Cost Estimating Basics Why cost estimating (and an overview of how) Cost Prof Unit I - Module 1 1
Unit Index Unit I – Cost Estimating 1. Cost Estimating Basics 2. Costing Techniques 3. Parametric Estimating Unit II – Cost Analysis Techniques Unit III – Analytical Methods Unit IV – Specialized Costing Unit V – Management Applications Cost Prof Unit I - Module 1 2
Outline • Introduction to Cost Estimating and Analysis • Overview of Cost Estimating and Analysis • Cost Estimating Products • Cost Estimating Process & Methods • Cost Estimating Certification • Summary • Resources Cost Prof Unit I - Module 1 3
Introduction to Cost Estimating and Analysis • Definition and Purpose • Applications • Organizations • Skills Cost Prof Unit I - Module 1 4
Cost Estimating • Cost Estimating: – The process of collecting and analyzing historical data and applying quantitative models, techniques, tools, and databases to predict the future cost of an item, product, program or task • Purpose of cost estimating – Translate system/functional requirements associated with programs, projects, proposals, or processes into budget requirements – Determine and communicate a realistic view of the likely cost outcome, which can form the basis of the plan for executing the work Cost Prof Unit I - Module 1 5
Applications of Cost Estimating • As part of a total systems analysis, cost estimating helps decision makers to: – Make decisions on program viability, structure, and resource requirements – Establish and defend budgets – Assess technology changes 13 – Conduct analysis of alternatives (Ao. A) – Create new business proposals and perform 14 source selection 16 – Perform design trade-offs – Comply with public law – Satisfy oversight requirements Cost Prof Unit I - Module 1 6
Cost Estimating Organizations 1 20 • Cost oversight organizations • Program Offices and project teams • Budgeting, contracting, and purchasing organizations • Manufacturers • Consultants Cost Prof Unit I - Module 1 7
Cost Estimating Skills 5 • Cost estimating and analysis at its best is an interdisciplinary mix of: – Mathematics, Probability, Statistics 10 – Economics, Econometrics, Business, Accounting, Budgeting – Operations Research, Management 11 Science, Industrial Engineering – Mechanical Engineering, Systems Engineering, Physics, etc. Estimating 101, Naval Center for Cost Analysis – Sales and Marketing Cost (NCCA), http: //www. ncca. navy. mil/about/101. cfm. Cost Prof Unit I - Module 1 8
Overview of Cost Estimating and Analysis • Requirements • Benefits and Qualities • Limitations and Concerns • Types of Cost Estimates • Government Entities Cost Prof Unit I - Module 1 9
Requirements for Cost Estimating • Must estimate and plan consumption of resources – Capture impacts of changing resources 11 • Validated cost estimate necessary to continue through milestone reviews – Estimates should be updated periodically as program matures technically and schedules change • Efficient management of changing requirements under tight constraints – Supports management decisions by quantifying the resource impact of alternatives Cost analysis is required whenever resources are allocated Cost Prof Unit I - Module 1 10
Benefits of Cost Estimating • Supports budgeting process by enabling you to: 15 – – Integrate the requirements and budgeting processes Assess reasonableness of program budgets Effectively defend budgets to oversight organizations Quickly/accurately determine impacts of budget cuts on program baselines and associated functionality • Enhances profitability and organization’s future business potential • Uses established, repeatable methods • Enables identification of potential pitfalls such as cost growth, schedule slips early in a program’s life • Enables identification of future cost improvement initiatives Cost Prof Unit I - Module 1 11
Benefits of Cost Estimating • Provides for the identification and objective 9 quantification of the impact of program risks (technical and schedule risks) • Provides basis for evaluating competing 13 systems/initiatives (cost/benefit analyses and Ao. As) • Enables proposal pricing and evaluation of proposals 19 14 for cost reasonableness • Captures cost impacts of design decisions to facilitate 16 tradeoffs in CAIV/DTC/Target Costing • Facilitates evaluation of the impact of new ways of doing business (e. g. , in-sourcing vs. outsourcing, COTS vs. custom software) Cost Prof Unit I - Module 1 12
Cost Estimate Qualities 10 • The characteristics of high quality cost estimates are: – – – Cost Prof Accuracy Comprehensiveness Replicability and Auditability Traceability Credibility Timeliness Unit I - Module 1 13
Limitations of Cost Estimating • Cost estimating cannot – Be applied with cookbook precision – Produce results that are better than input data – Predict political impacts – Substitute for sound judgment, management, or control – Make final decisions Cost Prof Unit I - Module 1 14
