DAVIDSON COUNTY COURTHOUSE ADDITION AND RENOVATION INFORMATION SESSION June 4, 2019

DAVIDSON COUNTY COURTHOUSE ADDITION AND RENOVATION INFORMATION SESSION June 4, 2019

DAVIDSON COUNTY COURTHOUSE ADDITION AND RENOVATION Early Project Requirements v Building Users Relocated v

DAVIDSON COUNTY COURTHOUSE ADDITION AND RENOVATION Early Project Requirements v Building Users Relocated v Remove Overhead Lines and Poles v Relocate the Todd Cook Memorial v Temporary Site Fencing v Relocate the Gas Meter v Relocate the Transformer v Building Abatement and Demolition Package v v v Ramp at entrance to 2000 Building Lower Level and Stair Scaffold System Professional Services for Abatement/Demolition and Special Inspections Present Budget to the Facility Committee

Important Dates Release Barnhill to Procure Early Project Requirements – 6/11/19 Advertise for Professional

Important Dates Release Barnhill to Procure Early Project Requirements – 6/11/19 Advertise for Professional Services and Abatement and Demolition – 6/12/19 (After Board Approval) Prequalifications Complete – 6/14/19 Pre Bid Meeting Demolition and Abatement – 6/14/19 Bid Day for Abatement/Demolition and Professional Services – 6/27/19 Pre Bid Meeting Final GMP - 6/26/19 @ 1: 30 PM Final GMP - Bid Day Morning Date & Time: Group 1 – 7/23/19 @ 10: 00 AM Final GMP - Bid Day Afternoon Date & Time: Group 2 – 7/23/19 @ 2: 00 PM

Important Dates Close Center Street Parking Lot – 6/24/19 Construction Activity Start - 6/24/19

Important Dates Close Center Street Parking Lot – 6/24/19 Construction Activity Start - 6/24/19 Submit for Building Permits – 6/26/19 Submit to DOI – 6/26/19 Approve Final GMP – 8/13/19 Anticipated Construction Finish - 2/28/21