BNL FNAL LBNL SLAC DOE Review 09 July

































- Slides: 33

BNL - FNAL - LBNL - SLAC DOE Review ‘ 09 July 13 -14, 2009 FNAL Long Quadrupole Giorgio Ambrosio OUTLINE: - Status - Coil, Instrum & QP, Structure, Test Prep. - Plans - Schedule and budget DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole 1

Long Quadrupole Main Features: • Aperture: 90 mm • magnet length: 3. 6 m Target: • Gradient: 200+ T/m Goal: • Demonstrate Nb 3 Sn magnet scale up Timeframe: – 1 st Long Quad test by the end of 2009 – 2 nd Long Quad test in Spring 2010 LQ Design Report available online at: https: //plone 4. fnal. gov/P 1/USLARP/Magnet. RD/longquad/LQ_DR. pdf G. Ambrosio - Long Quadrupole DOE Review 09 - FNAL, July 13 -14, 2009 2

LQ WBS • Coils are being fabricated at FNAL and BNL F. Nobrega (FNAL), and J. Schmalzle (BNL) • Quench protection and instr. design & proc. at LBNL H. Felice • Shell structure: design, procur. & assembly at LBNL P. Ferracin • Collar structure: procurement at FNAL (STOPPED) F. Nobrega • All LQ models to be tested at FNAL G. Chlachidze DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole 3

Status Summary • 4 coils ~ready for LQS 01 assembly • Shell-structure is ready • Pre-assembly practice in progress – Readiness review: ~July 27 • Test prep ~completed – Readiness review TBD • LQS 01 test in October DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

COILS DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Coil Fabrication • Coil fabrication is a labor intense work, using a lot of different tooling – – – Wind & Cure: 3 weeks Reaction: ~5 weeks Impregnation: 4 weeks Instrumentation: 2 weeks Shipment(s): 2 weeks each • Found and fixed several “bumps on the road” – See next slides • Long coil fabrication technology is improving – Last FY we fixed the HT, this FY the impregnation DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Discrepancy Reports We are implementing Discrepancy Reporting, formal (FNAL) and/or verbal (BNL, FNAL) minor DR: parts are missing or don't fit properly, revisions to drawings or traveler moderate DR: no permanent damage to the coil, change in process and/or part required severe DR: damage or irregularity to coil Discrepancy reports during winding & curing: DR's LQ 06 LQ 07 LQ 08 LQ 09 LQ 10 LQ 11 Total minor 7 2 3 1 1 15 moderate 1 4 2 2 0 2 11 severe 0 0 0 0 Total DR's 8 6 5 3 1 3 26 Discrepancy reports during reaction: Moderate/severe : 1 (coil #7) Discrepancy reports during impregnation: Severe : 2 (coils #6 and #9) DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Coil Fabrication Status – I • Found tension on conductor after coil #3 heat treatment • Performed analysis† • Developed solution for LQS 01 coils (gaps) Further analysis by Toohig fellow and core programs Coils 4 and 5 will be used for practice assembly Coils 6 to 9 will be used for LQS 01 †G. Ambrosio, et alt. , “Development and Coil Fabrication for the LARP 3. 7 -m Long Nb 3 Sn Quadrupole”, ASC 08 – To be Published in IEEE Trans. on App. Supercond. 8

Coil Fabrication Status – II • Coil #4: non effective mold-release Practice coils – In use for practice assembly; Mold-release tested on coil #3 parts • Coil #5: leakage during impregnation incomplete impregnation – Used for QP heater tests; for practicing with 2 nd impregnation; in use for practice assembly • Coil #6: incomplete impregnation – Fixed by 2 nd impregnation; added soak time under pressure after impregnation • Coil #7: Power outage during HT stopped argon flow – Witness samples are OK; removed valves • Coil #8: No problem • Coil #9: Midplane insulation stuck to impregnation fixture – Repaired with room-temperature epoxy • Coil #10 & #11 in progress DOE Review 09 - FNAL, July 13 -14, 2009 Next coils should show that debugging is over! G. Ambrosio - Long Quadrupole

Instrumentation • Completed plan – LBNL: trace design, procur. , ID instr. – BNL & FNAL: trace installation, OD instr. • Revisions to traces and procedures – Based on practice coils and first production coils – Added trace QC tests – Additional insulation over ends • Decided and implemented qualification tests for production coils Modification required based on coils #4 and #5 feedback implemented in coil #8 and subsequent coils – Data shared on LARP plone • Test of protection heaters at LN on practice coil #5 – Successfully passed with large margin Test of coil#5 protection heaters at LN 10 DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Coil Readiness Review DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

STRUCTURE DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Structure Assembly • LQS structure has been fully assembled LQSD = LQS with Al dummy coils Yoke rod tension: 330 MPa Compressive force: 760 k. N DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Short Model Test at LN • 1 section (850 mm) was assembled with aluminum coils, pre-loaded and tested at LN σy σz MPa Meas. +138 ± 6 +41 ± 13 Target +142 +43 Meas. -231 ± 23 +74 ± 7 Target -247 +63 Comparison: measurements and target values after cool-down Shell Coil Dummy coil stress during cool-down to 77 K Axial Azimuthal DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

