Chapter 5 Scheduling the Project MEM 612 Project

  • Slides: 49
Download presentation
Chapter 5 Scheduling the Project MEM 612 Project Management

Chapter 5 Scheduling the Project MEM 612 Project Management

PERT AND CPM NETWORKS MEM 612 Project Management

PERT AND CPM NETWORKS MEM 612 Project Management

History • Late 1950 s – Program Evaluation and Review Technique (PERT) • U.

History • Late 1950 s – Program Evaluation and Review Technique (PERT) • U. S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft • Probabilistic activity durations – Critical Path Method (CPM) • Dupont De Nemours Inc. • Deterministic activity durations MEM 612 Project Management

The Language of PERT/CPM • Activity – task or set of tasks – use

The Language of PERT/CPM • Activity – task or set of tasks – use resources • Event – state resulting from completion of one or more activities – consume no resources or time – predecessor activities must be completed MEM 612 Project Management

The Language of PERT/CPM continued • Milestones – events that mark significant progress •

The Language of PERT/CPM continued • Milestones – events that mark significant progress • Network – diagram of nodes and arcs – used to illustrate technological relationships • Path – series of connected activities between two events MEM 612 Project Management

The Language of PERT/CPM concluded • Critical Path – set of activities on a

The Language of PERT/CPM concluded • Critical Path – set of activities on a path that if delayed will delay completion of project • Critical Time – time required to complete all activities on the critical path MEM 612 Project Management

Building the Network • AOA Network • AON Network MEM 612 Project Management

Building the Network • AOA Network • AON Network MEM 612 Project Management

Table 5 -1 A Sample Set of Project Activities and Precedences MEM 612 Project

Table 5 -1 A Sample Set of Project Activities and Precedences MEM 612 Project Management

Figure 5 -1 Stage 1 of a Sample AON Network MEM 612 Project Management

Figure 5 -1 Stage 1 of a Sample AON Network MEM 612 Project Management

Figure 5 -2 Stage 2 of a Sample AON Network MEM 612 Project Management

Figure 5 -2 Stage 2 of a Sample AON Network MEM 612 Project Management

Figure 5 -3 A Completed Sample AON Network MEM 612 Project Management

Figure 5 -3 A Completed Sample AON Network MEM 612 Project Management

Figure 5 -4 Stage 1 of a Sample AOA Network MEM 612 Project Management

Figure 5 -4 Stage 1 of a Sample AOA Network MEM 612 Project Management

Figure 5 -5 Stage 2 of a Sample AOA Network MEM 612 Project Management

Figure 5 -5 Stage 2 of a Sample AOA Network MEM 612 Project Management

Figure 5 -6 a A Completed Sample AOA Network MEM 612 Project Management

Figure 5 -6 a A Completed Sample AOA Network MEM 612 Project Management

Figure 5 -6 b A Completed Sample AOA Network Showing the Use of a

Figure 5 -6 b A Completed Sample AOA Network Showing the Use of a Dummy Task MEM 612 Project Management

Table 5 -2 A Sample Problem for Finding the Critical Path and Critical Time

Table 5 -2 A Sample Problem for Finding the Critical Path and Critical Time MEM 612 Project Management

Figure 5 -7 Stage 1 of a Sample Network MEM 612 Project Management

Figure 5 -7 Stage 1 of a Sample Network MEM 612 Project Management

Figure 5 -8 A Complete Network MEM 612 Project Management

Figure 5 -8 A Complete Network MEM 612 Project Management

Figure 5 -9 Information Contents in an AON Node MEM 612 Project Management

Figure 5 -9 Information Contents in an AON Node MEM 612 Project Management

Figure 5 -10 The Critical Path and Time for Sample Project MEM 612 Project

Figure 5 -10 The Critical Path and Time for Sample Project MEM 612 Project Management

Calculating Activity Slack • Slack or Float LST - EST = LFT - EFT

Calculating Activity Slack • Slack or Float LST - EST = LFT - EFT = Slack MEM 612 Project Management

PROJECT UNCERTAINTY AND RISK MANAGEMENT MEM 612 Project Management

PROJECT UNCERTAINTY AND RISK MANAGEMENT MEM 612 Project Management

Calculating Probabilistic Activity Times • Three Time Estimates a. k. a 3 -point estimation

Calculating Probabilistic Activity Times • Three Time Estimates a. k. a 3 -point estimation or beta distribution • PERT technique to measure 3 values of estimates: – pessimistic (a) – min reasonable period of time – most likely (m) – time required for completion – optimistic (b) – max reasonable period of time MEM 612 Project Management