Cost Estimating Concerns • Support Critical Decisions 16 – May be difficult to quantify cost impacts of alternatives – Cannot trade off non-cost variables • Timeliness 18 – Schedule constraints on estimate delivery • Estimate quality suffers with fast turnaround requirements – Quick and easy access to historical data may not be possible – Lower quality estimate limits utility to key decision makers • Quality 4 – – Definition of “good data” Adjustments to raw data may be made several times Inadequate documentation Undocumented or tacit knowledge • Coordination – Large number of organizations may be involved Cost Prof Unit I - Module 1 15
Cost Estimating Concerns • Consistency – Estimates must track over time – Estimates developed by other organizations must be based on same content and assumptions – Historical data is not consistent between differing cost element or work breakdown structures • Security/access – Company-proprietary data – Data classification/security – Possible misuse of data Cost Prof Unit I - Module 1 16
Types of Cost Estimates – Budget • Budget Estimate 1 6 – Estimate prepared for inclusion in budget to support acquisition programs – Ensures project feasibility and attainable performance levels – A reliable project cost estimate consistent with realistic schedules – Used to establish baseline project definitions, schedules, and costs – May or may not include risk Cost Prof Unit I - Module 1 17
Types of Cost Estimates – LCCE • Life Cycle Cost Estimate (LCCE) 12 – “Cradle to grave" estimate – Includes research and development (R&D), production, operations and support (O&S), and disposal • Commercial definitions are similar • Life cycle is often confused with O&S but actually includes all of the above – Should be performed as early in the life cycle as possible – Estimate costs regardless of funding source – AKA Total Ownership Cost (TOC) estimate Cost Prof Unit I - Module 1 18
Types of Cost Estimates – ICE • Independent Cost Estimate (ICE) – LCCE developed by an independent organization – “True facts" assessment of what the program's most likely cost will be – Provides an unbiased test of the reasonableness of the Program LCCE (PLCCE) – Identifies potential budgetary excesses and shortfalls – Reduces the cost risks associated with the project Cost Prof Unit I - Module 1 19
Types of Cost Estimates – ROM & EA • Rough-Order-of-Magnitude (ROM) – – Very little specific information is known about the project The design effort has not begun Estimate uses ratios or factored historical information Used for feasibility studies and selection from among alternatives – AKA “Quick Look” • Economic Analysis (EA) 13 – Describes specific mission requirement(s) and lists specific alternative courses of action – Framework for systematically investigating problems of choice – Compares the costs and benefits associated with each alternative course of action Cost Prof Unit I - Module 1 20
Types of Cost Estimates – Ao. A & ABC 13 16 • Analysis of Alternatives (Ao. A) – Evaluates the costs and benefits of different alternatives – Shows advantages and disadvantages of the alternatives being considered • Activity Based Costing (ABC) – Accounting methodology that assigns all costs to activities – Enables resources and overhead costs to be accurately assigned to products and services – Assists in making decisions about pricing, outsourcing, capital expenditures and operational efficiency. Cost Prof Unit I - Module 1 21
Government Entities Responsible for Cost Estimating • OSD Cost Analysis Improvement Group (CAIG) – Milestone review authority, has oversight of Do. D service cost centers • Intelligence Community CAIG (IC CAIG) – Provides independent cost assessments to the Director of Central Intelligence (DCI) for selected IC programs • Naval Center for Cost Analysis (NCCA) – Prepares and briefs the Component Cost Analysis (CCA) to the CAIG – Holds a reconciliation meeting prior to the formal CAIG meeting • US Army Cost and Economic Analysis Center (CEAC) – CEAC prepares CCA and briefs results to the CAIG – Army Cost Review Board works with the Assistant Secretary of the Army (Financial Management) to develop the Army cost position briefed to the CAIG • Air Force Cost Analysis Agency (AFCAA) – Air Force Cost Directorate, SAF/FMCC, prepares the AF cost position, after reconciliation between the System Program Office estimate and the AFCAA’s CCA Cost Prof Unit I - Module 1 22
Cost Products • Cost Analysis Requirements Description (CARD) • Cost Estimate • Estimate Documentation Cost Prof Unit I - Module 1 23
Cost Analysis Requirements Description (CARD) • Cost Analysis Requirements Description (CARD) 2 – Detailed technical, programmatic, and schedule description • Purpose of CARD – Collect, integrate and coordinate technical, programmatic, and schedule information necessary to estimate the costs of a program – Ensures that cost projections developed by the analyst are based on a common definition of the system and the acquisition program CARD is a Do. D requirement for major programs but a CARD-like document should be developed for any estimate, government or private industry Cost Prof Unit I - Module 1 24
