DHS Project 2018 Sept 21 2018 Concrete Footers

  • Slides: 7
Download presentation
DHS Project 2018 Sept 21, 2018

DHS Project 2018 Sept 21, 2018

Concrete Footers are complete. Re. Bar out the top is for CMU walls. There

Concrete Footers are complete. Re. Bar out the top is for CMU walls. There is also a brick ledge on exterior walls. Insulation protects from frost. Sleeves were installed for plumbing and electrical.

This is the drive that was soft. Undercut 18 -24”s. Geo grid added for

This is the drive that was soft. Undercut 18 -24”s. Geo grid added for stability. Then stoned and compacted. Drainage was added due to continual water flow from south end of parking lot. C. O # 006 $18, 406. 99

Underground plumbing is underway and should be completed by 9/28. This is typical, with

Underground plumbing is underway and should be completed by 9/28. This is typical, with the addition of the acid waste tanks for the science classrooms. Upon plumbing completion this area will be prepped for concrete slab placement.

DLC. Chase for 2 nd floor drains to main. Clinic bathroom before block, and

DLC. Chase for 2 nd floor drains to main. Clinic bathroom before block, and after. Interior drain rough-in plumbing is mostly complete, as well.

Drainage and site work has ramped up in order to complete certain areas in

Drainage and site work has ramped up in order to complete certain areas in advance of the paving process on “Fall Break. ” Getting the drainage issues corredted are essential to a lasting product. It will all look great upon completion, but it needs to perform for years.

Site Work has been challenging. It will be a constant through “Fall Break. ”

Site Work has been challenging. It will be a constant through “Fall Break. ” Constant communication, monitoring and feedback are helping our environment stay as safe and educational as possible.