CLIC Schedule issues K Foraz CLIC 09 Workshop
- Slides: 20
CLIC Schedule issues K. Foraz CLIC 09 Workshop 12 -16 October 2009
Outline • CLIC-ILC comparisons : From CLIC workshop 2008 to ALCPG 09 in Albuquerque – CLIC workshop 2008 – ILC - GDE in Tsukuba in 2009 – ILC - ALCPG 09 in Albuquerque in 2009 • CLIC schedule progress and issues – Main LINAC: from module production to installation schedule – Injectors: very first drafts October, 15 een 2009 K. Foraz, CLIC Worshop 2009
From CLIC workshop 2008 to ALCPG 09 in Albuquerque CLIC workshop 2008 • First draft for the main LINAC was presented: – Phase 1: ~ 7 years – Phase 2: ~ 10 years • Actions were: – Compare CLIC and ILC assumptions – Review ILC schedule with same CLIC assumptions October, 15 een 2009 K. Foraz, CLIC Worshop 2009
From CLIC workshop 2008 to ALCPG 09 in Albuquerque ILC-GDE Tsukububa 09: ILC schedule – 2 tunnels • 2 versions were presented: – Unlimited resources total duration = 6 years – Resource « leveled total duration = 9 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009
From CLIC workshop 2008 to ALCPG 09 in Albuquerque Tsukuba 09: ILC and CLIC Schedule comparison CLIC 500 Ge. V ILC 3 Te. V Unlim. Resour. Leveled resources Nb of TBM 2 9 4 Nb of teams for elec. general services 4 24 8 Nb of teams for cooling and ventilation 4 12 4 Nb of teams for cabling 4 24 8 Nb of teams for machine installation 2 12 2 6 9, 5 (years) 7, 2 10, 5 2 tunnels October, 15 een 2009 K. Foraz, CLIC Worshop 2009
From CLIC workshop 2008 to ALCPG 09 in Albuquerque– ILC schedule 1 tunnel Question raised: • Number of fronts for the machine • Number of TBM October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues • Main Linac – The schedule of the production of modules has been checked with respect to the installation schedule (see next slides) – Since last year, the cross section evolved (ventilation ducts, pipes in “radier”, and the system are becoming more matures (for instance the survey); the progress rates will be reviewed with the project engineers (to be done) • Injectors – First draft for 500 Ge. V October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Modules production and installation • Production – – – – Tendering process ends t 0+1. 5 year Module comp. reception starts t 0+3 years Module assembly starts t 0+4 years Module ready for inst. starts t 0+5 years Last module ready for inst t 0+10 years 3 lines of production 60 months of production Courtesy G. Riddone • Installation – Transport : up to 40 modules /day with 6 vehicles (1 shift, 5 d/wk) (K. Kershaw) October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 1 • What is the t 0 (for module production) ? – With the hypothesis that the contracts for modules will be signed 6 months after the start of civil engineering works: ► t 0(modules)=to(c. e. start)-2 years • modules will have to be stored before installation (see next slides) • but the installation of modules can end at t 0(c. e. start)+9 years !!! -3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years) C. E start of works Tendering process Component procurement Component reception Module assembly 500 Ge. V 3 Te. V Courtesy G. Riddone October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 1 Modules production and installation if modules contracts are signed 6 months after the civil engineering starts 20000 6 -8 & 8 -10 Nb of modules 15000 4 -6 & 5 -7 Stock 2 -4 & 3 -5 10000 Production 1 -2 & 1 -3 5000 Installation 0 0 To+4 years 6 12 18 24 30 Months 36 42 48 54 • 500 Ge. V modules in place at to+6 years • 3 Te. V modules in place at to+9 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues From module prod. to installation schedule * Case 1 1 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) Time for construction and installation of general services for 500 Ge. V : 5. 2 years 3 4 5 6 7 Commissioning 8 The reverse schedule shows that: 2 TBM, 4 teams of each guild and 4 transport vehicles are sufficient to stick with the production of modules 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues With 4 TBM * Case 1 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 8 4 TBM gives more margins, and can correspond to 3 CE contracts 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 • What is the t 0 (for module production) ? – With the hypothesis that the contracts for modules will be signed 6 months before the start of civil engineering works: ► t 0(modules)=to(c. e. start)-3 years • modules will have to be stored before installation (see next slides) • but the installation of modules can end at t 0(c. e. start)+8 years !!! -3 -2 -1 0 1 2 3 4 5 6 7 8 9 (years) C. E start of works Tendering process Component procurement Component reception Module assembly 500 Ge. V 3 Te. V Courtesy G. Riddone October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 Modules production and installation if modules contracts are signed when the civil engineering starts 20000 6 -8 & 8 -10 Nb of modules 15000 4 -6 & 5 -7 2 -4 & 3 -5 10000 Stock Production 1 -2 & 1 -3 Installation (1. 5 years) 5000 0 0 To+3 years 6 12 18 24 30 Months 36 42 48 54 • 500 Ge. V modules in place at to+6 years • 3 Te. V modules in place at to+8 years October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Schedule of the main LINAC – Machine * Case 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 Just in time schedule ; a 4 TBM version will be more appropriate (see next slide) 6 transport vehicles needed 8 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues With 4 TBM * Case 2 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 2 3 4 5 6 Commissioning 7 8 9 10 October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Start of Module production versus end of installation End of module installation (form t 0 in years) 10 9 8 500 Ge. V 7 3 TEV 6 5 -1 -0, 5 0 0, 5 1 1, 5 Contracts for modules (w. r. t civil eng. start) in years October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC main LINAC - Summary • The start of the process for the production of modules has an impact on the end dates. • The next step is to schedule the delivery and tendering process for the other components, as well as the integration milestones. • Since October the typical cross section changed, and each system is more mature (for instance survey); progress rates need to be reviewed with the groups. October, 15 een 2009 K. Foraz, CLIC Worshop 2009
CLIC schedule progress and issues Injectors 500 Ge. V – first draft for civil engineering 11 -9 9 -7 7 -5 5 -3 3 -1 1 -2 2 -4 4 -6 6 -8 8 -10 (4. 39 km) (6. 26 km) (4. 39 km) 1 Injectors & curves 3 years 2 3 4 5 6 Commissioning 7 8 Drive beam + Main beam + curves = 3 years 9 slopes down to points 3 and 2 with a road header (15 m/wk), i. e. t 0+4 years slopes � excavated, in line with the construction of the main LINAC. 10 � ~ 3 years for the installation and commissioning of the injectors (schedule to be studied) October, 15 een 2009 K. Foraz, CLIC Worshop 2009
Conclusions / homeworks (!!) • Main LINAC – Schedule the delivery and tendering process for the other components – Review of the progress rates w. r. t the evolution of the project. • Injectors – Schedule the installation and commissioning – Schedule the injectors for 3 Te. V • Technical note on schedule – Started October, 15 een 2009 K. Foraz, CLIC Worshop 2009
- Contoh top schedule dan supporting schedule
- Sales invoice double entry
- Clicséqur mon dossier citoyen
- Sistema web res. 1102-404 y res. 785
- Las siguientes imagenes pueden causar
- Cosas que empiezan con u
- S4x clic
- Alphabet etrusque
- Clic paris emeraude
- Clic
- Dead clic
- Soplos mesosistolicos
- Clic clac saint nicolas
- Cern clic
- 1 clic reception
- Clic
- Workshop modular building
- Sex workshop
- Pwp railway workshop
- Tocodynamometer placement
- Html help workshop