CARD Contents • CARD includes: – System Technical Description – Work Breakdown Structure (WBS) – Predecessor System Description – Manpower Requirements – Risk – Operational Concept – Deployment Cost Prof – Logistics Support Concept – Training – Acquisition Schedule – Acquisition Strategy – System Test and Evaluation (ST&E) – Environmental Impact Analysis – Track to Prior CARD Unit I - Module 1 25
CARD Contents • CARD includes: – System Technical Description – Work Breakdown Structure (WBS) – Predecessor System Description – Manpower Requirements – Risk – Operational Concept – Deployment Cost Prof – Logistics Support Concept – Training – Acquisition Schedule – Acquisition Strategy – System Test and Evaluation (ST&E) – Environmental Impact Analysis – Track to Prior CARD Unit I - Module 1 26
Cost Estimate • Definition of a cost estimate – Cost estimate is an analysis of individual cost elements using established methodologies to project from data to estimated costs – Various types of estimates can be developed • Budget Estimate, LCCE, ICE, ROM Estimate, EA, Ao. A, ABC, etc. • Developed using one or more estimating 2 techniques • Analyst should consider past and current actual data Cost Prof Unit I - Module 1 27
Cost Estimate Characteristics • Input rates – Labor, materials, tooling, scrap, etc. – Application of audited or negotiated direct and indirect rates • Model structure – Estimate developed to a varying level of detail depending on system and schedule – Estimate is inflated and time phased • Model execution 9 – Applies COTS or custom model – May include sensitivity/risk analysis Cost Prof Unit I - Module 1 28
Estimate Documentation • Why document the estimate? – Provides reviewers with: • • • Purpose of cost estimate Program background and system description Program Schedule Scope of cost estimate Ground rules and assumptions – Robust and detailed documentation permits reviewers to follow estimate logic from assumptions to results Document not only for an external audience but for yourself! Cost Prof Unit I - Module 1 29
Estimate Documentation • What should be documented? 4 7 3 – The data, data sources, and normalization procedures – Labor rates and hours, content, and how they were developed – Material requirements and subcontracts – Methodology for any applicable cost improvement curves – Details regarding the factors and cost estimating relationships (CERs) applied Cost Prof Unit I - Module 1 30
Estimate Documentation • What should be documented? – Details regarding the applied cost models including • Relevance to the system/program • Inputs/outputs • Calibrations performed 9 – Inflation indices used and time phasing details – Detailed description of judgments applied by estimator(s) – Any details of risk and confidence analysis – The conclusion(s) resulting from the estimate – Appendices and appropriate references Cost Prof Unit I - Module 1 31
Cost Estimating Process WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof 8 • Work Breakdown Structure (WBS) Development • Program/System Baseline Development • Data Collection and Analysis • Cost Element Methodology • Estimate Development and Validation • Results and Report Generation Unit I - Module 1 32
Work Breakdown Structure (WBS) WBS • What is a WBS? Baseline Data Collection Data Analysis 3 – Common frame of reference for relating job tasks to each other and relating project costs at the summary level of detail – Framework for specifying the objectives, labor, materials, and contracts of the system/program • Structure defining the total program/system • Detailed definitions of individual elements required • WBS varies by program and project phase Methodology • WBS Cost Element Structure (CES) • MIL-STD-881 B previously the Do. D standard Validation Reports Cost Prof – Now MIL-HDBK-881 B is guidance – Excellent resource for WBS components/content Unit I - Module 1 33
Purpose of a WBS Baseline Data Collection Data Analysis • Displays and defines the system/program to be developed as a product-oriented family tree – Includes hardware, software, support, and/or service elements – WBS should encompass complete life cycle of the system/program • CARD (or similar type of document) is the source for this program plan • Establishes the physical work packages or elements and the activities within those packages Methodology that completely define a project Validation – Organizes the physical work packages into levels that can be developed into a summary Reports Cost Prof Unit I - Module 1 34
Purpose of a WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Relates the work scope elements to each other and to the end product(s) – Makes the relationships of the components clear and the relationship of the tasks to be completed (to each other and to the end product) clear • Key to developing/tracking costs – Provides financial reporting framework – Assists in tracking the status of efforts, resource allocations, cost estimates, expenditures, and cost and technical performance Unit I - Module 1 15 35
