Crossing Structures Crossing structures are those constructed at

  • Slides: 14
Download presentation
Crossing Structures • Crossing structures are those constructed at intersections of: 1. Waterway-road (culvert

Crossing Structures • Crossing structures are those constructed at intersections of: 1. Waterway-road (culvert or bridge). 2. Waterway-Waterway (syphon or aqueduct). 3. Waterway ending at another waterway (tail escape).

Road Water way Culvert or Bridge Water way Syphon or Aqueduct Water way Tail

Road Water way Culvert or Bridge Water way Syphon or Aqueduct Water way Tail escape

Culvert

Culvert

The culvert is a closed conduit (pipe or box section) constructed to carry the

The culvert is a closed conduit (pipe or box section) constructed to carry the discharge of a waterway under a road. The selection of the type of the culvert is based on the discharge as follows: • For Q ≤ 3. 0 m 3/sec use Pipe culvert. • For Q ≤ 12. 0 m 3/sec use Box section.

≥. 15 m ≥. 3 m d D S H

≥. 15 m ≥. 3 m d D S H

Hydraulic Design The purpose of the hydraulic design is to select the culvert’s dimensions.

Hydraulic Design The purpose of the hydraulic design is to select the culvert’s dimensions. The dimensions are selected based on: • Velocity through culvert between 1. 0 to 2. 0 m/sec. • Head losses is less then 15 cm. • Entrance submergence is at least 30 cm.

The only equation available is the continuity equation: Q=A. V Where Q is the

The only equation available is the continuity equation: Q=A. V Where Q is the discharge in m 3/sec, A is the culvert’s cross section area in m 2, and V is the water velocity through the culvert in m/sec. Since the discharge is known, the velocity must be assumed to determine the dimensions of the culvert. The velocity is usually assumed between 1. 0 and 2. 0 m/sec for practical reasons.

Once the dimensions are determined, then head losses must be checked. Head losses are

Once the dimensions are determined, then head losses must be checked. Head losses are calculated as follows, Where Hl is the head losses in m V is the velocity in m/sec g is the acceleration of gravity

Ce is the entrance coefficient of loss (= 0. 5 ) Cf is the

Ce is the entrance coefficient of loss (= 0. 5 ) Cf is the friction coefficient Co is the outlet coefficient of losses ( = 1. 0 ) Friction coefficient can be calculated as follows,

Where f is coefficient depends on the culvert material and dimension, L is the

Where f is coefficient depends on the culvert material and dimension, L is the length of the culvert and m is the hydraulic radius. The coefficient a and b are constant and depends on the material of the conduit. For Steel: a = 0. 0048, b = 0. 0256 For Concrete: a = 0. 00316, b= 0. 0305

 • Example 1: Design a culvert under a road. The discharge is 3

• Example 1: Design a culvert under a road. The discharge is 3 m 3/sec and the water depth is 1. 8 m. The culvert length is 20 m. • Sol. Q = 3 m 3/sec * use pipe culvert assume V=1. 3 m/sec A = Q/V = 2. 31 m 2 A = ∏ D 2/4 * D = 1. 7 m However, D ≤ 1. 8 – 0. 3 … 1. 5 m

Then use 2 pipes …one pipe A = 1. 155 m 2 D =

Then use 2 pipes …one pipe A = 1. 155 m 2 D = 1. 3 m …. V = 1. 13 m/sec … OK Check of heading up m = D/4 = 0. 325 m f = 0. 0052 Cf = 0. 32 Hu = (1. 13)2/(2*9. 81) *(0. 5+0. 32+1) = 0. 12 m … OK

 • Example 2: design a culvert under a road. The discharge is 5

• Example 2: design a culvert under a road. The discharge is 5 m 3/sec and the water depth is 2. 2 m. The culvert length is 20 m. • Sol. Q = 5 m 3/sec … Use Box culvert Assume V = 1. 3 m/sec A = Q/V = 3. 85 m 2 H = 2. 2 – 0. 3 = 1. 9 m S = 3. 85/1. 9 = 2. 0 m

S < 1. 5 H … OK V = 5/(1. 9*2) = 1. 32

S < 1. 5 H … OK V = 5/(1. 9*2) = 1. 32 m/sec Check for Heading Up m = 2*1. 9/(2+1. 9)*2= 0. 49 m f = 0. 00336 Cf = 0. 14 Hu = 0. 145 m … OK