CLIC Schedule issues K Foraz CLIC 09 Workshop

  • Slides: 20
Download presentation
CLIC Schedule issues K. Foraz CLIC 09 Workshop 12 -16 October 2009

CLIC Schedule issues K. Foraz CLIC 09 Workshop 12 -16 October 2009

Outline • CLIC-ILC comparisons : From CLIC workshop 2008 to ALCPG 09 in Albuquerque

Outline • CLIC-ILC comparisons : From CLIC workshop 2008 to ALCPG 09 in Albuquerque – CLIC workshop 2008 – ILC - GDE in Tsukuba in 2009 – ILC - ALCPG 09 in Albuquerque in 2009 • CLIC schedule progress and issues – Main LINAC: from module production to installation schedule – Injectors: very first drafts October, 15 een 2009 K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG 09 in Albuquerque CLIC workshop 2008 • First

From CLIC workshop 2008 to ALCPG 09 in Albuquerque CLIC workshop 2008 • First draft for the main LINAC was presented: – Phase 1: ~ 7 years – Phase 2: ~ 10 years • Actions were: – Compare CLIC and ILC assumptions – Review ILC schedule with same CLIC assumptions October, 15 een 2009 K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG 09 in Albuquerque ILC-GDE Tsukububa 09: ILC schedule

From CLIC workshop 2008 to ALCPG 09 in Albuquerque ILC-GDE Tsukububa 09: ILC schedule – 2 tunnels • 2 versions were presented: – Unlimited resources total duration = 6 years – Resource « leveled total duration = 9 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG 09 in Albuquerque Tsukuba 09: ILC and CLIC

From CLIC workshop 2008 to ALCPG 09 in Albuquerque Tsukuba 09: ILC and CLIC Schedule comparison CLIC 500 Ge. V ILC 3 Te. V Unlim. Resour. Leveled resources Nb of TBM 2 9 4 Nb of teams for elec. general services 4 24 8 Nb of teams for cooling and ventilation 4 12 4 Nb of teams for cabling 4 24 8 Nb of teams for machine installation 2 12 2 6 9, 5 (years) 7, 2 10, 5 2 tunnels October, 15 een 2009 K. Foraz, CLIC Worshop 2009

From CLIC workshop 2008 to ALCPG 09 in Albuquerque– ILC schedule 1 tunnel Question

From CLIC workshop 2008 to ALCPG 09 in Albuquerque– ILC schedule 1 tunnel Question raised: • Number of fronts for the machine • Number of TBM October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues • Main Linac – The schedule of the production

CLIC schedule progress and issues • Main Linac – The schedule of the production of modules has been checked with respect to the installation schedule (see next slides) – Since last year, the cross section evolved (ventilation ducts, pipes in “radier”, and the system are becoming more matures (for instance the survey); the progress rates will be reviewed with the project engineers (to be done) • Injectors – First draft for 500 Ge. V October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Modules production and installation • Production – – –

CLIC schedule progress and issues Modules production and installation • Production – – – – Tendering process ends t 0+1. 5 year Module comp. reception starts t 0+3 years Module assembly starts t 0+4 years Module ready for inst. starts t 0+5 years Last module ready for inst t 0+10 years 3 lines of production 60 months of production Courtesy G. Riddone • Installation – Transport : up to 40 modules /day with 6 vehicles (1 shift, 5 d/wk) (K. Kershaw) October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 1 • What is the t 0 (for module production) ? – With the hypothesis that the contracts for modules will be signed 6 months after the start of civil engineering works: ► t 0(modules)=to(c. e. start)-2 years • modules will have to be stored before installation (see next slides) • but the installation of modules can end at t 0(c. e. start)+9 years !!! -3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years) C. E start of works Tendering process Component procurement Component reception Module assembly 500 Ge. V 3 Te. V Courtesy G. Riddone October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 1 Modules production and installation if modules contracts are signed 6 months after the civil engineering starts 20000 6 -8 & 8 -10 Nb of modules 15000 4 -6 & 5 -7 Stock 2 -4 & 3 -5 10000 Production 1 -2 & 1 -3 5000 Installation 0 0 To+4 years 6 12 18 24 30 Months 36 42 48 54 • 500 Ge. V modules in place at to+6 years • 3 Te. V modules in place at to+9 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues From module prod. to installation schedule * Case 1