Work Breakdown Structure (WBS) Early Development WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • WBS development should start early in the conceptual stages of the program – Provides structure to the design requirements and functional architecture • WBS evolves as system/program evolves – Evolves through iterative analysis of the development strategy, objectives and requirements – Define detailed technical objectives and specify work tasks for each WBS element Unit I - Module 1 36
Work Breakdown Structure (WBS) Continued Development WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • As the program/system matures – Engineering efforts focus on system-level performance requirements and top-level specifications – Major subsystems and configuration items are identified – WBS continues to be defined at lower levels – Eventually the total system definition is complete • During production, maintain and update the WBS • WBS Dictionary – Develop WBS dictionary while developing WBS – Should be routinely revised to incorporate changes and current status of the program throughout the program's life Tip: Dictionaries are often overlooked and are critical to use of a WBS Unit I - Module 1 37
Program/System Baseline Definition WBS Baseline Data Collection Data Analysis Methodology Validation • Program/system baseline definition encompasses all the information of a CARD • Process for defining program/system baseline – Determine the programmatic scope of estimate • Period to be estimated • Phases estimated – Determine the technical scope of estimate • Program requirements • Work not included • Deliverables Reports Cost Prof Unit I - Module 1 38
Program/System Baseline Definition WBS Baseline Data Collection Data Analysis Methodology Validation • Process for defining program/system baseline – Develop detailed system technical description • Include key performance characteristics, hardware/software components, architecture, configurations, reliability and security requirements, etc. – Include previously developed WBS – Develop detailed description of predecessor systems, if any • Include technical details, reason for replacing, legacy hardware/software, phase-out plan, etc. Reports Cost Prof Unit I - Module 1 39
Program/System Baseline Definition WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Process for defining program/system baseline – Determine manpower requirements • Include skills, salaries, location, etc. – Incorporate technical/performance, schedule, and cost risk • Determined by management and/or engineers – Define the operational concept • Include program management details, operation specifics, platforms – Determine deployment details • Include sites, schedules, special preparations, site configurations, transition plans, etc. Unit I - Module 1 40
Program/System Baseline Definition WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Process for defining program/system baseline – Detail logistics support 7 • Include maintenance, sparing, and upgrade plans – Define the training plan • Include types of training/certification, providers, locations, frequency, etc. – Establish the acquisition schedules • Include milestones, strategy, contracting details, etc. Unit I - Module 1 41
Program/System Baseline Definition WBS Baseline Data Collection Data Analysis Methodology Validation • Process for defining program/system baseline – Detail the system test and evaluation plan • Include schedule, number of tests, criteria, locations, etc. – Describe any environmental impacts • Include disposal concept, mitigation plans, conditions, materials, etc. – Maintain track to the original baseline • As programs mature, define changes Reports Cost Prof Unit I - Module 1 42
Data Collection and Analysis WBS Baseline Data Collection Data Analysis Methodology Validation • Data Collection – Obtaining data – Normalizing data 4 • Data Analysis 4 5 6 8 – Methods and process Tip: These two steps of the process go hand in hand are somewhat iterative. Reports Cost Prof Unit I - Module 1 43
Data Collection WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Understand total picture of estimating task – Intended use of the estimate – Scope of the estimate 4 • Establish cost element structure – Based on WBS • Understand estimating techniques and data collection needs – Identify proposed estimating technique(s) – Identify potential data sources Unit I - Module 1 44
Data Collection WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Develop data collection plan – Ensure sources identified for all needed cost elements – Identify alternative/backup data sources 4 – Identify sources for cross-checks – Establish a timeline/schedule • Collect the data • Normalize the data – Make data consistent and comparable – Types of normalization include Cost Units, Sizing Units, Key Groupings, State-Of. Development Variables, and End Terms for Homogeneity Unit I - Module 1 45
Data Analysis WBS • Scatter plot the data Baseline – Develop visual depiction of the 14 relationships in the data Data Collection • Calculate descriptive statistics Data Analysis Methodology Validation Reports Cost Prof 6 – For example, the means and CVs • Look for outliers – Points far from the center of the data • Compare to history – Standard factors, rules of thumb, other historical data Unit I - Module 1 46
