Beam Line Installation Schedule PeterRaymond Kettle Installation Meeting
Beam Line Installation & Schedule Peter-Raymond Kettle Installation Meeting PSI August 2006 1
Main removable Components DS End-Cap + Insertion System US End-Cap Triplet II + Seperator Steering Magnet Peter-Raymond Kettle Degrader BTS Installation Meeting PSI August 2006 2
Component Status • Main beam line optical components ready for installation • COBRA US End-Cap Manufactured & assembled, tested & ready for Installation Vacuum Chamber connection N 2 Bag + TC • DS End-Cap + Insertion & Drive System currently being manufactured DS End-Cap expected – mid September Insertion & Drive system – mid-end September • Target System – presented by Bill • Collimator System – needs modifying Peter-Raymond Kettle Installation Meeting PSI August 2006 3
Constraints US End-Cap: • US End-Cap preparations mounting PSI workshops 6 WD • US End-Cap installation 5 WD installation after US N 2 Bag DS End-Cap + Insertion & Drive System: • DS End-Cap preparations mounting PSI workshops 6 WD • Insertion & Drive System mounting + testing PSI workshops 6 WD • DS End-Cap + Insertion & Drive System installation 10 WD installation after DS N 2 Bag Target System: • Target assembly + installation 2 W (mounted on DC structure) Beam Commissioning (degrader + 4 cm Tg. ) • New APD array must be available (designed & built by Run! 17 chs) • Beam Line setup + survey 5 WD post US End-Cap • BTS cryo-connections + pump & cool-down 8 WD • Beam Commissioning Run 4 Weeks, He-atmosphere + COBRA + BTS • Pion Beam Tune CEX 7 D (if not during Comm. Run) before LXe Calib. Peter-Raymond Kettle Installation Meeting PSI August 2006 4
US Assembly Instructions 1 9 5 3 7 2 4 Peter-Raymond Kettle 6 8 Installation Meeting PSI August 2006 10 5
Schedule (full DC Scenario) 11/9 US+DS TC N 2 Bag+Rail Installation 5 D 15/9 18/9 US End-Cap Installation 5 WD 22/9 2/10 Sep 41. + Triplet II Installation + Survey 5 WD Peter-Raymond Kettle 20/9 18/9 IS delivery + Work. Shop 18/9 DS End-Cap Work. Shop 6 WD 25/9 26/9 US TC Installation 3 D 4/10 5/10 BTS Installation + Survey Pumping + Cryo. Connections + cool-down 10 D 13/9 DS End-Cap delivery 15/9 DS End-Cap + IS Installation E 5 8 WD 6/10 14/10 DS TC Installation 3 D 15/10 !!! 5/10 9/10 Beam Commissioning No Tg or DCs 4 W Remove DS End-Cap + IS For DC + Tg Installation 7 D Installation Meeting PSI August 2006 28/9 12/11 ? ? ? 6
Schedule (Part DC Scenario) 11/9 15/9 US+DS TC N 2 Bag +Rail Installation 5 D 18/9 DS End-Cap delivery 15/9 18/9 US End-Cap Installation 5 WD 22/9 2/10 US TC Installation 3 D 4/10 IS delivery + Work. Shop 28/9 18/9 DS End-Cap Work. Shop 6 WD 25/9 24/9 DC + Tg Assembly 9 D 2/10 6/10 3/10 DS TC Installation DC + Tg Installation 7 D 3 D 9/10 13/9 Sep 41. + Triplet II Installation + Survey 5 WD 9/10 10/10 20/9 BTS Installation + Survey Pumping + Cryo. Connections + cool-down 10 D 17/10 Peter-Raymond Kettle DS End-Cap + IS Installation E 5 8 WD 20/10 Installation Meeting PSI August 2006 19/10 Beam Commissioning with Tg & part DCs 4 W 20/11 7
- Slides: 7