Objectively measures performance of the project as it moves from project initiation through project closure. Ø Provides early warning of potential project adverse performance. Ø Shows Opportunity associated with positive schedule variance. Ø Enables the management of risk associated with underwriting or insuring against negative schedule variance. Ø Provides a means to forecast future performance based upon past performance.

Спасибо! Dmitry. Kekelidze@cern. ch Questions?

Спасибо! Dmitry. Kekelidze@cern. ch Questions?