Cost Element Methodology WBS Baseline Data Collection Data Analysis Methodology Validation • Select estimating methodology that most reliably estimates program costs • Primary cost estimating techniques or methodologies 2 16 – Analogy 3 8 – Parametric – Engineering build-up • Other methods – Expert opinion – Extrapolation from actuals Reports Cost Prof Unit I - Module 1 47
Estimate Development and Validation WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Develop estimate with appropriate costing techniques • Validate estimate – Crosscheck with historical data for similar 17 programs, another estimating methodology, or another model – Compare estimate with industry “rules of thumb” – Crosscheck proprietary models with Excel backups • Document estimate while developing Unit I - Module 1 48
Results and Report Generation WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Document the estimate – Written justification of the estimate – Well-documented estimate withstands scrutiny 13 and increases credibility – Provide sufficient information to replicate the estimate • Develop results and report at appropriate level of detail – – Crisp and complete Easy to comprehend Address important details Convey competence Unit I - Module 1 49
Results and Report Generation WBS Baseline Data Collection Data Analysis Methodology Validation Reports Cost Prof • Conduct other analysis – Cost As an Independent Variable (CAIV) • Making performance and schedule a function of available resources 16 – Sensitivity analysis • Tool for determining effect of changes for decisionmaking – Risk analysis • Analyzing technical, schedule, performance and other risks 9 • Used to adjust cost estimate • Final result is defendable cost estimate for decision making Unit I - Module 1 50
Cost Estimating Certification • So you want to be a cost analyst… – Society of Cost Estimating and Analysis (SCEA) offers the important professional certification Certified Cost Estimator/Analyst (CCE/A) – Combination of educational and job experience requirements (minimum 2 years) – CCE/A exam ($85) – More details on SCEA website (http: //www. sceaonline. net) under Certification Cost Prof Unit I - Module 1 51
Summary • Rigorous and systematic estimating leads to a better understanding of the problem • Quality and accuracy depend on the expertise of the estimator – Estimator must understand complexity, technology, and programmatic issues • Don’t lose sight of the forest for the trees – Leaving out components – Double-counting components – Forgetting integration costs • Ability to reproduce the estimate • Estimator must understand all estimating methods applied Cost Prof Unit I - Module 1 52
Resources • Cost Estimating Handbook, 2 nd ed. , Rodney D. Stewart, Wiley, 1991 • Engineering Cost Estimating, 3 rd ed. , Phillip F. Ostwald, Prentice-Hall, 1991 • Do. D MIL-HDBK-881 “Work Breakdown Structure, ” 02 Jan 1998 Cost Prof Unit I - Module 1 53
Resources – Agencies • Oversight agencies – NCCA, http: //www. ncca. navy. mil – CEAC, http: //www. ceac. army. mil – AFCAA, http: //www. saffm. hq. af. mil/afcaa • NCCA Cost Analysis 101 – http: //www. ncca. navy. mil/about/101. cfm • Budget/financial organizations – – Cost Prof GAO, http: //www. gao. gov OMB, http: //www. whitehouse. gov/omb USD(C), http: //www. dtic. mil/comptroller DCAA, http: //www. dcaa. mil Unit I - Module 1 54
Resources – Regulatory • Title 10, United States Code, Section 2434 – Independent Cost Estimates; Operational Manpower Requirements • Clinger-Cohen Act of 1996 Cost Prof Unit I - Module 1 55
Resources – Regulatory • Title 10, United States Code, Section 2434 – Independent Cost Estimates; Operational Manpower Requirements • Clinger-Cohen Act of 1996 Cost Prof Unit I - Module 1 56
Resources – Regulatory • Title 10, United States Code, Section 2434 – Independent Cost Estimates; Operational Manpower Requirements • Clinger-Cohen Act of 1996 Cost Prof Unit I - Module 1 57
Resources – Policy • Do. DD 5000. 1, Do. DI 5000. 2 “Defense Acquisition System, ” 23 October 2000 (incl Change 1, 4 Jan 2001) • Do. D 5000. 2 -R “Mandatory Procedures for MDAPs and MAIS Acquisition Programs, ” 11 Jun 2001 – http: //www. acq. osd. mil/ar/library. htm#directives • Do. DD 5000. 4 “OSD Cost Analysis Improvement Group (CAIG)” • Do. D 5000. 4 -M “Cost Analysis Guidance and Procedures, ” 11 Dec 1992 – http: //www. dtic. mil/whs/directives/corres/html/50004 m. htm • Do. DI 7041. 3 – Economic Analysis and Program Evaluation for Resource Management Cost Prof Unit I - Module 1 58
Resources – Policy • Do. DD 5000. 1, Do. DI 5000. 2 “Defense Acquisition System, ” 23 October 2000 (incl Change 1, 4 Jan 2001) • Do. D 5000. 2 -R “Mandatory Procedures for MDAPs and MAIS Acquisition Programs, ” 11 Jun 2001 – http: //www. acq. osd. mil/ar/library. htm#directives • Do. DD 5000. 4 “OSD Cost Analysis Improvement Group (CAIG)” • Do. D 5000. 4 -M “Cost Analysis Guidance and Procedures, ” 11 Dec 1992 – http: //www. dtic. mil/whs/directives/corres/html/50004 m. htm • Do. DI 7041. 3 – Economic Analysis and Program Evaluation for Resource Management Cost Prof Unit I - Module 1 59