Collimation Upgrade Plan Questions R Assmann CERN for



































- Slides: 35

Collimation Upgrade Plan & Questions R. Assmann, CERN for the collimation team 14/6/2011 LHC Collimation Project Review 6/14/11

LHC Collimation as Staged System • LHC collimation was conceived in 2003 as a staged system. • Phase 1: – For initial beam commissioning and early years of LHC operation. – Predicted not adequate for nominal and ultimate intensity. – Designed, constructed and commissioned 2003 – 2009. • Phase 2: – Upgrade for nominal, ultimate and higher beam intensities. – Solves issues in efficiency, impedance and radiation impact. – Originally not clear what the solution would be. – By now various upgrade solutions worked out and under design. • IR upgrade: – Adaptation to changes in IR upgrades: space and losses. – Adaptation to phase space modifications (ATS, crab cavities). 6/14/11

Overall Collimation Upgrade Plan (as defined in 2009) Interim collimation system (2014 – 2016) Inefficiency: 0. 002 % (p) b* ~ 1 – 2 m, 7 Te. V Gain ~100 in R 2 E (IR 7 IR 3) L ≤ 5 × 1033 cm-2 s-1 nominal ion intensity > 2 days per setup 2017 shutdown: IR(1)/2/(5)/7 DS Phase 2: integrated BPM’s, robust materials, red. impedance. Radiation opt. 2013 shutdown: IR 3 DS combined cleaning, IR 2 TCT’s, TCLP installation? Initial collimation system (2009 – 2012) Inefficiency: 0. 02 % (p) b* ~ 1 – 1. 5 m, 3. 5 Te. V R 2 E limits in IR 7? > 4 days per setup 6/14/11 Full collimation system (2018 onwards) Inefficiency: 0. 0004 % (p) b* ~ 0. 55 m, 7 Te. V L not limited (p and ions) 30 s per high accuracy setup Radiation optimization 2021 shutdown: tbd Collimation IR Upgrade (2022 onwards) Low b*, 7 Te. V TCT’s integrated into IR upgrade Compatibility with crab cavities

Prepared, Empty Secondary Collimator Slots for Phase 2 SLAC design PHASE I TCSG SLOT 1 st advanced phase 2 collimator CERN EMPTY PHASE II TCSM SLOT (30 IN TOTAL) 6/14/11

Luminosity Triplet aperture and collimation setup accuracy R. Bruce 6/14/11 Beambeam, brightness & robustness limits A. Dallocchio (new materials) Loss limits: collimation, (UFO’s), … D. Wollmann, A. Rossi, G. Bellodi

• Good news: – Available aperture about 50% larger than guaranteed by design (smaller orbit errors, better alignment, …). Gain here for luminosity! – Optics very well controlled (5 -10% beta beat, … for b* = 1. 5 m). Gain here! • As expected: – Very challenging to achieve collimation & protection tolerances (only infrequent setups possible, drifts over months, …) b* limited. – Addressed by collimators with integrated beam position pickups (almost all to be equipped). Not discussed in details for this review. 6/14/11

• Good news: – Collided successfully three times nominal brightness (head-on). Long-range beam-beam soon to be checked. Gain factor 3 here, if LR beam-beam OK as well! • Under study: – Robustness of collimators for the high achieved brightness. Simulation of realistic scenarios, tests in Hi. Rad. Mat facility starting in autumn. – Development of more robust collimator materials ( Eu. CARD/Col. Mat program since 2009, report A. Dallocchio). – Not discussed in details for this review. 6/14/11

• Good news: – Since middle of May: ~ complete experimental assessment at 3. 5 Te. V done. – Reached the design 500 k. W peak beam loss (protons) at primary collimators without quench of a super-conducting magnet! – Reached 80 MJ without a single quench from stored beam losses. – Transverse damper stabilizes beam at 3. 5 Te. V high impedance OK. – Reached 99. 995% collimation efficiency with 50% smaller gaps than design (low emittance, high impedance) and due to much less impact of imperfections than predicted (better orbit, lower beta beat, …). – Minimum beam lifetime at 3. 5 Te. V is ~4 times better than specified. 6/14/11

Collimation of High Power Loss No quench of any magnet! 6/14/11

Ultra-High Efficiency 99. 960 % worse 99. 995 % MD better 6/14/11

Achieved Stored Energy: 80 MJ 80 kg TNT 6/14/11

Stored Energy Compared to 2010 Goals 6/14/11

Therefore some questions I • It runs so well: Do we really need to invest a lot of work for a better collimation efficiency in the first long LHC shutdown (2013/14)? • Do operational experience and MD measurements not prove to us sufficiently well that we can reach nominal 7 Te. V luminosity in 2014/15 (with the efficiency of the present collimation system)? • Do the potential gains in b* and beam brightness (beam-beam) not provide an additional margin to increase luminosity (without pushing stored energy)? Reference p goal 2014 – 2017: L ≥ 1 × 1034 cm-2 s-1 at 7 Te. V Could be reached with ~50% of nominal intensity? 6/14/11

