DCM Engineering Design Review Prototyping and Production Plan











- Slides: 11
DCM Engineering Design Review Prototyping and Production Plan Y. Leclercq, S. Spathopoulos, F. Crisci, F. Savary, F. Di Ciocchis, J. B. Deschamps, S. Donche, J. Dequaire, R. Abdennour for WP 3 Engineering Design Review of the D 1 -DFX Connection Module (DCM) 15. 04. 2021
Contents § § § § Scope of work WBS – Who does what DCM assembly work flow Schedule Resource plan Infrastructure Concluding remarks DCM Engineering Design Review – Prototyping and Production Plan 2
Scope Work § 1 prototype DCM § It will be used in the IT String § WP 3 requires on-time availabilty of the 1 st DCM for installation in the string § DCM 1 required for July 2022 § 4 series DCM’s § They will be installed, as part of the HL-LHC Project plan § WP 3 requires on-time availabilty of the 4 DCM’s for installation in the tunnel § DCM’s 2 -5 required for July 2025 § The prototype will be identical to the series DCM’s, such that it can be used as a spare DCM, and installed in the machine if needed DCM Engineering Design Review – Prototyping and Production Plan 3
WBS – Who does what Courtesy F. Crisci DCM Engineering Design Review – Prototyping and Production Plan 4
Work breakdown § § Courtesy F. Crisci § § Main stream • Vacuum vessel • Helium vessel • Thermal shield • Diode stack • Instrumentations D 1 interface • Vacuum vessel • Helium vessel • Thermal shield • Connecting flexible to D 1 • Frame interface DCM is split in 3 sub-models Each sub-model is pre-assembled and tested out of the tunnel The sub-models will be connected only in the tunnel Tests on the whole DCM will be carried only in the tunnel Frame • Main structure • Connections to Vacuum vessel • Connection to ground DCM Engineering Design Review – XX. 04. 2021 5
DCM assembly workflow § B 189 nearby SMI 2 used as logistics platform for small items Courtesy Y. Lecrecq § Large items stored in Flex Building B 189 : Stock B 3191 (SMI 2) Plug Subassemblies* Diodes Instrumentation DCM manufacturing & QC Flex Building Vessels + Th. Shield DCM proto + series String / Tunnel Frame Installation DCM Engineering Design Review – Prototyping and Production Plan *Busbars assembled into Plug assemblies, see Lambda Plate review for detailed workflow 6
Schedule (numbers indicate FTE • m) 2021 Task description Detailed design and manufacturing dwgs Who TE-MSC-CMI Qualification tests TE-MSC-CMI DCM 1 - Prototype Cable delivery Copper Bus bars Plugs for X (cable soldering LMF) Support plate + He vessel Diodes (with instrumentation wires) Vacuum vessel Thermal screen with MLI Instrumentation (IFS-DCM) + LMF Support frame (sous-traitance) Final assembly and acceptance tests DCM 2 - Series DCM 3 - Series DCM 4 - Series DCM 5 - Series Total resources TE-MSC-CMI TE-MSC-SCD CMI + LMF TE-MSC-CMI EN-MME-FS TE-MPE-PE EN-MME-FS TE-MSC-CMI TE-MSC-CMI A M J J D. Off. 2 -pl. 1. 5 D. Off. 2 D. Off. 1 -pl. 1. 5 M-Up 1. 5 2022 A S O N D J F M A M J 2. 25 0 0 1 1 3 3 2+0. 25 M-Up 1. 5 milestone 01. 08 2+0. 25 milestone 28. 02 milestone 1 29. 04 1 milestone 3 3 30. 06 3 3 DCM Engineering Review 0 – Prototyping and 3 1. 5 2. 25 Design 2. 25 0 1 1 Production 3 3 Plan 3 3 See next slide 1. 5 3 7
Schedule & resource plan § 5 DCM to be produced over about two years Courtesy Y. Lecrecq § SMI 2 facility to be reorganized (layout) to fulfil production rate § During production, 3 operators 100 % with 75 % coordinator DCM Engineering Design Review – Prototyping and Production Plan 8
Infrastructure § Space reservation in Bldg. SMI 2 for the final assembly, QC and acceptance tests § For DCM: about 75 m 2 out of a total of 667 m 2 in SMI 2 as from Jan. 2022 § For Plugs: about 60 m 2 from now till mid of 2023 § Bldg. 189 will be used for proximity storage according to needs § Availability of Flex building needs to be checked DCM Engineering Design Review – Prototyping and Production Plan 9
Concluding remarks § § § § Today, the plan is based on a cable delivery in August 2021 It is assumed that the contributors, other than MSC-CMI, have sufficient resources to provide the services required. The needs of MSC-CMI in this respect are being put together, and the service providers will be approached to make sure they get prepared properly The qualification phase is expected to be completed in the beginning of Q 3 -2021 The prototype could be ready by end June 2022 The 5 th DCM could be ready by end February 2024. To achieve this, we assume that there is no interruption of the activities after completion of the prototype The resource profile for this project (part MSC-CMI) is almost flat over about 2 years The schedule needs to be integrated with the other activities within MSC-CMI. We do not expect major difficulties in relation to this integration The layout of SMI 2, and the associated needs in terms of storage, are being revised taking account of all the activities coming up in MSC-CMI in the coming years DCM Engineering Design Review – Prototyping and Production Plan 10
Thank you for your attention DCM Engineering Design Review – Prototyping and Production Plan 11