LQSD = LQ with Al Dummy Coil • Assembled and tested with many strain gauges: – Structure: 10 stations at the center of each shell segment – Coils: 6 stations – Each station with y and z gauges with temperature compensators

LQ Shipping & Test prep. • LQSD (LQ w dummy coils) gave us an opportunity to check handling and transportation (LBNL FNAL) OK to go! 1. 9 K top head Handling & pivoting fixture LQSD Shipping fixture w shock absorbers Dedicated container on dedicated truck DOE Review 09 - FNAL, July 13 -14, 2009 pedestal G. Ambrosio - Long Quadrupole

LQSD LN Test Results • Measured values close to targets • Stress variations in shell smaller than in TQS 02 – Shell roundness is better than in TQS 02 • Stress variations in coils larger than in TQS 02 – Due to shell ID variation (+/- 5 mil) from section to section σy σz MPa MPa Meas. +127 ± 18 +44 ± 14 TQS 02* +154 ± 27 +138 ± 19 Meas. -194 ± 25 +80 ± 24 TQS 02** -142 ± 13 -88 ± 20 Shell Meas. +127 ± 18 +44 ± 14 Target +133 +41 Coil Meas. -194 ± 25 +80 ± 24 Target -225 +66 Rod Meas. +195 ± 21 Target +191 *TQS shell 22 mm thick, LQS shell 20 mm thick DOE Review 09 - FNAL, July 13 -14, 2009 Meas. +195 ± 21 TQS 02*** +113 **TQS coils with Ti poles ***TQS rods made of aluminum G. Ambrosio - Long Quadrupole Note: LQSD has AL coils with higher module than TQS coils

Shell Readiness Reviews • LQS Structure Readiness Review – Hold at LBNL before CM 12 (April 7, 09) • Recommendations: PASSED • Action items: – Compute with FEM analysis the coil stress variation due to longitudinal ID variations +/- 15 MPa • Next step: LQS 01 pre-assembly review – Possibly the week of July 27 DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Collar-based Structure • The test of a Long Quadrupole with Collar-based structure was in the plan approved by the LQ Support Structure Review (Nov. 07) • In the FY 09 budget we planned to complete LQC procurement as back-up ($190 k) • Based on recent DOE guidelines we decided to stop any LQC work. At this point: – Skin and yoke parts have been procured – Assembly tooling has been designed – Collars and tooling have not been procured (~$90 k) DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

TEST PREPARATION DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Test Preparation • Quench Detection System with Adaptive Thresholds – To allow using low threshold at high current avoiding trips due to voltage spikes at low current – Both DQD and AQD • Symmetric Coil Grounding – To reduce peak coil-ground voltage • LQ needs larger dump resistance than TQ magnets (60 vs 30 m. Ohm) • Active Ground Fault Monitoring System (Proposal) • Reconfiguration of the Magnet Protection System – Additional Heater-Firing-Units for all LQ heaters (16) • Modified Strain Gauge Readout System – To reduce noise and sampling time DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

LQSD Test Experience LQSD (Long Quad w dummy coils) test at LN was very useful and successful for: – Practice LQS handling and connection to VMTF – Cooldown with limited temperature gradient (top-bottom) • 48 hrs of cool down will be necessary for LQS 01 to reach 4. 5 K if T (K) temperature constraint is ΔT<150 K: • Total of 4 days including overnight idling • It will take ~4 times longer if ΔT< 50 K ~ 30 hrs To 200 K – Strain Gauge readout systems • Comparison VMTF and portable LBNL systems: very good agreement Next: Test Readiness Review DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole ΔT=50 K 15 hrs ΔT=150 K 24 hrs

SCHEDULE BUDGET PLANS DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

LQS 01 Schedule • LQS 01 pre-assembly Readiness Review: ~July 27 • Start LQS 01 test: October • Spare/LQS 02 coils in progress DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole 24

Latest FY 09 Budget Original FY 09 budget + carry forward: 2, 487 733 1, 116 638 +41% increase LQ coil cost: - Estimates with no contingency - FY 09 budget while plan was not defined - $5 M max for magnet R&D DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole 25

“Project” monitoring • Weekly LQ Task Leader meetings (video/phone) – Status, progress, issues – All documents on LARP plone https: //plone 4. fnal. gov/P 1/USLARP/Magnet. RD/longquad/ • Expenses monitoring – Based on LARP finance status reports (irregular at year start) Estimated with linear spending in sub-tasks FNAL LQ coil Labor expenses Actual expenses Estimated with all spending at the end of each sub-task DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole 26

FY 10 Plans • Complete LQS 01 test, analysis and disassembly – Estimate: $168 k (counting on FY 09 carry-forward) • LQS 01 b/02 assembly, test, disassembly & analysis – LQS 01 b = LQS 01 changing one/two coils • If LQS 01 will show limited performance (G < 200 T/m) – LQS 02 = LQS with a new set of coils – I would like to count on • Goal: demonstrate performance reproducibility contingency money for a possible 3 rd LQ test Estimate: $482 k • Complete coils #12 & #13; make two new coils – Estimate: $686 k Meetings, reports, Reviews; – Estimate: $90 k TOTAL FY 10 Budget: $1, 426 k DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

