Chapter 9 Project Management Project Evaluation Review Technique





















- Slides: 21
Chapter 9 Project Management (Project Evaluation & Review Technique – PERT)
Lecture Outline • Probabilistic Activity Times • Project Crashing and Time-Cost Trade-off Copyright 2011 John Wiley & Sons, Inc. 9 -2
Probabilistic Time Estimates • Beta distribution • probability distribution traditionally used in CPM/PERT Mean (expected time): Variance: where a + 4 m + b t= 6 b-a = 6 2 2 a = optimistic estimate m = most likely time estimate b = pessimistic time estimate Copyright 2011 John Wiley & Sons, Inc. 9 -3
P(time) Examples of Beta Distributions a m t b a t Time m b P(time) Time a m=t b Time Copyright 2011 John Wiley & Sons, Inc. 9 -4
Project with Probabilistic Time Estimates Equipment installation Equipment testing and modification 1 4 6, 8, 10 2, 4, 12 System development Start 2 3, 6, 9 Position recruiting 3 Manual testing System training 8 3, 7, 11 5 2, 3, 4 Job Training 6 1, 3, 5 3, 4, 5 Final debugging 10 1, 4, 7 Finish 11 9 2, 4, 6 System testing 1, 10, 13 System changeover Orientation 7 2, 2, 2 Copyright 2011 John Wiley & Sons, Inc. 9 -5
Activity Time Estimates TIME ESTIMATES (WKS) ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 MEAN TIME VARIANCE a m b t б 2 6 3 1 2 2 3 2 1 1 8 6 3 4 2 7 4 4 10 10 9 5 12 4 5 2 11 6 7 13 8 6 3 5 3 4 2 7 4 4 9 0. 44 1. 00 0. 44 2. 78 0. 11 0. 00 1. 78 0. 44 1. 00 4. 00 Copyright 2011 John Wiley & Sons, Inc. 9 -6
Activity Early, Late Times & Slack ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 t б ES EF LS LF S 8 6 3 5 3 4 2 7 4 4 9 0. 44 1. 00 0. 44 2. 78 0. 11 0. 00 1. 78 0. 44 1. 00 4. 00 0 8 6 3 3 9 9 13 16 8 6 3 13 9 7 5 16 13 17 25 1 0 2 16 6 5 14 9 12 21 16 9 6 5 21 9 9 16 16 16 25 25 1 0 2 8 0 2 11 0 3 8 0 Copyright 2011 John Wiley & Sons, Inc. 9 -7
Earliest, Latest, and Slack 1 0 8 1 Start 2 0 6 0 3 2 8 9 3 5 10 13 17 8 9 7 9 6 6 Critical Path 2 -5 -8 -11 4 8 13 5 16 21 5 6 3 6 6 3 4 5 16 7 3 Finish 16 9 9 1 0 9 9 13 4 12 16 11 16 25 9 7 3 5 2 14 16 Copyright 2011 John Wiley & Sons, Inc. 9 -8
Total Project Variance 2 = б 22 + б 52 + б 82 + б 112 = 1. 00 + 0. 11 + 1. 78 + 4. 00 = 6. 89 weeks Copyright 2011 John Wiley & Sons, Inc. 9 -9
Probabilistic Network Analysis Determine probability that project is completed within specified time where = = x= Z= Z= x- tp = project mean time project standard deviation proposed project time number of standard deviations that x is from the mean Copyright 2011 John Wiley & Sons, Inc. 9 -10
Normal Distribution of Project Time Probability Z = tp Copyright 2011 John Wiley & Sons, Inc. x Time 9 -11
Southern Textile What is probability that project is completed within 30 weeks? P(x 30 weeks) = 6. 89 weeks 2 = 6. 89 = 2. 62 weeks = 25 x = 30 Z= x- 30 - 25 = 2. 62 = 1. 91 Time (weeks) From Table A. 1, (appendix A) a Z score of 1. 91 corresponds to a probability of 0. 4719. Thus P(30) = 0. 4719 + 0. 5000 = 0. 9719 Copyright 2011 John Wiley & Sons, Inc. 9 -12
Southern Textile What is probability that project is completed within 22 weeks? P(x 22 weeks) = 0. 1271 0. 3729 = 6. 89 weeks 2 = 6. 89 = 2. 62 weeks x = 22 = 25 Z= x- 22 - 25 = 2. 62 = -1. 14 Time (weeks) From Table A. 1, (appendix A) a Z score of 1. 14 corresponds to a probability of 0. 3729. Thus P(22) = 0. 5000 - 0. 3729 = 0. 1271 Copyright 2011 John Wiley & Sons, Inc. 9 -13
Project Crashing • reducing project time by expending additional resources • Crash time • an amount of time an activity is reduced • Crash cost • cost of reducing activity time • Goal • reduce project duration at minimum cost Copyright 2011 John Wiley & Sons, Inc. 9 -14
Project Network – Building a House 4 2 8 12 7 4 1 12 3 4 Copyright 2011 John Wiley & Sons, Inc. 5 4 6 4 9 -15
Normal Time and Cost vs. Crash Time and Cost $7, 000 – $6, 000 – Crash cost $5, 000 – Crashed activity Slope = crash cost per week $4, 000 – $3, 000 – $2, 000 – Normal activity Normal cost $1, 000 – – 0 Normal time Crash time | 2 Copyright 2011 John Wiley & Sons, Inc. | 4 | 6 | 8 | 10 | 12 | 14 Weeks 9 -16
Project Crashing ACTIVITY 1 2 3 4 5 6 7 NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST 12 8 4 12 4 4 4 7 5 3 9 1 1 3 $3, 000 2, 000 4, 000 500 500 15, 000 $5, 000 3, 500 7, 000 71, 000 1, 100 22, 000 $75, 000 $110, 700 Copyright 2011 John Wiley & Sons, Inc. CRASH COST TOTAL ALLOWABLE CRASH TIME (WEEKS) 5 3 1 3 3 3 1 CRASH COST PER WEEK $400 500 3, 000 7, 000 200 7, 000 9 -17
$500 $7000 4 2 8 FROM … $7000 12 7 4 1 12 $400 3 4 $3000 Project Duration: 36 weeks 6 4 5 4 $200 $7000 $500 TO… Project Duration: 31 weeks Additional Cost: $2000 $7000 12 7 4 1 7 $400 3 4 $3000 Copyright 2011 John Wiley & Sons, Inc. 4 2 8 5 4 6 4 $200 9 -18
Time-Cost Relationship • Crashing costs increase as project duration decreases • Indirect costs increase as project duration increases • Reduce project length as long as crashing costs are less than indirect costs Copyright 2011 John Wiley & Sons, Inc. 9 -19
Time-Cost Tradeoff Minimum cost = optimal project time Total project cost Cost ($) Indirect cost Direct cost Crashing Time Project duration Copyright 2011 John Wiley & Sons, Inc. 9 -20
Copyright 2011 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein. Copyright 2011 John Wiley & Sons, Inc. 6 -21