Current status Toshiba 14 cryostat Sapphire fibers ET
Current status (Toshiba, 1/4 cryostat, Sapphire fibers, ET meeting, Jena) Kazuhiro Yamamoto Institute for Cosmic Ray Research The university of Tokyo KAGRA cryogenic payload meeting 12 December 2012 1
Toshiba 1/2 dummy payload with sapphire dummy mirror (Initial cooling time by radiation) Manufacturing started and is in progress. 2
1/4 cryostat Design and discussion for 1/4 cryostat to check payload is in progress. Bid (for parts) will be opened in this. y r a n i December. m i l Pre 3
Sapphire fibers with nail heads Ettore Majorana asked IMPEX High. Tech Gmb. H (German company). They can make similar fibers (nail heads on the both ends). Finally. . . 4
Sapphire fibers (c) Sapphire fibers with nail heads IMPEX fibers arrived ! (15 th of Nov. ) 5
Sapphire fibers Quality check Q-value and profile of Moltech fibers: Y. Sakakibara at Glasgow and Jena. Although they are broken, the measurement result is promising. Two Moltech fibers and two IMPEX fibers were sent to Jena (29 th of Nov. ). 6
Sapphire fibers Two Moltech fibers and two IMPEX fibers were sent to Jena (29 th of Nov. ). They survived ! (Photos from Jena) 7
ET meeting in Hannover 4 th-5 th Dec. 2012 http: //et-meeting 2012. aei. mpg. de/ Kazuhiro reported the current status of KAGRA cryogenic system. http: //gwdoc. icrr. u-tokyo. ac. jp/cgi-bin/Doc. DB/Show. Document? docid=1407 8
Jena 6 th-7 th Dec. 2012 Kazuhiro visited Friedrich-Schiller-Universitaet Jena. Yusuke measured Q-values of sapphire fibers. http: //gwdoc. icrr. u-tokyo. ac. jp/cgi-bin/private/Doc. DB/Show. Document? docid=1420 9
Jena Nitric acid washing works well ! Before After 10
Jena 6 th-7 th Dec. 2012 Ronny, Christian, Ettore (skype from Rome), Yusuke, and Kazuhiro discussed the strategy. In Jena Q-value with other type clamps, Thermal conductivity, Unbroken Moltech fibers, IMPEX fibers, X-ray (crystal structure), impurity measurement Around March, these fibers will be sent to Rome and Ettore continue the investigation. 11
Jena 6 th-7 th Dec. 2012 Ronny, Christian, Ettore (skype from Rome), Yusuke, and Kazuhiro discussed the strategy. In Rome, Ettore ordered other IMPEX fibers (manufacturing procedure is different). They will arrive on the end of January. Q-measurement system in Jena could be exported to Japan. If possible, students and Post doc are exchanged. 12