CLIC schedule progress and issues From module prod. to installation schedule * Case 1 1 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) Time for construction and installation of general services for 500 Ge. V : 5. 2 years 3 4 5 6 7 Commissioning 8 The reverse schedule shows that: 2 TBM, 4 teams of each guild and 4 transport vehicles are sufficient to stick with the production of modules 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues With 4 TBM * Case 1 11 -9 9

CLIC schedule progress and issues With 4 TBM * Case 1 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 8 4 TBM gives more margins, and can correspond to 3 CE contracts 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 • What is the t 0 (for module production) ? – With the hypothesis that the contracts for modules will be signed 6 months before the start of civil engineering works: ► t 0(modules)=to(c. e. start)-3 years • modules will have to be stored before installation (see next slides) • but the installation of modules can end at t 0(c. e. start)+8 years !!! -3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years) C. E start of works Tendering process Component procurement Component reception Module assembly 500 Ge. V 3 Te. V Courtesy G. Riddone October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 Modules production and installation if modules contracts are signed when the civil engineering starts 20000 6 -8 & 8 -10 Nb of modules 15000 4 -6 & 5 -7 2 -4 & 3 -5 10000 Stock Production 1 -2 & 1 -3 Installation (1. 5 years) 5000 0 0 To+3 years 6 12 18 24 30 Months 36 42 48 54 • 500 Ge. V modules in place at to+6 years • 3 Te. V modules in place at to+8 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case

CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 Just in time schedule ; a 4 TBM version will be more appropriate (see next slide) 6 transport vehicles needed 8 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues With 4 TBM * Case 2 11 -9 9

CLIC schedule progress and issues With 4 TBM * Case 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 8 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Start of Module production versus end of installation End

CLIC schedule progress and issues Start of Module production versus end of installation End of module installation (form t 0 in years) 10 9 8 500 Ge. V 7 3 TEV 6 5 -1 -0, 5 0 0, 5 1 1, 5 Contracts for modules (w. r. t civil eng. start) in years October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC main LINAC - Summary • The start of the process for the production

CLIC main LINAC - Summary • The start of the process for the production of modules has an impact on the end dates. • The next step is to schedule the delivery and tendering process for the other components, as well as the integration milestones. • Since October the typical cross section changed, and each system is more mature (for instance survey); progress rates need to be reviewed with the groups. October, 15 een 2009 K. Foraz, CLIC Worshop 2009

CLIC schedule progress and issues Injectors 500 Ge. V – first draft for civil

CLIC schedule progress and issues Injectors 500 Ge. V – first draft for civil engineering 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 Injectors & curves 3 years 2 3 4 5 6 Commissioning 7 8 Drive beam + Main beam + curves = 3 years 9 slopes down to points 3 and 2 with a road header (15 m/wk), i. e. t 0+4 years slopes � excavated, in line with the construction of the main LINAC. 10 � ~ 3 years for the installation and commissioning of the injectors (schedule to be studied) October, 15 een 2009 K. Foraz, CLIC Worshop 2009

Conclusions / homeworks (!!) • Main LINAC – Schedule the delivery and tendering process

Conclusions / homeworks (!!) • Main LINAC – Schedule the delivery and tendering process for the other components – Review of the progress rates w. r. t the evolution of the project. • Injectors – Schedule the installation and commissioning – Schedule the injectors for 3 Te. V • Technical note on schedule – Started October, 15 een 2009 K. Foraz, CLIC Worshop 2009