CITY OF ROCHESTER BUREAU OF WATER Water Main
CITY OF ROCHESTER BUREAU OF WATER Water Main Extensions & Improvements Program
Water Main Extensions and Improvements 2018 Public Informational Meeting May 16, 2018 Lovely A. Warren, Mayor Norman Jones, Commissioner, DES Patrick O’Connor, Water Bureau Director
2018 Water Main Extensions & Improvements Project Team: • Patrick O’Connor, P. E. , Director • Michael Bushart , PE–Managing Engr • George Wheatley– Project Manager • Kyle Bour– Field Engineer • Richard Clark – Villager Construction Pres. • Mark Simmons– Villager Construction Project Manager
2018 Water Main Extensions & Improvements Project • Project sponsored by Rochester Water • • • Bureau Designed by Rochester Water Bureau Construction inspection and project administration performed by Rochester Water Bureau Project awarded to Villager Construction, Inc. at a cost of $1, 791, 830. 00 – Richard Clark, Owner
PROJECT OBJECTIVE • Identify and replace water mains in the distribution • • • system that are found to be experiencing a high frequency of main breaks. Identify water mains that are hydraulically deficient for fire or domestic flow improvement. Replace unlined cast iron water mains that are known to cause rusty water problems. Work with Department of Neighborhood & Business Development to identify mains that need replacement to encourage business development.
2018 Water Main Extension & Improvements Project • Swan St (E. Main St to 400’ south of E. • • • Main St) Frost Ave (Genesee St to Jefferson Ave) Lyncrest Dr (Mc. Call Rd to Southampton Dr) Southampton Dr (Lyncrest Dr to Lyncrest Dr)
2018 Water Main Extensions & Improvements Project
Design, Bid & Award Phases • • Survey street and obtain utility drawings Design new water main Assemble bid plans, contract specifications, and estimate Obtain review approval from: • • • Monroe County Health Department City of Rochester Street Design & DES Permit Office Monroe County Traffic Engineering, Traffic Control Board Coordinate with Portland Ave. resurfacing project Other agencies and utilities as necessary • Hold Public Informational Meeting • Process Project Award and Issue Notice-to-Proceed
2018 Water Main Extension & Improvements Project • Additionally Frost Avenue has Catch • Basin and Manhole Cover work. Frost Ave will be milled and resurfaced the full width with pavement markings and bicycle markings.
Service Line Flushing
2018 Water Main Extensions & Improvements Project Tentative Project Schedule: Start / Finish Construction: • Swan Street • Frost Avenue • Lyncrest Drive • Southampton Drive
2018 Water Main Extensions & Improvements Project Thank you!! Questions