Culver City Unified School District Photovoltaic System Project

  • Slides: 6
Download presentation
Culver City Unified School District Photovoltaic System Project Update June 11, 2013 © 2011

Culver City Unified School District Photovoltaic System Project Update June 11, 2013 © 2011 Sun. Power Corporation

CCUSD Solar Project Status Update • SCE Easement issue update: Following a site visit

CCUSD Solar Project Status Update • SCE Easement issue update: Following a site visit from the SCE regional planner Sun. Power received informal approval to proceed with construction as planned. SPWR is preparing to submit the official encroachment request paperwork. • Permitting Update: Sun. Power did not receive DSA approval on June 4 th as originally scheduled. DSA was concerned about the solar arrays spanning across multiple campuses. This issue has been resolved and a new over the counter review date has been scheduled for June 18 th. • Steel has been ordered and is being procured. Fabrication will begin shortly after receiving DSA approval. • Mobilization is scheduled to occur on July 1 st. © 2011 Sun. Power Corporation

CCUSD Solar Project Status Update • Sun. Power and CCUSD have agreed on an

CCUSD Solar Project Status Update • Sun. Power and CCUSD have agreed on an alternate location for the Farragut ES solar array. The garden area will no longer be covered and no trees will be removed. © 2011 Sun. Power Corporation

CCUSD Solar Project Timeline Task System Design Start Date 3/1/13 Finish Date 6/14/13 Duration

CCUSD Solar Project Timeline Task System Design Start Date 3/1/13 Finish Date 6/14/13 Duration 70 days DSA Permitting (over the counter) 6/18/13 1 days Construction 7/1/13 10/18/13 80 days 7/1/13 7/8/13 8/5/13 9/23/13 7/5/13 8/16/13 8/30/13 9/20/13 10/18/13 5 days 30 days 20 days 15 days 20 days 10/21/13 11/15/13 20 days 10/21/13 10/28/13 11/4/13 10/25/13 11/15/13 5 days 10 days 11/18/13 12/20/13 25 days 11/18/13 11/25/13 12/2/13 Jan 2014 11/22/13 11/29/13 12/20/13 Jan 2019 5 days 15 days 5 years Mobilize, Site Prep, Lighting Demo Concrete Foundations Steel Erection PV Module Installation Lighting, Wiring, Terminations, Misc. Commissioning Test and Commission PV System Commissioning Punch List Utility Inspection and PTO CSI Reservation Submit CSI Documentation Site Inspection by 3 rd Party Firm CSI Application Review and Approval CSI Reservation Incentive Checks © 2011 Sun. Power Corporation 4

CCUSD Solar Project Timeline Highlights • Sun. Power will submit look-ahead schedules and coordinate

CCUSD Solar Project Timeline Highlights • Sun. Power will submit look-ahead schedules and coordinate all construction activities with Balfour Beatty and CCUSD. • Sun. Power will build all three campuses simultaneously, but work will be phased to accommodate parking needs. We will delineate our work areas and maintain parking and traffic control. Construction deliveries will be scheduled and coordinated to avoid school drop off and pick up times. • All “heavy construction” (underground work, concrete work and steel erection) will take place during Summer 2013. This will minimize the impact of our construction activities when school returns in the fall. • One twelve hour shutdown will be required for electrical interconnection. Shutdown will be scheduled on a weekend or after hours. • When school begins in September 2013, construction will be limited to the areas directly beneath the arrays. Construction areas will be safely delineated with temporary fencing. © 2011 Sun. Power Corporation 5