On the Other Side • Predicted leakage mechanisms and locations are fully confirmed, both for protons and ions. • Proposed upgrade plan will gain factor ~10 in efficiency: can be used for higher stored energy and/or larger collimation gaps (relaxed tolerances and lower impedance). Lowest risk approach. • All experience relies on 3. 5 Te. V beam energy (higher quench margin, larger collimation gaps, lower impedance, easier operation for transverse damper, lower cross-section single-diffractive scattering, …). • All experience relies on operation with 1/2 of nominal emittance (50 ns) beam core far away from jaw surface, lower loss spikes, more room to close collimator gaps. • It is assumed that 7 Te. V beam is as stable as 3. 5 Te. V, that quench limits and efficiency scale as predicted and that losses do not become more localized at 7 Te. V. 6/14/11

Protons: Simulations vs Measurement Cleaning Inefficiency B 1 v, 3. 5 Te. V, β*=3. 5 m, IR 7 B 1 Measured Simulated (ideal) Losses in SC magnets understood: location and magnitude 6/14/11

3. 5 Te. V: Luminosity Operation Collimation IR 7 CMS ATLAS Collimation IR 3 LHCb Collimation IR 6 Fill #1645, 200 bunches, 2. 4 e 13 p per beam, peak luminosity 2. 5 e 32 6/14/11

Origin of Dispersion Suppressor Losses Coll on energy Collision p–C Coll. Mat. Collision p–p Pb – Pb Quad Coll Quad Dipole Dip ole on energy Quad Coll off energy 6/14/11 Coll Dipole Dip ole

Zoom IR 7 (and illustration of 2013 upgrade for IR 3) D. Wollmann, G. Valentino, F. Burkart, R. Assmann, … 6/14/11

Proton losses phase II: Zoom into DS downstream of IR 7 99. 997 %/m 99. 99992 %/m quench level Very low load on SC magnets less radiation damage, much longer lifetime. Simulation T. Weiler Impact pattern on cryogenic collimator 2 Impact pattern on cryogenic collimator 1 imu n o i lat S 6/14/11 Cryo-collimators can be one-sided!

better WARNING: Grid simulation here for nonnominal optics and perfect machine! Impedance Target Phase 1 R. Assmann T. Weiler E. Metral (full octupoles, no transv. feedback, nominal chromaticity) Phase 1 Target Inefficiency (nominal intensity, design peak loss rate) Gap × 1. 5 × 2 Impedance Target Phase 2 (full octupoles, no transv. feedback, nominal chromaticity) Acceptable Area × 1. 2 better Ideal Inefficiency [1/m] Better Efficiency and/or Lower Impedance Phase 2 Installation of collimation phase II including collimators in cryogenic dispersion suppressors 6/14/11 Impedance Increase gaps by factor 1. 5 Nominal I. Larger triplet/IR aperture or lower b*

Ions: Beam 2 Leakage from IR 7 Collimation (much worse, as expected) 6/14/11

Therefore some questions II • Can the upgrade of the IR 3 dispersion suppressors be delayed without any danger for magnet lifetime (SC magnets as halo dumps)? • Is later upgrade work feasible in dispersion suppressors (activation)? • Are we sufficiently sure about 7 Te. V beam behavior to give up the improvement in collimation efficiency and/or impedance for 2014? • Is the presently predicted “proton” safety factor ~4 above nominal intensity big enough ( assumptions and energy scaling)? • Do we need an upgrade of the IR 3 dispersion suppressors for reaching nominal ion luminosity? • Will a delay of the IR 3 dispersion suppressors lead to unacceptable knock -on effects for other dispersion suppressor work (IR 2 for ions, IR 1/5 losses into dispersion suppressors, …)? • Will decision force us to work with small emittances (impact on 25 ns)? 6/14/11

Overall Collimation Plan (possible modification, acceptable risk? ) Initial collimation system (2014 – 2016) Inefficiency: 0. 005 % (p) b* ~ 1 – 2 m, 7 Te. V Gain ~100 in R 2 E (IR 7 IR 3) L ~ 1 × 1034 cm-2 s-1 Ion intensity and lumi limits > 2 days per setup 2017 shutdown: IR(1)/2/3/(5)/7 DS Phase 2: integrated BPM’s, robust materials, reduced impedance. Radiation opt. IR 2 TCT’s, combined cleaning IR 3, TCLP installation? Initial collimation system (2009 – 2012) Inefficiency: 0. 005 % (p) b* ~ 1 – 1. 5 m, 3. 5 Te. V R 2 E limits in IR 7? > 4 days per setup 6/14/11 Full collimation system (2018 onwards) Inefficiency: 0. 0004 % (p) b* ~ 0. 55 m, 7 Te. V L not limited (p and ions) 30 s per high accuracy setup Radiation optimization 2021 shutdown: tbd Collimation IR Upgrade (2022 onwards) Low b*, 7 Te. V TCT’s integrated into IR upgrade Compatibility with crab cavities

