Earned Value Analysis the original plan € 1 € 1 € 1 BAC =

Earned Value Analysis the original plan € 1 € 1 € 1 BAC = Budget At Completion = € 5 progress at milestone 1: € 1. 50 € 2. 50 EV = € 2 Only 2 tasks; both overspent. We had planned to do € 3 of work, but only ‘earned’ € 2. Unfortunately it cost us € 4 to do it. We can use the power of EVA to forecast the future…

Earned Value Analysis If you, in the role of project manager, convince your customer

Earned Value Analysis If you, in the role of project manager, convince your customer that the project will cost xxx, and you also cost each task or major milestone along the way, then in the customer’s mind each task or milestone will be worth what you said. So if you are so poor at controlling the project that a task has cost you twice the original estimate why should the customer pay for your incompetence? This is the essence of EVA; you will only earn what the customer sees as the value of task. Many large organisations pay their contractors in this way

Earned Value Analysis – Jargon - 1 EV is Earned Value EV = €

Earned Value Analysis – Jargon - 1 EV is Earned Value EV = € 2 PV is Planned Value PV = € 3 AC is Actual Cost AC = € 4 Earned Value means the total value of the tasks we have actually completed by this time Planned Value means the total value of the tasks we had meant to complete by this time Actual Cost means the total cost we have incurred getting to this point in time From the original estimates

So What? – 1 IF: … EV is less than AC We have spent

So What? – 1 IF: … EV is less than AC We have spent more than we have earned AC is less than EV We have earned more than we have spent PV is less than EV We have earned more than we had planned PV is less than AC We have spent more than we had planned

The Graphs cost PV The Actual Cost is running ahead of the Planned Value,

The Graphs cost PV The Actual Cost is running ahead of the Planned Value, therefore the project is over budget AC EV time The Earned Value is running behind Planned Value, therefore the project is behind schedule This poor performance could have been identified here…

Earned Value Analysis – Jargon - 2 We can look at variance: CV is

Earned Value Analysis – Jargon - 2 We can look at variance: CV is Cost Variance; CV = EV - AC CV = 2 - 4 = -2 A negative variance is BAD… SV is Schedule Variance; SV = EV - PV SV = 2 - 3 = -1

Earned Value Analysis – Jargon - 3 We can extrapolate from the current position:

Earned Value Analysis – Jargon - 3 We can extrapolate from the current position: …. CPI is Cost Performance Index; CPI = EV/AC CPI = 2/4 = 0. 5 Everything we do seems to cost us twice what we had planned: … EAC is Estimate At Completion; EAC = BAC/CPI EAC = 5/0. 5 = 10 Warning: may be a naive assumption: …

So What? - 2 EAC is Estimate At Completion; EAC = BAC/CPI EAC =

So What? - 2 EAC is Estimate At Completion; EAC = BAC/CPI EAC = 5/0. 5 = 10 This is only true if all future tasks overrun at the same rate as now. If we think we have fixed the problems behind the current cost overrun then a better EAC formula is: … EAC = AC + Remaining PV EAC = AC + (BAC-EV) EAC = 4 +(5 -2) = 7 This is a much smaller EAC, but remember our premise…

Earned Value Analysis – Jargon - 4 EAC is Estimate At Completion; EAC =

Earned Value Analysis – Jargon - 4 EAC is Estimate At Completion; EAC = BAC/CPI EAC = 5/0. 5 = 10 The EAC is obviously a really important figure in the overall cost control for the project, but there is another figure that many people will want to know: … ETC is Estimate to Complete, meaning how much more money will it take to finish this project. ETC is easy to compute. ETC = EAC - AC ETC = 10 – 4 = 6

Earned Value Analysis – Jargon - 5 More extrapolation, albeit slightly more risky. We

Earned Value Analysis – Jargon - 5 More extrapolation, albeit slightly more risky. We know that every task we have finished seems to be taking longer than planned, so maybe we can infer that all future tasks will overrun their schedule by a similar amount. This means we can calculate a Schedule Performance Index, as follows: EV = € 2 PV = € 3 AC = € 4 CPI = 2/4 = 0. 5 SPI is Schedule Performance Index; SPI = EV/PV SPI = 2/3 = 0. 66 So if the original duration was 5, the new duration could be: OD/SPI = 5/0. 66 = 7. 6

Earned Value Analysis ØEVA can be a powerful tool forecasting outturn Øit requires accurate

Earned Value Analysis ØEVA can be a powerful tool forecasting outturn Øit requires accurate estimating as well as control ØIt assumes future cost performance will be similar to current Upper Control Limit 1. 2 1. 1 1. 0 0. 9 0. 8 Lower Control Limit

Classroom Practice - 1 All figures are cumulative 1. What is the CPI at

Classroom Practice - 1 All figures are cumulative 1. What is the CPI at the end of month 4 2. What is the SPI at the end of month 4 3. What is the EAC at the end of month 4 4. What is the ETC at the end of month 4

Classroom Practice - 2 All figures are cumulative 1. What is the CV at

Classroom Practice - 2 All figures are cumulative 1. What is the CV at the end of month 4 2. What is the SV at the end of month 4 3. If all the work completed in Month 4 fails quality testing, and has to be reworked in Month 5, meaning that none of Month 5’s tasks can be completed: 3 a. What is the EV at the end of month 5 3 b. What is the AC at the end of month 5 3 c. What is the CPI at the end of month 5