Cost Control Do project managers control costs monitor
- Slides: 60
Cost Control
Do project managers control costs, monitor costs or both?
Cost Management Cost estimating v Cost accounting v Project cash flow v Company cash flow v Direct labor costing v Overhead rate costing v Others, such as incentives, penalties, and profit-sharing v
Cost And Control System PLANNING PHASE I PLANNING CYCLE WORK DATA AUTHORIZATION COLLECTION AND RELEASE AND REPORTING PHASE III COST ACCOUNTING PHASE IV OPERATING CYCLE CUSTOMER AND MANAGEMENT REPORTING PHASE V
Cost Control Requirements Measure resources consumed v Measure status and accomplishments v Compare measurements to projections and standards v Provide the basis for diagnosis and replanning v
Cost Control Requirements Thorough planning of the work to be performed to complete the project v Good estimating of time, labor, and costs v Clear communication of the scope of required tasks v A disciplined budget and authorizations of expenditures v Timely accounting of physical progress and cost expenditures v Periodic re-estimation of time and cost to complete remaining work v
Cost Control Requirements (Continued) v Frequent, periodic comparison of actual progress and expenditures to schedules and budgets, both at the time of comparison and at project completion
WHEN TO IMPLEMENT A COST MANAGEMENT SYSTEM Possible cost reductions Cost of change PROJECT COSTS PROJECT LIFE CYCLE PHASES CONCLUSION A cost management system should be implemented right at the beginning of the life cycle of the project.
Partitioning The Budget
The Work Authorization Form
Work Authorization Form WBS: 31. 03. 02 Work order no: D 1385 Date of original release: Date of revision: Revision number: Description - Test Material - Processing - Final inspection - Packaging - Delivery Cost Centers 2400 2610 2621 2623 2624 03 Feb 97 18 March 97 C Hours 150 160 140 46 Cost R 4500 R 7500 R 3500 R 750 R 350 Work Starts 1 Aug Work Ends 15 Sept Project office authorization signature: ________
PLANNING AND BUDGETING WBS Element Work packages M G R Org Org Work Package WP______ORG_______ Description of task__________ Sched: Start____Stop__ Budget: _______
COST ACCOUNT CHANGE NOTICE (CACN) CACN No. _______ Revision to Cost Account No. ______ Date ______ DESCRIPTION OF CHANGE: ____________________________________________________________________________________ REASON FOR CHANGE: ____________________________________________________________________________________ _________________________________________ Labor Hours Materials ODCS Requested Budget _________________ Authorized Budget _________________ Period of performance From _______ To _______ BUDGET SOURCE: Funded Contract Change Management Reserve Undistributed Budget Other _________ INITIATED BY: ______________ APPROVALS: Program Mgr. ____ Prog. Control ____
Sources Of Additional Funding v Funded contract change v Management reserve v Undistributed budget v Other (e. g. profits)
Cost data collation and reporting flow chart Actuals Labor Monthly Total Program Effort BCWP Weekly Labor Reports ACWP Inventory Accounts Computer MCCS Comparison reports To All Execs BCWS Variance Report
Cost Data Labor v Material v Other direct charges v Overhead v
Types of Budgets Distributed budget v Management budget v Undistributed budget v Contract changes v
Variance Analyses
VARIABLES FOR VARIANCE ANALYSIS v BUDGETED COST FOR WORKED SCHEDULED (BCWS) IS THE BUDGETED AMOUNT OF COST FOR WORD SCHEDULED TO BE ACCOMPLISHED PLUS THE AMOUNT OF LEVEL OF EFFORT OR APPORTIONED EFFORT SCHEDULED TO BE ACCOMPLISHED IN A GIVEN TIME PERIOD. v BUDGETED COST FOR WORK PERFORMED (BCWP) IS THE BUDGETED AMOUNT OF COST FOR COMPLETED WORD, PLUS BUDGETED FOR LEVEL OF EFFORT OR APPORTIONED EFFORT ACTIVITY COMPLETED WITHIN A GIVEN TIME PERIOD. THIS IS SOMETIMES REFERRED TO AS AN “EARNED VALUE. ” v ACTUAL COST FOR WORK PERFORMED (ACWP) IS THE AMOUNT REPORTED AS ACTUALLY EXPENDED IN COMPLETING THE WORK ACCOMPLISHED WITHIN A GIVEN TIME PERIOD. v COST VARIANCE = BCWP – ACWP v SCHEDULE/PERFORMANCE VARIANCE = BCWP - BCWS
Variances The cost variance compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished. v The scheduling variance provides a comparison between planned and actual performance but does not include costs. v
Measurements Measurable efforts: discrete increments of work with a definable schedule for accomplishment, whose completion produces tangible results. v Level of effort: work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support and project control. v
COST VARIANCE CALCULATION CV = BCWP - ACWP A NEGATIVE VARIANCE INDICATES A COST OVERRUN
SCHEDULE VARIANCE CALCULATION SV = BCWP - BCWS A NEGATIVE VARIANCE INDICATES A BEHIND SCHEDULE CONDITION
VARIANCE PERCENTS SCHEDULE VARIANCE % (SVP) COST VARIANCE % (CVP) = = SV BCWS X 100 CV BCWP X 100
Project Variance Analysis VARIANCE UPPER BOUNDARY PROJECTED COST $ ACTUAL COST VARIANCE LOWER BOUNDARY R&D PHASE I QUALIFICATION PHASE II TIME DEVELOPMENT PHASE III
Trend Analyses
Management Reserve CONTRACTED COST MANAGEMENT RESERVE ACTUAL COST $ RELEASED BUDGET TIME
Information Requirements v v v v Budgeted cost for work scheduled (BCWS) Budgeted cost for work performed (BCWP) Actual cost for work performed (ACWP) Estimated cost at completion Budgeted cost at completion Cost and schedule variances/explanations Traceability
Variance Analysis Questions What is the problem causing the variance? v What is the impact on time, cost, and performance? v What is the impact on other efforts, if any? v What corrective action is planned or under way? v What are the expected results of the corrective action? v
VARIANCE REPORTING Variance reporting is accomplished at each reporting interval. However, the variance threshold reports are exception reports and occur only when the variances exceed the upper and lower boundaries of the project variances envelope.