Conclusion • Equipping the IR 3 dispersion suppressors with collimators improves the performance reach for LHC and has the lowest risk for LHC performance. It was defined as a minimal plan some years ago. • There a number of recent good news at 3. 5 Te. V in collimation and other LHC areas that must be taken into account: – It opens the possibility to discuss delaying the IR 3 collimation upgrade in the dispersion suppressors by three years. – Some important issues were summarized and some questions put up that require attention and advice. – Subsequent talks will go into more details. • Predicting performance at 7 Te. V is tricky and quite involved: loss spikes, quench limit, nuclear physics p/ions, energy deposition details, small collimation gaps, high impedance, … • Your advice is very much welcome! 6/14/11

Additional Info 6/14/11

Origin of Losses in Dispersion Suppressor • Effect understood and predicted as early as 2003. • Collimators in straight sections “generate” off-momentum p and ions (effectively). • Off-momentum particles pass through straight sections and are deflected by first dipoles in dispersion suppressors. • Downstream magnets act as offmomentum halo beam dump. • SC regions off-hands: Impossible to put collimators in dispersion suppressors (as in LEP). 6/14/11 • Clear physics sources: p have single-diffractive scattering in matter, ions dissociate/fragment! • Now confirmed by experimental data (also in horizontal plane). • Loose factor ~10 with nonsmooth aperture (alignment)!

p – C Interaction: Multiple Coulomb & Single-Diffractive Scattering 6/14/11

Analytically Derived Simple Scaling Law (E 0 = 1 Te. V) R. Assmann, Proc. HE-LHC Workshop 6/14/11 MCS SD

Monte-Carlo Simulation of Realistic Beam Halo and Interactions 6/14/11

Why Off-Energy Hadrons can be so Disturbing (A) Ve • Loss pattern cannot be compared to case of point scatterers like UFO’s or wire scanners very diluted showers. • Off energy hadrons produce a very sharp impact line. • BLM’s cannot distinguish the two cases! • Important uncertainties about BLM response and thresholds with such a concentrated loss. • Plan quench tests for this case. 6/14/11 (A) ry d low risk iluted Very for que Interaction nch “Fixed” by rela x limits ( small T ing BLM ) Halo/shower (B) Con centrat ed UFO) Hscatterer Point losses igh risk (e. g. f or quen Protect ch by tigh t limits ( medium BLM Interaction – large Halo/shower T) Low energy tail after V bend

3. 5 Te. V: Losses in DS of IR 5 (CMS) Fill #1647, 200 bunches, 2. 4 e 13 p per beam, peak luminosity 2. 5 e 32 6/14/11

Simple Extrapolation of Losses in Dispersion Supressor of IR 5 Parameter Fill #1645, 3. 5 Te. V 7 Te. V scaled Luminosity 0. 025 × 1034 cm-2 s-1 1 × 1034 cm-2 s-1 Loss @ BLM 3. 1 × 10 -6 Gy/s 2. 4 × 10 -4 Gy/s Limit @ BLM 5 × 10 -4 Gy/s ~3 × 10 -4 Gy/s Int. loss @ BLM for 200 d at 0. 039 k. Gy/y 3. 1 k. Gy/y 75% efficiency Int. peak loss magnet coil ? ? (must be much higher) Limit for int loss in dipole Note: Clear c Does not include significant loads from ion operation. NOT A onclusion: Does not include effect of b*. T ALL C O Does not include steeper scaling of losses with lumi (up to factor 5 MFO RTAB higher paper Annika Nordt). Win with monitor factor? LE! Should be able to gain something with TCL/TCLP collimators (cannot fix problem due to zero dispersion). In the past strong concerns about dipoles with this load (K. H. Mess). Now OK? 6/14/11

Quench Limit vs Energy 6/14/11

Where to Find Links to Info (New and Old)? https: //espace. cern. ch/lhc-collimation-workspace Links to past meetings, minutes, presentations, … 6/14/11

Where to Find or Put Reference Info for Upgrade? https: //espace. cern. ch/lhc-collimation-upgrade Minutes from collimation upgrade management meetings, agreed production and installation, tables, agreed planning, safety, … 6/14/11
Tisiogena
Database upgrade project plan
Utwente
Marine sextant
Collimation error
Star test collimation
And a modular collimation system
Microsoft server
Visio 2010 updates
Upgrade image quality
Rhel 6 to 7 upgrade
Remedy upgrade
Cisco ise upgrade readiness tool
Cisco ios upgrade planner tool
Vip seat vue
Caloundra bruce highway upgrade
Windws update
Cisco ap 컨트롤러형 설정
Past perfect after
Getting a license illegally may result in
Gfs upgrade
Hg6246r
Maximo upgrade resources
Define upgrade advisor
Maximo anywhere training
Cisco ios upgrade planner tool
Backup exec 21
Aec 09
Upgrade bene
Siebel upgrade process
Planning a network upgrade
Maximo upgrade
Upgrade ake
Maximo upgrade process
Network upgrade proposal
Thor johnsen