CERN X-band Test-Stand Progress and Perspective Directional coupler Circular pumping port Klystron XL 5 Mode convertors RF Valve High voltage modulator Circular waveguide F=50 mm SLED Pulse compressor CERN - CEA – PSI – SLAC
Stand alone Test Stand in CTFII Courtesy: S. Doebert Circular WG WG valve Mode converter load pump coupler Pump Tee F-Cup+Isolator 0. 5 m ACC girder Concrete block girder 0. 5 m
CTF 2 CLIC WS 10/2009 KM Schirm BE-RF 3
Components Control PCB, Sol PS, Vac PS, RF equippment RF-Valve Courtesy: F. Peauger CEA HVPS, New place Primary Power Connectio ns GYCOM Pulse Compressor Courtesy: GYCOM/I. Syratchev Filame nt PS Core Bias PS Coolin g Syste m Flow Oil Pumps/Filt er Guard s
Pulse Compressor (Gycom) KM Schirm BE-RF 5
Klystron CLIC WS 10/2009 KM Schirm BE-RF 6
Flanges CLIC WS 10/2009 KM Schirm BE-RF 7
LL-RF Collaboration Meeting 01/2009 KM Schirm BE-RF 8
Schedule (10/2009) ! Klystron and Modulator still driving the schedule ! Special RF components require close follow-up ! 12 GHz power (without compression) should be available in CTF 2 in May 2010
Conclusion: Ø Ø Ø Ø Activity running smooth – collaboration is excellent Program is (still? ) on track – planning and budget Trouble is in the details – real challenges ahead…. Need to follow more closely certain items Installation and commissioning will be men-power driven…… Involving future users will be required…… Still hoping for an additional klystron…… CLIC WS 10/2009 KM Schirm BE-RF 10
CLIC WS 10/2009 KM Schirm BE-RF 11