Chapter 9 Net Present Value and Other Investment

  • Slides: 53
Download presentation
Chapter 9 • Net Present Value and Other Investment Criteria Mc. Graw-Hill/Irwin Copyright ©

Chapter 9 • Net Present Value and Other Investment Criteria Mc. Graw-Hill/Irwin Copyright © 2006 by The Mc. Graw-Hill Companies, Inc. All rights reserved.

Key Concepts and Skills • Be able to compute payback and discounted payback and

Key Concepts and Skills • Be able to compute payback and discounted payback and understand their shortcomings • Understand accounting rates of return and their shortcomings • Be able to compute the internal rate of return and understand its strengths and weaknesses • Be able to compute the net present value and understand why it is the best decision criterion 1

What is capital budgeting? • Process of planning and evaluating expenditures on asset whose

What is capital budgeting? • Process of planning and evaluating expenditures on asset whose cash flows are beyond 1 year. • Decide which are acceptable investments • Decide which actually should be purchased (or invested) • Long-term decisions; involve large expenditures. • Very important to firm’s future. 2

Good Decision Criteria • We need to ask ourselves the following questions when evaluating

Good Decision Criteria • We need to ask ourselves the following questions when evaluating capital budgeting decision rules • Does the decision rule adjust for the time value of money? • Does the decision rule adjust for risk? • Does the decision rule provide information on whether we are creating value for the firm? 3

Main criteria • • • The Payback The Discounted Payback Net Present Value The

Main criteria • • • The Payback The Discounted Payback Net Present Value The Internal Rate of Return The Profitability Index The Average Accounting Return 4

What is the payback period? The number of years required to recover a project’s

What is the payback period? The number of years required to recover a project’s cost, or how long does it take to get the business’s money back? 5

Payback for Franchise L (Long: Most CFs in out years) 0 1 CFt -100

Payback for Franchise L (Long: Most CFs in out years) 0 1 CFt -100 Cumulative -100 Payback. L = 2 2 10 -90 + 30/80 2. 4 60 100 -30 0 3 80 50 = 2. 375 years 6

Franchise S (Short: CFs come quickly) 0 CFt -100 Cumulative -100 Payback. S 1.

Franchise S (Short: CFs come quickly) 0 CFt -100 Cumulative -100 Payback. S 1. 6 2 3 70 100 50 20 -30 40 1 0 20 = 1 + 30/50 = 1. 6 years 7

Payback Period • Computation • Estimate the cash flows • Subtract the future cash

Payback Period • Computation • Estimate the cash flows • Subtract the future cash flows from the initial cost until the initial investment has been recovered • Decision Rule – Accept if the payback period is less than some preset limit • If the cut-off point is 2 years, which project should be accepted, which should be rejected? 8

Strengths and weaknesses of payback • Strengths • Provides an indication of a project’s

Strengths and weaknesses of payback • Strengths • Provides an indication of a project’s risk and liquidity. • Easy to calculate and understand. • Weaknesses • Ignores the time value of money. • Ignores CFs occurring after the payback period. • requires an arbitrary cut-off point 9

Discounted Payback Period • Compute the present value of each cash flow and then

Discounted Payback Period • Compute the present value of each cash flow and then determine how long it takes to payback on a discounted basis • Compare to a specified required period • Decision Rule - Accept the project if it pays back on a discounted basis within the specified time 10

Discounted Payback: Uses discounted rather than raw CFs. Project L 0 10% 1 2

Discounted Payback: Uses discounted rather than raw CFs. Project L 0 10% 1 2 3 10 60 80 CFt -100 PVCFt -100 9. 09 49. 59 60. 11 Cumulative -100 -90. 91 -41. 32 18. 79 Discounted = 2 payback + 41. 32/60. 11 = 2. 7 yrs Recover invest. + cap. costs in 2. 7 yrs. 11

Discounted payback period (project S) • Uses discounted cash flows rather than raw CFs.

