Chapter 12 Network Scheduling Techniques Scheduling Techniques Gantt
- Slides: 17
Chapter 12 Network Scheduling Techniques
Scheduling Techniques • • Gantt or bar charts Milestone charts Line Balancing Networks – Program Evaluation and Review Technique (PERT) – Arrow Diagram Method (ADM) also called the Critical Path Method (CPM) – Graphical Evaluation and Review Technique (GERT) – Precedence Diagram Method (PDM)
Scheduling Advantages • Needed for planning • Evaluate alternatives (what-if’s) • Resource scheduling • Controlling
Bar (Gantt) Charts TASKS 1 2 3 4 5 MONTHS AFTER GO-AHEAD 1 2 3 4 5
Milestone Chart ACTIVITY TESTING ANALYSIS REPORT PRESENTATION TIME
Standard PERT Nomenclature 6 3 WEEKS COMPLETE TESTING 3 COMPLETE FINAL REPORT LEGEND EVENT ACTIVITY
Dependencies 26 31 31 18 18 7 7 BURST POINT 26 SINK
Simplified PERT Network 3 1 5 2 6 7 8 4 LEGEND: (TIME = WEEKS) EVENT ACTIVITY CRITICAL PATH ACTIVITY 9
Dummy Activities D A PRECEDING ACTIVITY DUMMY B C A B C D B A, B
NETWORK FOR HOUSE CONSTRUCTION 6 POUR BASEMENT FLOOR INSTALL DRAINS 1 EXC & POUR FOOTINGS 2 POUR FOUND. INSTALL ROUGH ELECT. & PLUMB 3 ERECT FRAME & ROOF 7 11 8 INSTALL COOLING & HEATING INSTALL DRY WALL 9 4 10 LAY FLOORING 12 INSTALL KITCHEN EQUIP. PAINT FINISH CARPETING LAY BRICKWORK INSTALL FIN. PLUMB 16 FINISH ELECTR. WORK 5 LAY STORM DRAINS FINISH ROOF 13 14 18 POUR WALKS & LANDSCAPE INSTALL ROOF DRAINAGE 15 FINISH FLOORS FINISH GRADING 17
Slack Identification ACTIVITY EARLIEST START TIME EARLIEST FINISH TIME C (8, 10) 2 (15, 17) TIME LATEST FINISH TIME LATEST START TIME
Schedule Compression • • Elimination of some parts of the project Addition of more resources Substitution of less time-consuming components or activities Parallelization of activities Shortening critical path activities Shortening early activities Shortening longest activities
Schedule Compression (Continued) • Shortening easiest activities • Shortening activities that are least • • costly to speed up Shortening activities for which you have more resources Increasing the number of work hours per day
Resource Leveling • Resource leveling is an attempt to eliminate the manpower peaks and valleys by smoothing out the period-toperiod resource requirements. The ideal situation is to do this without changing the end date. However, in reality, the end date moves out and additional costs are incurred.
Resource Allocation • Resource allocation (or resource limited planning) is an attempt to find the shortest possible critical path based upon the available or fixed resources. The problem with this approach is that the employees may not be qualified technically to perform work on more than one activity in a network.
Types Of Precedence Charts FINISH-TO-START ACTIVITY 1 START ACTIVITY 2 START-TO-START ACTIVITY 1 START ACTIVITY 2
Types Of Precedence Charts FINISH-TO-FINISH ACTIVITY 1 PERCENT COMPLETE FINISH ACTIVITY 2 ACTIVITY 1 50 % 20 % ACTIVITY 2
- Gantt chart adalah
- Manajemen waktu proyek
- Gantt chart in operating system
- Preemptive priority scheduling
- Project management gant chart
- Sjn scheduling
- Interval scheduling: greedy algorithm
- Maintenance scheduling techniques
- Datagram switching
- Network topologies
- Features of peer to peer network and client server network
- Network systems design using network processors
- Network centric computing
- Packet switching vs circuit switching
- Different network techniques of project management
- Network traffic management techniques
- Network traffic monitoring techniques
- Network planning techniques