CMS OPENING 3. 74 m (scenario N 1) 2

CMS OPENING 3. 74 m (scenario N 1) 2

Radiation shielding. Main support. Traverse 3

Radiation shielding. Main support. Traverse 3

Main support. Parameter drawing 4

Main support. Parameter drawing 4

Access platform 5

Access platform 5

Access platform 6

Access platform 6

Main support-options 7

Main support-options 7

The frame for attach main support onto concrete block 8

The frame for attach main support onto concrete block 8

The frame for attach main support onto concrete block 9

The frame for attach main support onto concrete block 9

The frame for attach main support onto concrete block 10

The frame for attach main support onto concrete block 10

Main support installation TEST Very preliminary 11

Main support installation TEST Very preliminary 11

BP radiation shielding. Parameter motivation 12

BP radiation shielding. Parameter motivation 12

BP radiation shielding. Parameter motivation 13

BP radiation shielding. Parameter motivation 13

BP radiation shielding. Parameter motivation 14

BP radiation shielding. Parameter motivation 14

BP shielding installation. Step by step 15

BP shielding installation. Step by step 15

BP radiation shielding installation. Parameter drawings 16

BP radiation shielding installation. Parameter drawings 16

17

17

BP radiation shielding. Parameter drawings 18

BP radiation shielding. Parameter drawings 18

Beam pipe shielding. Parameter drawing (scenario N 1 -2) 19

Beam pipe shielding. Parameter drawing (scenario N 1 -2) 19

BP radiation shielding. Parameter drawings (1 -2) 20

BP radiation shielding. Parameter drawings (1 -2) 20

Scenario N 4 YB 0/YB 1/YB 2 maintenance 21

Scenario N 4 YB 0/YB 1/YB 2 maintenance 21

BP radiation shielding. Parameter drawings 22

BP radiation shielding. Parameter drawings 22

Scenario N 7 CMS OPENINING EB Super module reinstallation 23

Scenario N 7 CMS OPENINING EB Super module reinstallation 23

BP radiation shielding. Parameter drawings 24

BP radiation shielding. Parameter drawings 24

BP & shielding support (7) 25

BP & shielding support (7) 25

Scenario N 8 CMS OPENINING 10 m TK/HB/EB/ES/EE maintenance 26

Scenario N 8 CMS OPENINING 10 m TK/HB/EB/ES/EE maintenance 26

BP radiation shielding. Parameter drawings 27

BP radiation shielding. Parameter drawings 27

BP & shielding supports (1 -2 -4 -5 -8 -9) 28

BP & shielding supports (1 -2 -4 -5 -8 -9) 28

Radiation protection (scenario N 8) Very preliminary 29

Radiation protection (scenario N 8) Very preliminary 29

Scenario N 10 PIXEL maintenance (End Cap open 10 m) 30

Scenario N 10 PIXEL maintenance (End Cap open 10 m) 30

PIXEL maintenance (scenario N 10) 31

PIXEL maintenance (scenario N 10) 31

PIXEL maintenance. Shielding installation 32

PIXEL maintenance. Shielding installation 32

BP radiation shielding. Parameter drawings 33

BP radiation shielding. Parameter drawings 33

BP radiation shielding. Parameter drawings (10) 34

BP radiation shielding. Parameter drawings (10) 34

Radiation shielding/Traverses interface 35

Radiation shielding/Traverses interface 35

Radiation shielding/Traverses interface 36

Radiation shielding/Traverses interface 36

Radiation shielding/Traverses interface stop 37

Radiation shielding/Traverses interface stop 37

BP shielding & Traverse INTERFACE (Parameter drawings) 38

BP shielding & Traverse INTERFACE (Parameter drawings) 38

BP shielding & Traverse INTERFACE (Parameter drawings) 39

BP shielding & Traverse INTERFACE (Parameter drawings) 39

TRAVERSE for BP shielding installation Scenario N 1 -2 -8 -10 40

TRAVERSE for BP shielding installation Scenario N 1 -2 -8 -10 40

TRAVERSE for BP shielding installation (8) 41

TRAVERSE for BP shielding installation (8) 41

Beam pipe mechanical protection (scenario N 1 -2 -4 -5 -8) 42

Beam pipe mechanical protection (scenario N 1 -2 -4 -5 -8) 42

Scenario N 11 TK maintenance 43

Scenario N 11 TK maintenance 43

TK reinstallation TOOLING (11) 44

TK reinstallation TOOLING (11) 44

Main platforms adjustable support (11) 45

Main platforms adjustable support (11) 45

Main platforms support (11) 46

Main platforms support (11) 46

Radiation shielding. Option I(11) 47

Radiation shielding. Option I(11) 47

HB (RBX) maintenance (1 -st step) 48

HB (RBX) maintenance (1 -st step) 48

HB RBX maintenance 49

HB RBX maintenance 49

HB (RBX) maintenance (2 -nd step) BP shielding 50

HB (RBX) maintenance (2 -nd step) BP shielding 50

Dear Colleagues, This material was prepared for discussion. Your recommendation, remarks and comments are

Dear Colleagues, This material was prepared for discussion. Your recommendation, remarks and comments are welcome. Without your participation will be impossible to provide the radioactive shielding & tooling design. I hope to have response from following people !: Wolfram Zeuner Patrick Lepeule Joseph Howell Dick Loveless Ken Bell Lino Demaria Karl Aaron Gill Gino Bolla Jean Bos Nicola Bacchetta Dmitry Druzhkin Austin Ball Nicolas Siegrist Gerard Faber Farshid Feyzi Stephane Bally Wolfgang Funk Domenico Dattola Daniel Wenman Ettore Focardi Nebojsa Smiljkovic Hubert Gerwig; Christoph Schaefer; Andrea Gaddi; Michel Arnaud Also it is necessary the responses from the sub-detectors and subsystems coordinators. 51