REPORTING INTERVALS Depends on the type of organization and characteristics of the projects. v Project-driven organization - weekly. v Non-project-driven organization - monthly v
Cost Account Variance Analysis Report Cost account no/cam WBS/Description Cost performance data BCWS Variance BCWP ACWP SCHED COST Month to date ($) Contract to date ($k) Reporting level As of At completion Budget EAC Var. Problem cause and impact Corrective action (including expected recovery date) Cost account Date Cost center Date WBS element Date Mgr. Date
The 50/50 rule HALF OF THE BUDGET FOR EACH ELEMENT IS RECORDED AT THE TIME THAT THE WORK IS SCHEDULED TO BEGIN AND THE OTHER HALF AT THE TIME THE WORK IS SCHEDULED TO BE COMPLETED. FOR A PROJECT WITH A LARGE NUMBER OF ELEMENTS THE AMOUNT OF DISTORTION FROM SUCH A PROCEDURE IS MINIMAL.
ANALYSIS Budgeted cost for work Budget - 6 Scheduled (BCWS) Performed (BCWP) Cost account budget = 100 (thousands) 8 14 12 10 Work packages 12 8 BCWS = 38 BCWP = 49 SCHED. VARIANCE = +11 12 10 8 50 -50 rule used for work in process J F M A M J J A S O N D
Using The 50 -50 Rule 4, 000 TIME LINE 10, 000 LEGEND 12, 000 COMPLETED 4, 000 NOT COMPLETED 6, 000 BCWS = 34, 000 BCWP = 33, 000 BAC = 52, 000 6, 000 10, 000 TIME
Earned Value Status Reporting CUMMULATIVE COST, $ TIME LINE BCWS ACWP SV CV BCWP TIME
Estimated Cost At Completion
ESTIMATE AT COMPLETION (EAC) EAC = ACWP X Budget at completion BCWP (BAC) The estimate at completion is the best estimate of the total cost at the completion of the project. The EAC is a periodic evaluation of the status of the project - usually on a monthly basis or until a significant change has been identified.
PROGRESS REPORTING Progress reporting needs to answer four fundamental questions: 1. Where are we today (time and cost)? 2. Where will we end up (time and cost)? 3. What are the present and future risks? 4. Are there any special problems that need to be addressed and what can management do to help?
Monthly Project Report 1. VARIANCE ANALYSIS (Cost in Thousands) Milestone Subtask Status 1 June 1997 Budgeted Cost Work Actual Scheduled Performed Cost Variance, Schedule % Cost 1 2 Completed 100 100 0 0 Completed 50 50 55 0 -10 3 Completed 50 50 40 0 20 4 Not Started 70 0 0 -100 5 Completed 90 90 140 0 6 Not started 40 0 0 -100 -- 7 Started 50 50 25 0 50 8 Not started 0 0 0 -- -- 450 340 360 -24. 4 -5. 9 Total --55. 5
2. ESTIMATE AT COMPLETION (EAC) EAC = (360/340) X 579, 000 = $613, 059 Overrun = 613, 059 - 579, 000 = $34, 059 3. COST SUMMARY Costs are running approximately 5. 9% over budget due to higher salaried labor. 4. SCHEDULE SUMMARY The 24. 4% behind schedule condition is due to subtasks 4 and 6 which have not yet begun due to lack of raw materials and the 50/50 method for booking costs. Overtime will get us back on schedule but at an additional cost of 2. 5% of direct labor costs.
