Drawing the AON network Project Management lecture Elements













- Slides: 13

Drawing the AON network Project Management (lecture)

Elements of an Ao. N diagram • Activity (node) – Work element or task – Name or identification of the tasks must be added – No need for dummy (unreal) activities • Dependency or sequence arrow – Shows the interrelationship between activities

Conventions • Time flows from left to right – Arrows’ direction – Labels’ increase • Head nodes always have a greater/higher label (letter) that of the tail node. • A complete network has only one starting and only one ending event.

Examples of activity combinations

Graphical representation • Representation of dependency time: lags • Activity duration times & finish to start dependency • Representation of milestones/deadlines (external constraints): Identified by an inverted triangle over the activity node (occasionally with an imposed time for the event)

Overlapping activities • If the activities are not fully discrete • The second activity can start before the first is completed but not before it is at least partly completed. • Breaking activities into components

Interfacing • When an activity is common to two or more subnetworks it is said to be an ‘interface’ activity between those subnetworks and is represented by a pair of concentric circles or rectangles.

Two errors in logic • Looping: underlying logic must be at fault • Dangling: an activity is undertaken with no result

Hammock activities • Artificial activities created for the representation of the overhead cost with the aim of cost control. • Embrace activities belong to the same cost centre • Zero duration time (not taking part in the time analysis) • Overhead cost rate is assumed to be constant over the life of the hammock.

Multiple starts and finishes • Only used in computer programs • All starting activities can occur at the start and all finish activities will occur at the end of the project.

CPA, CPM and PERT • Critical Path Analysis (CPA), Critical Path Method (CPM) – deterministic with only one estimation • Program Evaluation and Review Technique (PERT) – probabilistic with three estimated durations

Readings • Lockyer – Gordon (2005) Chapter 12

Thanks for the attention!
Aon critical path
Project management aon
Network management principles
01:640:244 lecture notes - lecture 15: plat, idah, farad
Project procurement management lecture notes
Project management for software development
Project management lecture notes doc
Software cost estimation notes
Project management lecture
Project planning and management lecture notes ppt
Introduction for project
Aon global risk consulting
Drawing lecture
Drawing lecture