Cavity Cool Down and Cavity Support N Nigam

  • Slides: 13
Download presentation
Cavity Cool Down and Cavity Support N. Nigam 650 MHz High Beta CM Prototype

Cavity Cool Down and Cavity Support N. Nigam 650 MHz High Beta CM Prototype PDR 11 December 2019 In partnership with: India/DAE Italy/INFN UK/STFC France/CEA/Irfu, CNRS/IN 2 P 3

Contents • • Charge 1 a, 1 b & 1 c Introduction Cooldown simulation

Contents • • Charge 1 a, 1 b & 1 c Introduction Cooldown simulation for Support post & Cavity C-clamp design Conclusion 12/11/2019

Introduction Charge 1 a, 1 b & 1 c • The prototype High Beta

Introduction Charge 1 a, 1 b & 1 c • The prototype High Beta 650 MHz cryomodule will have four β=0. 9 cavities and two β=0. 92 cavities. • Cooldown simulation for both the type of cavity have been performed for thermal contraction. • All the interface have been considered during simulation. • On the basis of simulation design requirement for different bellows in p. CM have been written. • A design report was prepared with Teamcenter Number ED 0010081. • Cavity support using C-clam (During cooldown & Transportation) 0. 92 cavities 12/11/2019 0. 9 cavities

Description of the model Charge 1 a, 1 b & 1 c 24 Nos.

Description of the model Charge 1 a, 1 b & 1 c 24 Nos. 06 Nos. 12 Nos. Cavities & cavity support have been modeled independently. Any mismatch will be taken care by C-clamp. 12/11/2019

Cool down of the cavity support Charge 1 a, 1 b & 1 c

Cool down of the cavity support Charge 1 a, 1 b & 1 c • G-11 Support post designed by T. Nicol with Teamcenter Number ED 0009950. “ 650 MHz Cryomodule Support Post Shrink Fit Analysis”. • During simulation SS & Ti cavity support have been considered. Simulation model with Boundary condition and loading 12/11/2019 Temp. distribution (output of thermal analysis) Structural simulation model with Boundary condition and loading

Cool down of the cavity support Charge 1 a, 1 b & 1 c

Cool down of the cavity support Charge 1 a, 1 b & 1 c Based on the simulation & Also advantage of having better Magnetic hygiene , Ti cavity support was proposed 12/11/2019

Cool down of the cavity • Cooldown simulation for both the cavity was performed

Cool down of the cavity • Cooldown simulation for both the cavity was performed from Room temp. to 2 K. • Thermal contraction was evaluated. Results for β 0. 9 cavity 12/11/2019 Charge 1 a, 1 b & 1 c

Cool down of the cavity Charge 1 a, 1 b & 1 c Results

Cool down of the cavity Charge 1 a, 1 b & 1 c Results for β 0. 9 cavity Similar Thermal contractions were evaluated for β=0. 92 cavity w. r. t. to Strongback 12/11/2019

C_Clamp Charge 1 a, 1 b & 1 c • The C-Clamp placed on

C_Clamp Charge 1 a, 1 b & 1 c • The C-Clamp placed on support structure must have following feature q q Fine adjustment of position alignment during string assembly Locking feature during transportation. Accommodate thermal contraction of dressed cavity during cooldown. Maintain cavity position during operation. Left Hand Side C-Clamp 2 Nos. per cavity 12/11/2019 Right Hand Side C-Clamp 2 Nos. per cavity

C_Clamp Charge 1 a, 1 b & 1 c • The C-Clamp placed on

C_Clamp Charge 1 a, 1 b & 1 c • The C-Clamp placed on support structure must have following feature q q Fine adjustment of position alignment during string assembly Locking feature during transportation. Accommodate thermal contraction of dressed cavity during cooldown. Maintain cavity position during operation. A wire welded to the bearing support will prevent the bearing to fall during the transportation even if some screws got loosed 12/11/2019 During transportation a cap will be put on the Belleville assemblies to lock the movement. These caps will be removed through access port after transportation

C_Clamp Charge 1 a, 1 b & 1 c Access port are available on

C_Clamp Charge 1 a, 1 b & 1 c Access port are available on both side of the vacuum vessel 12/11/2019

Conclusion Charge 1 a, 1 b & 1 c • Thermal contraction of both

Conclusion Charge 1 a, 1 b & 1 c • Thermal contraction of both the cavity in cryomodule have been simulated & design report was prepared with Teamcenter Number ED 0010081 – Displacement is acceptable • C clamp (interface between dressed cavity & cavity support) can secure position during transportation & operation. A design report have been prepared for C clamp with Teamcenter number ED 0011241. 12/11/2019

End 12/11/2019

End 12/11/2019