e. RA Project Team Meeting Project Management Plan April 23, 2002

e. RA Project Team Meeting Project Management Plan April 23, 2002

Project Management Plan w Purpose: – To describe the management processes in use by

Project Management Plan w Purpose: – To describe the management processes in use by the e. RA project w Scope: – Applies to the software development, maintenance, and operations activities conducted on the e. RA project

Goals of e. RA Project Management w Ensure that commitments made to the user

Goals of e. RA Project Management w Ensure that commitments made to the user community, the IC’s, and the Steering Committee are met with fidelity w Ensure that e. RA allocates resources in accordance with business priorities as determined by the Steering Committee w Implement modern project management processes that best serve e. RA’s advanced software engineering environment and position the project for compliance with industry standard

Project Management w New projects/new software development and major enhancements to existing software w

Project Management w New projects/new software development and major enhancements to existing software w Minor enhancements, bug fixes, software maintenance w Operations, which supports the development and maintenance of software

Project Planning w Development of the Business Plan – Describe the project – Estimate

Project Planning w Development of the Business Plan – Describe the project – Estimate cost and schedule – Estimate the WBS w Evaluation of the Business Plan – e. RA CIO, Architect, ISSO w Presentation of Business Plan to Project Team for approval

Monitor and Control Cost and Schedule w Tools – Project Central – Time Tracking

Monitor and Control Cost and Schedule w Tools – Project Central – Time Tracking System (Oracle SBS) • Cost categories • Life Cycle phase • Workflow – Contractor invoicing

Project Central w Project file conversion completed w Users guide completed and posted w

Project Central w Project file conversion completed w Users guide completed and posted w Next steps – – Validate project plans Provide training to business area groups Configure ODBC settings Assign tasks / create accounts – using resource pool

Time Tracking System (SBS) w Implemented to provide real-time estimates on project time and

Time Tracking System (SBS) w Implemented to provide real-time estimates on project time and cost w Supports all contracting and government staff – ~242 staff members w Time tracked by cost category and workflow

Time Tracking System (SBS)

Time Tracking System (SBS)