Concho River Improvements February 18 2014 River Improvements
Concho River Improvements February 18, 2014
River Improvements Project • Consideration of approving matters related to Concho River improvements: • Review financial information associated w/ construction project; • Approval of change order 16 to include: the repairs of the supporting columns of the pedestrian bridge west of Abe Street; replacement of the decking of the pedestrian bridge east of Koenigheim; and installation of 8 additional LED lights under Abe and Koenigheim Bridges under the agreement with Templeton Construction Co. , Inc. , Project PK-05 -10 in the amount of $148, 642. 88, and requesting approval of said amount to be funded by remaining and unused contract funds for the river project construction previously approved by City Council
River Improvements Project • Discussion and consideration of approving a conceptual design and budget for the expanded games court area (“The Bosque”) and authorizing staff to proceed with finalizing designs with Kinney Franke Architects for the improvements. • Discussion and consideration of authorizing staff to solicit request for proposals for operation of the concession and games court area (“The Bosque”).
River Improvements Project a. Review financial information associated w/ construction project;
River Improvements Project • Construction Manager at Risk: Templeton Construction Co. , Inc. • Time Summary • Contract Date: Oct. 1, 2011 • Completion Date: substantial completion Sept. 12, 2013 • Budget Summary • Original project budget = $9, 300, 000 • Total net change orders to date = $820, 432 • Project budget = $10, 120, 432 • Cost to date = $9, 824, 797 • Retainage held to date (0. 0025%) = $25, 000 • Cost to date (less retainage) = $9, 797
River Improvements Project
River Improvements Project b. Approval of change order 16 to include: the repairs of the supporting columns of the pedestrian bridge west of Abe Street; replacement of the decking of the pedestrian bridge east of Koenigheim; and installation of 8 additional LED lights under Abe and Koenigheim Bridges under the agreement with Templeton Construction Co. , Inc. , Project PK-05 -10 in the amount of $148, 642. 88, and requesting approval of said amount to be funded by remaining and unused contract funds for the river project construction previously approved by City
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project c. Discussion and consideration of approving a conceptual design and budget for the expanded games court area (“The Bosque”) and authorizing staff to proceed with finalizing designs with Kinney Franke Architects for the improvements.
River Improvements Project Goals for the development of “The Bosque”: • to enhance the games court area, reflecting on the past miniature golf course and looking to the future – new concession, food trucks, etc. and • to provide economic potential for a partnering entrepreneur balanced with open public space and amenities.
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project
River Improvements Project “The Bosque” games court area improvements:
River Improvements Project
River Improvements Project d. Discussion and consideration of authorizing staff to solicit request for proposals for operation of the concession and games court area (“The Bosque”).