Figure 5 -13 The Statistical Distribution of all Possible Times for an Activity MEM

Figure 5 -13 The Statistical Distribution of all Possible Times for an Activity MEM 612 Project Management

Activity Expected Time and Variance MEM 612 Project Management

Activity Expected Time and Variance MEM 612 Project Management

 • • Example: Optimistic (a) = 10 days Most likely (m) = 13

• • Example: Optimistic (a) = 10 days Most likely (m) = 13 days Pessimistic (b) = 25 days TE = [10 + 4(13) + 25] / 6 = 14. 5 = 15 days σ2 = [(25 – 10) / 6] 2 = 6. 25 σ = 2. 5 days MEM 612 Project Management

MEM 612 Project Management

MEM 612 Project Management

95 Percent Level • Task will be a or lower 5 percent of the

95 Percent Level • Task will be a or lower 5 percent of the time • Task will be b or greater 5 percent of the time MEM 612 Project Management

90 Percent Level • Task will be a or lower 10 percent of the

90 Percent Level • Task will be a or lower 10 percent of the time • Task will be b or greater 10 percent of the time MEM 612 Project Management

95 Percent Level (Alternative Interpretation) • Task will be between a and b 95

95 Percent Level (Alternative Interpretation) • Task will be between a and b 95 percent of the time MEM 612 Project Management

90 Percent Level (Alternative Interpretation) • Task will be between a and b 90

90 Percent Level (Alternative Interpretation) • Task will be between a and b 90 percent of the time MEM 612 Project Management

Figure 5 -14 An AON Network MEM 612 Project Management

Figure 5 -14 An AON Network MEM 612 Project Management

The Probability of Completing the Project on Time =NORMDIST(D, , , TRUE) MEM 612

The Probability of Completing the Project on Time =NORMDIST(D, , , TRUE) MEM 612 Project Management

Figure 5 -18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h MEM

Figure 5 -18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h MEM 612 Project Management

Selecting Risk and Finding D NORMINV(probability, , , TRUE) MEM 612 Project Management

Selecting Risk and Finding D NORMINV(probability, , , TRUE) MEM 612 Project Management

SIMULATION MEM 612 Project Management

SIMULATION MEM 612 Project Management

Traditional Statistics Versus Simulation • Similarities – must enumerate alternate paths • Differences –

Traditional Statistics Versus Simulation • Similarities – must enumerate alternate paths • Differences – simulation does not require assumption of path independence MEM 612 Project Management

THE GANNT CHART MEM 612 Project Management

THE GANNT CHART MEM 612 Project Management

Figure 5 -23 A Gantt Chart of a Sample Project MEM 612 Project Management

Figure 5 -23 A Gantt Chart of a Sample Project MEM 612 Project Management

Figure 5 -14 An AON Network MEM 612 Project Management

Figure 5 -14 An AON Network MEM 612 Project Management

Figure 5 -24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections,

Figure 5 -24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT MEM 612 Project Management

Figure 5 -25 A Gantt Chart of a Day Care Project Showing Expected Durations,

Figure 5 -25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements MEM 612 Project Management

Figure 5 -26 A Progress Report on a Day Care Project Showing Actual Progress

Figure 5 -26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline MEM 612 Project Management

EXTENSIONS TO PERT/CPM MEM 612 Project Management

EXTENSIONS TO PERT/CPM MEM 612 Project Management

Precedence Diagramming • • Finish-to-start linkage Start-to-start linkage Finish-to-finish linkage Start-to-finish linkage MEM 612

Precedence Diagramming • • Finish-to-start linkage Start-to-start linkage Finish-to-finish linkage Start-to-finish linkage MEM 612 Project Management

Figure 5 -27 Precedence Diagramming Conventions MEM 612 Project Management

Figure 5 -27 Precedence Diagramming Conventions MEM 612 Project Management

Other Methods • Graphical Evaluation and Review Technique (GERT) – combines flowgraphs, probabilistic networks,

Other Methods • Graphical Evaluation and Review Technique (GERT) – combines flowgraphs, probabilistic networks, and decision trees – allows loops back to earlier events and probabilistic branching MEM 612 Project Management

Copyright 2005 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of

Copyright 2005 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein. MEM 612 Project Management

QUIZ MEM 612 Project Management

QUIZ MEM 612 Project Management