LQ FY 10 Schedule Q 1 • Start LQS 01 b/02 assembly: January 2010 • Start LQS 01 b/02 test: April 2010 • Two spare coils after LQS 01 test feedback DOE Review 09 - FNAL, July 13 -14, 2009 Q 2 G. Ambrosio - Long Quadrupole Q 3 28

Conclusions • Four coils the and shell-structure are ready for the assembly of LQS 01 • The test facility upgrade is almost complete LQS 01 test planned in October 09 Most feedback after the test; nonetheless presently we can say that: – Long coil design and fabrication technology significantly improved – Long shell-structure was successfully assembled and tested at LN DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

Appendix DOE Review 09 - FNAL, July 13 -14, 2009 G. Ambrosio - Long Quadrupole

LQS 01 Readiness Reviews • GOAL: Assess readiness for LQS 01 assembly (by evaluating: choice of coils, structure, target pre-stress and assembly procedure) and test (test facility and test plan) • #1: “LQS structure and target pre-stress” – April 7, LBNL • #2: “LQ coil design and fabrication” – June 17, FNAL • #3: “LQS 01 pre-assembly” – end of July at LBNL • #4: “Test readiness and test plan” DOE Review 09 - FNAL, July#1 13 -14, 2009 Apr. 7, 2009 LQS 01 Readiness Review – LBNL, G. Ambrosio -–Long Quadrupole Introduction G. Ambrosio 31

Pre-load scenarios and comparison with TQS 02 (scaled) cases ey (293 K) ey (4. 5 K) σy (293 K) σy (4. 5 K) Microstrain MPa 240 T/m, σpeak_coil = 170 MPa +520 ± 190 +1860 ± 222 +40 ± 15 +165 ± 18 230 T/m, σpeak_coil = 160 MPa +386 ± 190 +1714 ± 222 +29 ± 15 +152 ± 18 220 T/m, σpeak_coil = 150 MPa +252 ± 190 +1567 ± 222 +19 ± 15 +139 ± 18 Shell TQS 02 a +1506 ± 284 +169 ± 30 TQS 02 b +1767 ± 333 +193 ± 37 TQS 02 c +1829 ± 334 +198 ± 43 TQS 02 d +1842 ± 319 +200 ± 37 Ti pole 240 T/m, σpeak_coil = 170 MPa -400 ± 157 -816 ± 231 -57 ± 12 -128 ± 24 230 T/m, σpeak_coil = 160 MPa -295 ± 157 -701 ± 231 -42± 12 -112 ± 24 220 T/m, σpeak_coil = 150 MPa -189 ± 157 -586 ± 231 -27 ± 12 -97 ± 24 TQS 02 a -960 ± 62 Paolo Ferracin -142 ± 13 04/07/2009 32

LQS 01 target pre-stress Scenario 2: pre-load for 230 T/m (13. 2 k. A) • Shell – Strain • From 386 to 1714 µε – Stress • From 29 to 152 MPa • Coil pole – Strain • From -295 to -701 µε – Stress • From -42 to -112 MPa • Coil peak stress: 160 MPa Paolo Ferracin 04/07/2009 33
BNL FNAL LBNL SLAC LARP DOE Review July
BNL FNAL LBNL SLAC LHQ Goals and Status
BNL FNAL LBNL SLAC Magnet Systems Program Status
BNL FNAL LBNL SLAC Magnet RD Plan for
BNL FNAL LBNL SLAC LARP Strand Status of
BNL FNAL LBNL SLAC U S LARP Magnet
BNL FNAL LBNL SLAC CAREHHHAPD IR 07 Nov
BNL FNAL LBNL SLAC Magnet Systems Status and
BNL FNAL LBNL SLAC Feb03 2012 LARP Conductor
BNL FNAL LBNL SLAC Thermal study of Nb
BNL FNAL LBNL SLAC Strand Cable and Procurement
BNL FNAL LBNL SLAC Long Quadrupole Giorgio Ambrosio
BNL FNAL LBNL SLAC LHQ Program Nb 3
BNL FNAL LBNL SLAC 9 th LARP Collaboration
BNL FNAL LBNL SLAC Measurement of Nb 3
BNL FNAL LBNL SLAC LARP Collaboration Meeting 14
BNL FNAL LBNL SLAC TQ Thermal Model Dariusz
BNL FNAL LBNL SLAC LQ DS VideoMeeting May
BNL FNAL LBNL SLAC LQ Collaboration Video Meeting
BNL FNAL LBNL SLAC LARP Collaboration Meeting 13
BNL FNAL LBNL SLAC HQLHQ Coil Parts Task
BNL FNAL LBNL SLAC Design and Test of
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program BNL FNAL LBNL
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program BNL FNAL LBNL
US LHC Accelerator Research Program bnl fnal lbnl
US LHC Accelerator Research Program bnl fnal lbnl