Discounted payback period (project S) • Uses discounted cash flows rather than raw CFs. 0 CFt PV of CFt Cumulative 10% -100 Disc Payback. S == 2 1 70 63. 64 -36. 36 + 2 50 41. 32 4. 96 36. 36 / 41. 32 3 20 15. 03 19. 99 = 1. 88 years 12

Advantages and Disadvantages of Discounted Payback • Advantages • Includes time value of money

Advantages and Disadvantages of Discounted Payback • Advantages • Includes time value of money • Easy to understand • Disadvantages • Requires an arbitrary cutoff point • Ignores cash flows beyond the cutoff point 13

Net Present Value • The difference between the market value of a project and

Net Present Value • The difference between the market value of a project and its cost • How much value is created from undertaking an investment? • The first step is to estimate the expected future cash flows. • The second step is to estimate the required return for projects of this risk level. • The third step is to find the present value of the cash flows and subtract the initial investment. 14

NPV: Sum of the PVs of inflows and outflows. Cost often is CF 0

NPV: Sum of the PVs of inflows and outflows. Cost often is CF 0 and is negative. 15

NPV – Decision Rule • If the NPV is positive, accept the project •

NPV – Decision Rule • If the NPV is positive, accept the project • A positive NPV means that the project is expected to add value to the firm and will therefore increase the wealth of the owners. • Since our goal is to increase owner wealth, NPV is a direct measure of how well this project will meet our goal. 16

What’s Franchise L’s NPV? Project L: 0 -100. 00 10% 1 2 3 10

What’s Franchise L’s NPV? Project L: 0 -100. 00 10% 1 2 3 10 60 80 9. 09 49. 59 60. 11 18. 79 = NPVL 17

Calculator Solution Enter in CFLO for L: -100 CF 0 10 CF 1 60

Calculator Solution Enter in CFLO for L: -100 CF 0 10 CF 1 60 CF 2 80 CF 3 10 I NPV = 18. 78 = NPVL 18

What’s Franchise S’s NPV? Project S: 0 10% -100. 00 1 2 3 70

What’s Franchise S’s NPV? Project S: 0 10% -100. 00 1 2 3 70 50 20 63. 64 41. 32 15. 03 19. 98 = NPVS 19

Calculator Solution Enter in CFLO for S: -100 CF 0 70 CF 1 50

Calculator Solution Enter in CFLO for S: -100 CF 0 70 CF 1 50 CF 2 20 CF 3 10 I NPV = 19. 98 = NPVS 20

Decision Criteria Test - NPV • Does the NPV rule account for the time

Decision Criteria Test - NPV • Does the NPV rule account for the time value of money? • Does the NPV rule account for the risk of the cash flows? • Does the NPV rule provide an indication about the increase in value? • Should we consider the NPV rule for our primary decision rule? 21

Internal Rate of Return • This is the most important alternative to NPV •

Internal Rate of Return • This is the most important alternative to NPV • It is often used in practice and is intuitively appealing • It is based entirely on the estimated cash flows and is independent of interest rates found elsewhere • Project A: cost $1000, PV of all future cash flows = $1500. What is NPV of A? • Project B: cost $1, 000, PV of all future cash flows = $1, 500, 000. What is NPV of B? • We might need a rate of return in this case. 22

Internal Rate of Return: IRR 0 1 2 3 CF 0 Cost CF 1

Internal Rate of Return: IRR 0 1 2 3 CF 0 Cost CF 1 CF 2 Inflows CF 3 IRR is the discount rate that forces PV inflows = cost. This is the same as forcing NPV = 0. 23

NPV: Enter r, solve for NPV. IRR: Enter NPV = 0, solve for IRR.

NPV: Enter r, solve for NPV. IRR: Enter NPV = 0, solve for IRR. 24

What’s Franchise L’s IRR? 0 IRR = ? -100. 00 PV 1 PV 2

What’s Franchise L’s IRR? 0 IRR = ? -100. 00 PV 1 PV 2 PV 3 0 = NPV 1 2 3 10 60 80 Enter CFs in CFLO, then press IRR: IRRL = 18. 13%. IRRS = 23. 56%. 25

Rationale for the IRR Method If IRR > cost of capital (or required return),

Rationale for the IRR Method If IRR > cost of capital (or required return), then the project’s rate of return is greater than its cost-- some return is left over to boost stockholders’ returns. Example: required return = 10%, IRR = 15%. Profitable. If required return = 10%, should we accept or reject L and S? 26

Decision Criteria Test - IRR • Does the IRR rule account for the time

Decision Criteria Test - IRR • Does the IRR rule account for the time value of money? • Does the IRR rule account for the risk of the cash flows? • Does the IRR rule provide an indication about the increase in value? • Should we consider the IRR rule for our primary decision criteria? 27

Advantages of IRR • Knowing a return is intuitively appealing • It is a

Advantages of IRR • Knowing a return is intuitively appealing • It is a simple way to communicate the value of a project to someone who doesn’t know all the estimation details • If the IRR is high enough, you may not need to estimate a required return, which is often a difficult task 28

