Chapter 5 Scheduling the Project MEM 612 Project
- Slides: 45
Chapter 5 Scheduling the Project MEM 612 Project Management
PERT AND CPM NETWORKS MEM 612 Project Management
History • Late 1950 s – Program Evaluation and Review Technique (PERT) • U. S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft • Probabilistic activity durations – Critical Path Method (CPM) • Dupont De Nemours Inc. • Deterministic activity durations MEM 612 Project Management
The Language of PERT/CPM • Activity – task or set of tasks – use resources • Event – state resulting from completion of one or more activities – consume no resources or time – predecessor activities must be completed MEM 612 Project Management
The Language of PERT/CPM continued • Milestones – events that mark significant progress • Network – diagram of nodes and arcs – used to illustrate technological relationships • Path – series of connected activities between two events MEM 612 Project Management
The Language of PERT/CPM concluded • Critical Path – set of activities on a path that if delayed will delay completion of project • Critical Time – time required to complete all activities on the critical path MEM 612 Project Management
Building the Network • AOA Network • AON Network MEM 612 Project Management
Table 5 -1 A Sample Set of Project Activities and Precedences MEM 612 Project Management
Figure 5 -1 Stage 1 of a Sample AON Network MEM 612 Project Management
Figure 5 -2 Stage 2 of a Sample AON Network MEM 612 Project Management
Figure 5 -3 A Completed Sample AON Network MEM 612 Project Management
Figure 5 -4 Stage 1 of a Sample AOA Network MEM 612 Project Management
Figure 5 -5 Stage 2 of a Sample AOA Network MEM 612 Project Management
Figure 5 -6 a A Completed Sample AOA Network MEM 612 Project Management
Figure 5 -6 b A Completed Sample AOA Network Showing the Use of a Dummy Task MEM 612 Project Management
Table 5 -2 A Sample Problem for Finding the Critical Path and Critical Time MEM 612 Project Management
Figure 5 -7 Stage 1 of a Sample Network MEM 612 Project Management
Figure 5 -8 A Complete Network MEM 612 Project Management
Figure 5 -9 Information Contents in an AON Node MEM 612 Project Management
Figure 5 -10 The Critical Path and Time for Sample Project MEM 612 Project Management
Calculating Activity Slack • Slack or Float LST - EST = LFT - EFT = Slack MEM 612 Project Management
PROJECT UNCERTAINTY AND RISK MANAGEMENT MEM 612 Project Management
Calculating Probabilistic Activity Times • Three Time Estimates – pessimistic (a) – most likely (m) – optimistic (b) MEM 612 Project Management
Figure 5 -13 The Statistical Distribution of all Possible Times for an Activity MEM 612 Project Management
Activity Expected Time and Variance MEM 612 Project Management
95 Percent Level • Task will be a or lower 5 percent of the time • Task will be b or greater 5 percent of the time MEM 612 Project Management
90 Percent Level • Task will be a or lower 10 percent of the time • Task will be b or greater 10 percent of the time MEM 612 Project Management
95 Percent Level (Alternative Interpretation) • Task will be between a and b 95 percent of the time MEM 612 Project Management
90 Percent Level (Alternative Interpretation) • Task will be between a and b 90 percent of the time MEM 612 Project Management
Figure 5 -14 An AON Network MEM 612 Project Management
The Probability of Completing the Project on Time =NORMDIST(D, , , TRUE) MEM 612 Project Management
Figure 5 -18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h MEM 612 Project Management
Selecting Risk and Finding D NORMINV(probability, , , TRUE) MEM 612 Project Management
SIMULATION MEM 612 Project Management
Traditional Statistics Versus Simulation • Similarities – must enumerate alternate paths • Differences – simulation does not require assumption of path independence MEM 612 Project Management
THE GANNT CHART MEM 612 Project Management
Figure 5 -23 A Gantt Chart of a Sample Project MEM 612 Project Management
Figure 5 -24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT MEM 612 Project Management
Figure 5 -25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements MEM 612 Project Management
Figure 5 -26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline MEM 612 Project Management
EXTENSIONS TO PERT/CPM MEM 612 Project Management
Precedence Diagramming • • Finish-to-start linkage Start-to-start linkage Finish-to-finish linkage Start-to-finish linkage MEM 612 Project Management
Figure 5 -27 Precedence Diagramming Conventions MEM 612 Project Management
Other Methods • Graphical Evaluation and Review Technique (GERT) – combines flowgraphs, probabilistic networks, and decision trees – allows loops back to earlier events and probabilistic branching MEM 612 Project Management
Copyright 2005 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein. MEM 612 Project Management
- 26-612
- Stamp duty(amendment) proclamation no. 612/2008
- Fertile cresent
- Solomon's temple location
- 2017:612
- Cs 612
- Sjn scheduling
- Sdm project management
- Scheduling principles in software engineering
- Project scheduling in software engineering
- Identify critical path
- Compartmentalization interdependency effort validation r
- Cpu scheduling project
- Project planning and organising
- Forward pass scheduling
- Compartmentalization interdependency effort validation r
- Cpu scheduling project
- Hát kết hợp bộ gõ cơ thể
- Slidetodoc
- Bổ thể
- Tỉ lệ cơ thể trẻ em
- Voi kéo gỗ như thế nào
- Thang điểm glasgow
- Hát lên người ơi
- Môn thể thao bắt đầu bằng chữ f
- Thế nào là hệ số cao nhất
- Các châu lục và đại dương trên thế giới
- Cong thức tính động năng
- Trời xanh đây là của chúng ta thể thơ
- Cách giải mật thư tọa độ
- Làm thế nào để 102-1=99
- Phản ứng thế ankan
- Các châu lục và đại dương trên thế giới
- Thể thơ truyền thống
- Quá trình desamine hóa có thể tạo ra
- Một số thể thơ truyền thống
- Cái miệng nó xinh thế chỉ nói điều hay thôi
- Vẽ hình chiếu vuông góc của vật thể sau
- Nguyên nhân của sự mỏi cơ sinh 8
- đặc điểm cơ thể của người tối cổ
- Thứ tự các dấu thăng giáng ở hóa biểu
- Vẽ hình chiếu đứng bằng cạnh của vật thể
- Tia chieu sa te
- Thẻ vin
- đại từ thay thế
- điện thế nghỉ