5. MILESTONE REPORT Milestone/ Scheduled Subtask Completion 1 4/1/97 2 5/1/97 3 5/1/97 4 7/1/97 5 6/1/97 6 8/1/97 7 9/1/97 8 10/1/97 Projected Completion Actual Completion 4/1/97 5/1/97 4/23/97 7/1/97 6/1/97 8/1/97 9/1/97 10/1/97
6. ACTIVITY REPORT Current Potential Corrective Problem Impact Action (a) Lack of raw Cost overruns and Overtime is scheduled. materials. (b) Customer unhappy with test results. behind schedule condition. May need additional planning. We will try to use lower salaried staff. Raw materials are expected to be on dock next week. Customer will provide us with revised statement of work on 6/15/97.
Status Reporting Is More Than Just A Computer Printout.
Intranet Status Reporting
Reporting Favorable Status
Reporting Unfavorable Status
DATA ACCUMULATION Organization WBS Budget BCWS SCHED VAR BCWP ACWP COST VAR
Cutting The Budget
Financial Close-Out
Cost Problems Poor estimating techniques and/or standards, resulting in unrealistic budgets v Out-of-sequence starting and completion of activities and events v Inadequate work breakdown structure v No management policy on reporting and control practices v Poor work definition at the lower levels of the organization v
Cost Problems (Continued) Management reducing budgets or bids to be competitive or to eliminate “fat” v Inadequate formal planning that results in unnoticed, or often uncontrolled, increases in scope of effort v Poor comparison of actual and planned costs v Comparison of actual and planned costs at the wrong level of management v Unforeseen technical problems v
Cost Problems (Continued) Schedule delays that require overtime or idle time costing v Material escalation factors that are unrealistic v
Problem Areas in Cost Control v Organization: v - Inadequate Work Breakdown Structure - Poor work definition at working levels - Lack of formal system procedures Planning and budgeting: - Inadequate forward planning v - Over-allocation of budget - Poor integration of budget, schedule, work authorization Accounting: v - Inability to account for cost of material on applied basis Analysis: v - Determination of status not based on work package completion - Comparison of actual vs. planned costs at improper level Revisions: - Failure to maintain valid measurement baseline
Cost Problems Per Phase v Proposal Phase – Failure to understand customer requirements – Unrealistic appraisal of in-house capabilities – Underestimating time requirements
Cost Problems Per Phase v Planning phase – – – Omissions Inaccuracy of the work breakdown structure Misinterpretation of information Use of wrong estimating techniques Failure to identify and concentrate on major cost elements – Failure to assess and provide for risks
Cost Problems Per Phase v Negotiation phase – Forcing a speedy compromise – Procurement ceiling costs – Negotiation team that must “win this one”
Cost Problems Per Phase v Contractual phase – Contractual discrepancies – SOW different from RFP requirements – Proposal team different from project team
Cost Problems Per Phase v Design phase – Accepting customer requests without management approval – Problems in customer communications channels and data items – Problems in design review meetings
Cost Problems Per Phase v Production phase – Excessive material costs – Specifications that are not acceptable – Manufacturing and engineering disagreement
- Cost control and cost reduction project report
- Cost control and cost reduction project report
- Profit and loss statement
- Monitor and control project work
- Cost control and cost reduction difference
- Cost control and cost reduction difference
- Cost incurrence
- The flow of costs in a job order cost system
- Project managers typically perform the tasks of
- Kytc project managers toolbox
- Project cost control
- The control process begins when managers set goals.
- Management control program
- Plan monitor control cycle
- Plan monitor control cycle
- Cost accumulation and cost assignment
- Cost accumulation and cost assignment
- Manufacturing cost vs non manufacturing cost
- Job order vs process costing
- Flotation cost in cost of equity
- Non controllable cost
- Cost accumulation and cost assignment
- Manufacturing cost vs non manufacturing cost
- Material price variance
- Cost of equity
- Cost accumulation and cost assignment
- Objectives of standard costing
- Literal cost gate input cost
- Distinguish between average cost and marginal cost
- The flow of costs in job order costing
- Ordering cost and carrying cost
- Literal cost gate input cost
- Literal cost gate input cost
- Opportunity costs and trade offs
- Cost behavior and cost-volume-profit analysis
- Cost management presentation
- Contoh cost control
- Reasons for reducing project duration
- Project cost duration graph
- Project cost breakdown
- Cost estimation table
- Cost control objectives
- Markstrat r&d strategy
- Principles of cost management
- Qm for windows
- Importance of project cost management
- Contoh cost baseline
- Pmi intranet
- Project cost duration graph
- Project cost management lecture notes
- Project cost duration graph
- Project cost
- Cost management pmp
- Estimating project time and cost
- Expedited cost
- Estimating project time and cost
- Lotfi gaafar
- Shrimp farm layout
- Pro forma statement of cash flows
- Authentic project proposal
- Writing a strategy