Dual Phase Field Cage Status DUNE HV Consortium

  • Slides: 13
Download presentation
Dual Phase Field Cage Status DUNE HV Consortium Meeting December 20, 2017 Jaehoon Yu

Dual Phase Field Cage Status DUNE HV Consortium Meeting December 20, 2017 Jaehoon Yu for A. Chatterjee, G. Brown & UTA Team A. Gendotti, S. Murphy, C. Cantini & ETH Team F. Pietropaolo & CERN Team

Contents • DP FC Design Concept • HV Divider board design and component testing

Contents • DP FC Design Concept • HV Divider board design and component testing status • DP FC Trial Installation Status • Summary 2 12/20/17 Jaehoon Yu | DP FC Status

Field Cage in proto. DUNE DP § Field Cage and cathode hangs off of

Field Cage in proto. DUNE DP § Field Cage and cathode hangs off of the ceiling § Essential to have light yet sturdy structure § Based on modular concept as SP Charge Readout Planes Field Cage (common structural elements with SP) 6 m 6 m 3 12/20/17 Jaehoon Yu | DP FC Status Catho de

Field Cage Design • Shares common basic structural elements w/ Proto. DUNE-SP • Consists

Field Cage Design • Shares common basic structural elements w/ Proto. DUNE-SP • Consists of 8 vertical modules of 6310 x 3010 mm 2 (2 modules per detector face) • Each module is assembled out of 3 distinct sub-modules • Three distinct types of sub-modules with 33, and 32 profiles each held by a frame with two 6” and two 3” horizontal FRP I-beams • 98 electrically continuous rings in 60 mm pitch using straight aluminum clips • Each profile is made of extruded aluminum with a supporting rib running in the middle • 11 profiles with one end bent at 45 degrees are electrically connected by 2 divider boards Sub-module 1 33 profiles • Inter-module connections made with FRP plates connected with FRP threaded rods Sub-module 2 33 profiles Sub-module 3 32 profiles + cathode Continuity at center and borders w/ Al clips 4 12/20/17 Jaehoon Yu | DP FC Status

HV Divider Board Mounting to DC A. Gendotti 5 12/20/17 Jaehoon Yu | DP

HV Divider Board Mounting to DC A. Gendotti 5 12/20/17 Jaehoon Yu | DP FC Status • Two parallel columns of 10 boards, totaling 20 boards • The total potential from the extraction grid to cathode: 294 k. V to 588 k. V • Two 2 GW resisters each stage for each board, providing 0. 5 GW effective resistance per stage • Current through the entire circuit: 6 m. A – 12

FC Production Status § The production for 24+3 sub-modules completed and shipped to CERN

FC Production Status § The production for 24+3 sub-modules completed and shipped to CERN § Additional spares have been ordered and will be conditioned and preassembled at UTA for shipping if necessary at CERN § HVDB boards (18+1 long and 2+1 short) have been certified and at CERN § A protective epoxy coating on the solder balls in between the profiles have been done at CERN § All boards have been recertified and ready for mounting § Per CERN group suggestion, an additional protective boards have been designed and being 6 12/20/17 Jaehoon Yu | DP FC Status

Activity at CERN § Two UTA students stayed at CERN from 11/19 – 12/8

Activity at CERN § Two UTA students stayed at CERN from 11/19 – 12/8 for a trial installation which planned to have 3/8 of FC installed § Have been trained for the elevating platform operation for FC installation work § They assembled 8 out of the 9 sub-modules when JY joined them on 11/30 for his three week stay § One sub-module was left to train the CERN technicians § Floor trial assembly of the three top sub-modules along with three HVDB mounted on Dec. 8 7 § Al clips connected the profiles in the straight and 90 degree section § Resistance measurements performed at the far end of the 12/20/17 Jaehoon Yu | DP FC Status board and showed good results (consistently ~980 MOhm

Floor Trial Assembly of Top Row 8 12/20/17 Jaehoon Yu | DP FC Status

Floor Trial Assembly of Top Row 8 12/20/17 Jaehoon Yu | DP FC Status

DP FC Installation at CERN § Load testing with 180 kg each for each

DP FC Installation at CERN § Load testing with 180 kg each for each of the 6 winches and cables completed the morning of Monday, Dec. 18 § Gendotti and Yu together with two CERN technicians and Resnati installed two sub-modules in 2. 5 hours § Installation sequence for a panel: 9 1. SS I-beams with SS L-brackets are mounted onto the cables and raised to ~2 m by the two manual winches top of the cryostat 2. Top sub-module placed under the SS I-beam and lower the I-beam into the FRP I-beams of the module and connect the module to SS I-beam 3. Raise the connected top sub-module to ~2 m | DP FC Status 4. 12/20/17 Place. Jaehoon the Yumiddle sub-module and connect it to the top

Module Connection Details 10 12/20/17 Jaehoon Yu | DP FC Status

Module Connection Details 10 12/20/17 Jaehoon Yu | DP FC Status

DP FC Installation at CERN § Gendotti, Yu together and two CERN technicians continued

DP FC Installation at CERN § Gendotti, Yu together and two CERN technicians continued the installation of the 2 nd two sub-modules yesterday § Needed help from Dominique Ducheneau to raise the manual winch § Took ~40 min to install the SS I-beam and the top submodule § Took another ~45 min for the second module due to the potential interference with the existing module § Due to cryo-pipe installation ongoing through the end of the week, the floor had to be removed, preventing us to continue installation § Raised the two modules above 2 m height and connected the two modules with the horizontal bar 11 Jaehoon Yu | DP FC Status to 12/20/17 prevent unexpected motion damaging the

First Two Modules 12 12/20/17 Jaehoon Yu | DP FC Status

First Two Modules 12 12/20/17 Jaehoon Yu | DP FC Status

● Summary All FRP and other parts for DP FC have been conditioned and

● Summary All FRP and other parts for DP FC have been conditioned and delivered to CERN ● ● HVDB boards with the minimal spares certified and delivered at CERN ● ● 13 Remaining spares will be produced, tested in warm and cold, certified and shipped to CERN early 2018 Trail installation of 2 partial panels of the 8 total completed in the past two days Installation was seamless and quick (~ 1 hour per submodule) but requires minimum four people ● ● All packages are in the CRB Two on the winches and two for module connection and safety We’ve learned tremendously from the trial installation We have obtained a reasonable confidence that the installation of FC will be expeditious, barring any 12/20/17 Jaehoon Yu with | DP FC Status interferences other parts 13