Business Process Review of Environmental Permitting for Transportation
Business Process Review of Environmental Permitting for Transportation Projects Preliminary Report Keenan Konopaski, JLARC Analyst Gary Walvatne, Tech. Law, Inc. August 5, 2005 JLARC Business Process Review of Environmental Permitting
Complex Environmental Work, But on Small Portion of Projects Environmental Documentation 42 Months 1% Permitting on Transportation Projects 26 Months 2% 15 Hours 97% August 5, 2005 JLARC Business Process Review of Environmental Permitting 1
Scope of Review Two elements to this review: 1. Analyze the environmental documentation and permitting processes to identify contributors to delays and prioritize streamlining efforts. 2. Assess recent changes in the regulation of drainage ditches and stormwater runoff. August 5, 2005 JLARC Business Process Review of Environmental Permitting 2
Objectives of Review 1. Evaluate the regulatory requirements for a set of major projects to clarify the regulatory business process 2. Assess the applicability of successful streamlining efforts to various environmental requirements for major transportation projects August 5, 2005 JLARC Business Process Review of Environmental Permitting 3
Objectives of Review (cont) 3. Analyze recent project histories to identify the root causes of schedule delay 4. Determine the extent to which the regulatory goals concerning drainage ditches and stormwater runoff have changed over time, and identify the impacts of changes August 5, 2005 JLARC Business Process Review of Environmental Permitting 4
Focus of Review Project definition complete Begin design August 5, 2005 Finalize design work Prepare environmental documentation and submit applications Permits approved Begin coordination with utilities/local government Agreement/ plans secured Determine right of way requirements and make offers Settlement/ adjudication reached Open to traffic/user PS&E completed Advertise JLARC Business Process Review of Environmental Permitting Construction 5
Which Projects did We Review? Environmental Documentation 42 Months 1% Permitting on Transportation Projects 26 Months 2% 15 Hours 97% August 5, 2005 JLARC Business Process Review of Environmental Permitting 6
Ten Sample Projects 1. I-90, Spokane, Build Lanes from Argonne Road to Sullivan Road 2. SR 31, Metaline Falls to International Border 3. SR 16, Tacoma, HOV Improvements, Union Avenue to Jackson Avenue 4. SR 161, Milton to Federal Way, Jovita Blvd. To S 360 th Widening 5. SR 522, Woodinville to Monroe, Fales Road – Echo Lake Road Interchange 6. SR 240, Richland, I-182 to Columbia Center Boulevard 7. US 12, Southeast of Pasco, Mc. Nary Pool to Attalia 8. I-5, Chehalis, Rush Road to 13 th Street 9. SR 509/I-5 Freight and Congestion Relief Project, City of Sea. Tac 10. I-405, Kirkland Nickel Project, from SR 529 to 522 August 5, 2005 JLARC Business Process Review of Environmental Permitting 7
General Relationship between Documentation and Permitting Work ESA Consultation Environmental Documentation Environmental Permitting Time August 5, 2005 JLARC Business Process Review of Environmental Permitting 8
Process-Based Flow Diagram: NEPA Flow Diagram August 5, 2005 JLARC Business Process Review of Environmental Permitting 9
Process-Based Flow Diagram: ESA Informal Consultation August 5, 2005 JLARC Business Process Review of Environmental Permitting 10
Successful Streamlining Activities Report Page 22 August 5, 2005 JLARC Business Process Review of Environmental Permitting 11
Root Causes (X) and Effects (E) of Delays Report Page 32 August 5, 2005 JLARC Business Process Review of Environmental Permitting 12
Causes (X) & Effects (E) of Environ. Delays Report Page 34 August 5, 2005 JLARC Business Process Review of Environmental Permitting 13
Drainage Ditches 9 th Circuit Court of Appeals issued Talent decision in 2001 regarding irrigation ditches. COE districts have interpreted Talent decision differently. Seattle District requires assessment of drainage ditches, including WSDOT ditches. WSDOT coordinated with the Seattle District to develop the Talent package format in 2004. Seattle District has provided minimal formal guidance regarding Section 404 applicability. August 5, 2005 JLARC Business Process Review of Environmental Permitting 14
Stormwater WSDOT Highway Runoff Manual (HRM) must correspond to Ecology Stormwater Management Manuals (SMMs) Main difference between 2004 HRM and 2004/2005 SMMs: n Flow Control – pre-development (SMM) vs. preexisting site conditions in highly urbanized areas (HRM) August 5, 2005 JLARC Business Process Review of Environmental Permitting 15
Conclusions Processes supporting environmental activities on complex projects can vary widely and are not uniform or routine Environmental permit streamlining is not fully mature, and additional efficiencies are possible Staff will have the greatest impact on improving schedule timelines by focusing on processes (using existing practical examples) that: n improve or sustain strong communication n support clear and complete applications n assist with timely regulatory reviews n enhance technology While environmental activities can be root causes of delays, they are often accompanied by other items that impact a project’s overall schedule attainment August 5, 2005 JLARC Business Process Review of Environmental Permitting 16
Conclusions (cont) Excess time spent on environmental activities is often a result of delays from other factors (right-of-way, lawsuits, funding interruptions) Funding interruptions were the most common cause of schedule delays, often resulting in further updates or revisions to environmental documentation and permits There is a lack of formal federal guidance on how a recent court decision will impact regulation and permitting in the long term related to drainage ditches There are some recent updates to stormwater runoff management requirements, but pending the outcomes of other evaluations, these changes may have minimal impact in highly urbanized locations August 5, 2005 JLARC Business Process Review of Environmental Permitting 17
Recommendation Themes for Final Report Improvements in scheduling and costs for environmental tasks Coordination with regulatory agencies on target timelines for permits Delegation of federal regulatory authority to Dept of Ecology, to streamline with existing Ecology permit processes Clarification of Talent authority, for applicability to ditches intended in original court decision Clarification of definition and location of “highly urbanized” areas for stormwater management Extend e-permitting to other projects and regulatory areas (e. g. , Forest Practices Act Permit) August 5, 2005 JLARC Business Process Review of Environmental Permitting 18