CHRODIS+ Working group sessions REPORT – WP 5 CHRODIS+ Kick-off event 20 September 2017

CHRODIS+ Working group sessions REPORT – WP 5 CHRODIS+ Kick-off event 20 September 2017

By the numbers. . . • 23 Partners, 20 present yesterday • Task 1

By the numbers. . . • 23 Partners, 20 present yesterday • Task 1 – 6 new country reports (and updates of existing ones) plus 1 overview report • Task 2 – 8 implementations – 5 contexts/good practices • Task 3 – #X recommendations for inter- & intra-sectoral collaboration WWW. CHRODIS. EU

Draft Action Plan for Year 1 (M 1 -M 12) Task/subtaks Responsible Involved organisations

Draft Action Plan for Year 1 (M 1 -M 12) Task/subtaks Responsible Involved organisations Deadline Task 1 Country reports Euro. Health. Net / THL CIPH, IPHS, NIGRi. R, SU, THL, NIJZ M 6 Task 1 Comparative overview report Euro. Health. Net / THL M 8 Task 2 Implementation Strategy Kronikgune (with implementers) M 4 Task 2 Preparation Phase (SWOT analysis, context analysis) Kronikgune ASL TO 3, CSJA, DOHI, EHNet, FINCB, HI, HSE, IPH, ISCIII, Kauno Klinikos, MFH-Malta, Mo. H-IT, MS/DGS, NIGRi. R, OOI, RIVM, SU, THL, VU M 12 WWW. CHRODIS. EU

Draft Action Plan for Year 1 (M 1 -M 12) Task/subtaks Responsible Involved organisations

Draft Action Plan for Year 1 (M 1 -M 12) Task/subtaks Responsible Involved organisations Deadline Task 2 Action Plans Kronikgune ASL TO 3, CSJA, DOHI (2 x), ISCIII, MFH-Malta M 12 Task 3 Light review of existing literature about success factors (inter- & intrasectoral collaboration) RIVM / OOI ASL TO 3, CSJA, DOHI, EHNet, FINCB, Kauno Klinikos, Kronikgune, HI, IPHS, MFH-Malta, Mo. HIT, MS/DGS, NCPHA, NIGRi. R, SU, THL, VU M 6 Task 3 Highlighting existing good practices RIVM / OOI ASL TO 3, CSJA, DOHI, EHNet, FINCB, Kauno Klinikos, Kronikgune, HI, IPHS, MFH-Malta, Mo. HIT, MS/DGS, NCPHA, NIGRi. R, SU, THL, VU M 12 WWW. CHRODIS. EU

Potential risks & mitigation Lack of engagement of partners Minimal financial resources Timeframe of

Potential risks & mitigation Lack of engagement of partners Minimal financial resources Timeframe of implementations WWW. CHRODIS. EU

Communication Plan Channels and frequency of internal communication • Regular TCs by tasks •

Communication Plan Channels and frequency of internal communication • Regular TCs by tasks • Short email updates to be sent to partners by WP leaders every 3 months • Updated mailing list with WP 1 and WP 5 leaders External Communication • Through WP 2 • Responsible: Euro. Health. Net and THL • Feeding news to WP 2 (e. g. Newsletters, PRs, input on comms products) • Through Euro. Health. Net’s own channels (social media…) WWW. CHRODIS. EU