Composite Filament Winding RIT Multidisciplinary Design Project P 09226 Shijo George, Alex Sandy, Tiago Santos, Christofer Brayton, Daniel Weimann www. thaicomposites. com
Project Background • Composite Tubing – Carbon Fiber, Fiberglass, Kevlar – Benefits • High strength • Light weight • High creep and fatigue performance • Chemical and corrosion resistance – Uses • • Drive shaft/half shaft Golf Clubs Pipes Pressure vessels
Filament Winding • Continuous strand of impregnated fibers wound onto a mandrel • Often computer controlled • Mandrel may be removed post cure
Project Goals • Capability – Develop filament winding within department – Base for future senior design teams • Composite tube – Variable length – Variable wrap angle • Machine – Robust expandable design – Simple partially automated operation • Test – Compare theoretical and experimental results • Risks – Budget • $2000 Preliminary budget – Design • Integration – Control structure • Resin Impregnation • Tension • Fiber Slip – Time • 2 quarters • 11 week build/test • Part lead time
Team Roles P 09226 Creel Tension Resin Bath Feedeye Mandrel Motors Shijo (ME) Dan (ME) Alex (ME) Tiago (ME) Shijo (ME) Alex (ME) Chris (EE) Tiago (ME) Dan (ME) Shijo (ME) Controls Chris (EE)
Responsibilities • Feedeye – Lead screw calculations – Carriage, mounting • Tension – Explore capabilities • Electromagnetic Brake • Motor Brake – Work with Chris (EE) to ensure control • Mandrel – Lathe condition • Chuck, Tailstock • Solid Modeling
Project Plan • Detailed Design Review • Senior Design 2 – Multiple reviews 2/92/18 – Build Stage • Executive Review – 2/20 • Finalized Parts List – 2/25 • Working Machine 4/24 – Testing • 4/27 – 5/1
Desired Outcome • Develop capability • Base for further within department development – Senior Design • Create composite wound • Increase Spools tube – Repeatable – Confirmable through testing • Advanced controls • Multi-axis
Closing Questions ? Contact Information Daniel Weimann DSW 1104@rit. edu 724 -454 -9622 32 Avondale Park Rochester NY 14620