NPV Vs. IRR • NPV and IRR will generally give us the same decision

NPV Vs. IRR • NPV and IRR will generally give us the same decision • Exceptions • Non-conventional cash flows – cash flow signs change more than once • Mutually exclusive projects • Initial investments are substantially different • Timing of cash flows is substantially different 29

NPV Vs. IRR • NPV and IRR will generally give us the same decision

NPV Vs. IRR • NPV and IRR will generally give us the same decision • NPV>0 and IRR> required return • NPV<0 and IRR< required return • NPV=0 and IRR= required return 30

Project Example Information • You are looking at a new project and you have

Project Example Information • You are looking at a new project and you have estimated the following cash flows: • • Year 0: Year 1: Year 2: Year 3: CF = -165, 000 CF = 63, 120; CF = 70, 800; CF = 91, 080; 31

NPV profile • A graphical representation of the relationship between an investment’s NPV and

NPV profile • A graphical representation of the relationship between an investment’s NPV and various discount rates (required return) • IRR = 16. 13324% • R = 0, NPV = 60, 000 • R = 10, NPV = 19, 324 • R = 16. 3224, NPV = 0 • R = 18, NPV = -5227 • IRR > R, NPV > 0 • IRR < R, NPV < 0 • Same decision 32

NPV Profile For The Project IRR = 16. 13% 33

NPV Profile For The Project IRR = 16. 13% 33

NPV Vs. IRR • NPV and IRR will generally give us the same decision

NPV Vs. IRR • NPV and IRR will generally give us the same decision • Exceptions • Non-conventional cash flows – cash flow signs change more than once • Mutually exclusive projects • Initial investments are substantially different • Timing of cash flows is substantially different 34

NPV Vs. IRR • Non-conventional cash flows – cash flow signs change more than

NPV Vs. IRR • Non-conventional cash flows – cash flow signs change more than once • Normal (conventional) Time 0 1 2 3 CF -300 150 200 250 sign + + + • Non-normal (non-conventional) Time 0 1 2 3 CF -90, 000 132, 000 100, 000 -150, 000 sign + + • More than 1 IRR, if the signs change 2 times, we have 2 IRRs, the signs changes 3 times, we have 3 IRRs 35

IRR and Non-conventional Cash Flows • When the cash flows change sign more than

IRR and Non-conventional Cash Flows • When the cash flows change sign more than once, there is more than one IRR • When you solve for IRR you are solving for the root of an equation and when you cross the x-axis more than once, there will be more than one return that solves the equation • If you have more than one IRR, which one do you use to make your decision? 36

Example – Non-conventional Cash Flows • Suppose an investment will cost $90, 000 initially

Example – Non-conventional Cash Flows • Suppose an investment will cost $90, 000 initially and will generate the following cash flows: • Year 1: 132, 000 • Year 2: 100, 000 • Year 3: -150, 000 • The required return is 15%. • Should we accept or reject the project? 37

Example – Non-conventional Cash Flows • Calculator: CF 0 = -90, 000; C 01

Example – Non-conventional Cash Flows • Calculator: CF 0 = -90, 000; C 01 = 132, 000; F 01 = 1; C 02 = 100, 000; F 02 = 1; C 03 = -150, 000; F 03 = 1; I = 15; CPT NPV = 1769. 54 • Solve for IRR • 0 = -90, 000 + 132, 000/(1+IRR)1 +100, 000/(1+IRR)2 -150, 000/(1+IRR)3 • (IRR-0. 101102)(IRR-0. 426585) = 0 • IRR = 10. 1102% and IRR = 42. 6585% • If you compute the IRR on the calculator, you get 10. 1102% because it is the first one that you come to. 38

Summary of Decision Rules • The NPV is positive at a required return of

Summary of Decision Rules • The NPV is positive at a required return of 15%, so you should Accept • If you use the financial calculator, you would get an IRR of 10. 11% which would tell you to Reject • You need to recognize that there are nonconventional cash flows and look at the NPV profile • When you have conflict between NPV and IRR, go with the NPV 39

NPV Profile IRR = 10. 11% and 42. 66% 40

NPV Profile IRR = 10. 11% and 42. 66% 40

IRR and Mutually Exclusive Projects • Independent and Mutually exclusive projects • Independent: the

