Change Order Request Restore ED Authority Purchase Order

  • Slides: 12
Download presentation
Change Order Request, Restore ED Authority Purchase Order No. 11398 MCRR 1364 Jones Island

Change Order Request, Restore ED Authority Purchase Order No. 11398 MCRR 1364 Jones Island Water Reclamation Facility Bar Screen #3 Repairs Commission Agenda Item #2

Jones Island Bar Screens • Used to screen rags, large solids, & other debris

Jones Island Bar Screens • Used to screen rags, large solids, & other debris from plant influent • Series of vertical bars mounted to stationary frame • A series of chain-driven rake beams travel vertically along face of bar screen to remove screenings 2

8 Bar Screens in Prelim. Bldg. 3

8 Bar Screens in Prelim. Bldg. 3

4

4

Bar Screen #3 Bar Rack Rake Beam 5

Bar Screen #3 Bar Rack Rake Beam 5

Bar Screen #3 • Low level screw pump flight broke off – Carried downstream

Bar Screen #3 • Low level screw pump flight broke off – Carried downstream to bars screens – Damaged • Bar racks • Rake beams • Chain Drive System • Other components • Screen is out of service 6

Purchase Order No. 11398 • August 2020, District issued PO $147, 793 to VWM/Doral

Purchase Order No. 11398 • August 2020, District issued PO $147, 793 to VWM/Doral • Perform following scope of work: – Replace 5 damaged bar racks – Replace 3 damaged rake beams • In September 2020, the Commission delegated $50, 000 of change authority to the ED 7

Requested Change Order • After work began, OEM (Huber Technology) performed inspection • Inspection

Requested Change Order • After work began, OEM (Huber Technology) performed inspection • Inspection identified additional parts requiring replacement: – 6 additional rake beams – 1 scraper assembly for the top of the screen – 1 complete guide rail set – 2 chain wheel protection plates 8

Change Order Scraper Assembly Guide Rails 9

Change Order Scraper Assembly Guide Rails 9

Change Order (CO) • Total cost of the additional work is $67, 084 •

Change Order (CO) • Total cost of the additional work is $67, 084 • 12 -14 week lead time for the additional parts • Issued CO of $43, 750 using ED authority to order spare parts • Requesting $23, 334 CO for installation & VWM markup 10

Request to Restore ED Authority • There is $6, 250 remaining ED authority for

Request to Restore ED Authority • There is $6, 250 remaining ED authority for future change orders • Request to restore ED authority is in case any additional changes beyond that remaining authority. 11

QUESTIONS? 12

QUESTIONS? 12