IRR and Mutually Exclusive Projects • Independent and Mutually exclusive projects • Independent: the decision to accept/reject one project does not affect the decision to accept/reject another. • Mutually exclusive: If you choose one, you can’t choose the other • NPV(L) = 18. 79, NPV(S) = 19. 98 • If L and S are independent, which project should we accept? • IF L and S are mutually exclusive, which project should we accept? • Intuitively you would use the following decision rules (if mutually exclusive) • NPV – choose the project with the higher NPV • IRR – choose the project with the higher IRR 41

Example With Mutually Exclusive Projects Period Project A Project B 0 -500 -400 1

Example With Mutually Exclusive Projects Period Project A Project B 0 -500 -400 1 325 200 IRR 19. 43% 22. 17% NPV 64. 05 The required return for both projects is 10%. Which project should you accept and why? 60. 74 42

Period A B A-B 0 -500 -400 -100 1 325 0 2 325 200

Period A B A-B 0 -500 -400 -100 1 325 0 2 325 200 125 • Cross-over rate is the rate where NPV(A) = NPV(B). It is the IRR of the difference in the cash flows of the 2 projects • IRR (A-B) = cross over rate = 11. 8034% 43

NPV Profiles IRR for A = 19. 43% IRR for B = 22. 17%

NPV Profiles IRR for A = 19. 43% IRR for B = 22. 17% Crossover Point = 11. 8% 44

Example With Mutually Exclusive Projects Period Project A Project B 0 -500 -400 1

Example With Mutually Exclusive Projects Period Project A Project B 0 -500 -400 1 325 200 IRR 19. 43% 22. 17% NPV 64. 05 The required return for both projects is 10%. Which project should you accept and why? 60. 74 45

Conflicts Between NPV and IRR • NPV directly measures the increase in value to

Conflicts Between NPV and IRR • NPV directly measures the increase in value to the firm • Whenever there is a conflict between NPV and another decision rule, you should always use NPV • IRR is unreliable in the following situations • Non-conventional cash flows • Mutually exclusive projects 46

Profitability Index • PI = PV of future cash flows/ Intial cost • Measures

Profitability Index • PI = PV of future cash flows/ Intial cost • Measures the benefit per unit cost, based on the time value of money • A profitability index of 1. 1 implies that for every $1 of investment, we create an additional $0. 10 in value • Can have conflict with NPV in some mutually exclusive projects • This measure can be very useful in situations in which we have limited capital 47

Advantages and Disadvantages of Profitability Index • Advantages • Closely related to NPV, generally

Advantages and Disadvantages of Profitability Index • Advantages • Closely related to NPV, generally leading to identical decisions • Easy to understand communicate • May be useful when available investment funds are limited • Disadvantages • May lead to incorrect decisions in comparisons of mutually exclusive investments 48

Summary – Discounted Cash Flow Criteria • Net present value • • Difference between

Summary – Discounted Cash Flow Criteria • Net present value • • Difference between market value and cost Take the project if the NPV is positive Has no serious problems Preferred decision criterion • Internal rate of return • • Discount rate that makes NPV = 0 Take the project if the IRR is greater than the required return Same decision as NPV with conventional cash flows IRR is unreliable with non-conventional cash flows or mutually exclusive projects • Profitability Index • • Benefit-cost ratio Take investment if PI > 1 Cannot be used to rank mutually exclusive projects May be used to rank projects in the presence of capital rationing 49

Summary – Payback Criteria • Payback period • Length of time until initial investment

Summary – Payback Criteria • Payback period • Length of time until initial investment is recovered • Take the project if it pays back in some specified period • Doesn’t account for time value of money and there is an arbitrary cutoff period • Discounted payback period • Length of time until initial investment is recovered on a discounted basis • Take the project if it pays back in some specified period • There is an arbitrary cutoff period 50

Capital Budgeting In Practice • If NPV is superior than all other method, why

Capital Budgeting In Practice • If NPV is superior than all other method, why should we consider IRR, payback, etc? • Convenience • NPV is only an estimate, it depends on future cash flows and discount rate. Both are estimates. Therefore, we need to compute other criteria to strengthen our decisions • In theory, NPV is the best • In practice, NPV: 74. 9%, IRR: 75. 7%, and payback 56. 7%. Small companies use payback, big companies use IRR, NPV 51

Capital Budgeting In Practice • We should consider several investment criteria when making decisions

Capital Budgeting In Practice • We should consider several investment criteria when making decisions • NPV and IRR are the most commonly used primary investment criteria • Payback is a commonly used secondary investment criteria 52