AWAKE Run 2 integration effect of installation transport

  • Slides: 23
Download presentation
AWAKE Run 2 integration - effect of installation, transport issues - comparison of 3

AWAKE Run 2 integration - effect of installation, transport issues - comparison of 3 versions Run 2 meeting 18/6/2020 Ans Pardons, for the AWAKE integration team 3 D views from Vincent Clerc

Outline • Introduction: • • • AWAKE Run 1 transport volume AWAKE-SPS dependency TT

Outline • Introduction: • • • AWAKE Run 1 transport volume AWAKE-SPS dependency TT 43 tunnel Crane in TCC 4 Parameters for comparison of different integration versions • Presentation of 3 integration versions: • diagonal • parallel compact • parallel liberty • Summary table • Conclusion

AWAKE Run 1 : transport volume 1. 2 m H=2 m TCC 4 1.

AWAKE Run 1 : transport volume 1. 2 m H=2 m TCC 4 1. 2 m H=2 m TT 41 TSG 41 TCV 4 A 1. 2 m wide and 2 m high transport volume as shown above is kept free in the run 1 layout. It allows, after shielding removal, to install or remove equipment from TCC 4 (or TT 41) via TSG 41, TCV 4 and TAG 41, and therefore independent from SPS operation. Note also the large “transfer area” (from crane to trailer or vice-versa) in upstream TCC 4.

AWAKE / SPS dependency Opening this door stops the SPS beam . This passage

AWAKE / SPS dependency Opening this door stops the SPS beam . This passage can only be used during Long shutdown (LS 2, LS 3) End-of-year shutdown (YETS, EYETS) Scheduled short SPS stops during run Transport paths for equipment TCC 4 to ECA 4, via TT 41 TCC 4 to ECA 4, via TSG 41 TCC 4 to ECA 4, via TT 43 (limtations, see next slide)

SLOPE 17°/ 30% 5 m TCC 4 to ECA 4, via TT 43 This

SLOPE 17°/ 30% 5 m TCC 4 to ECA 4, via TT 43 This passage has a very steep (30%) slope, and is not suited for transport of - heavy items (>200 kg (to be confirmed)) - long items (>1 m) - tall items (>1. 2 m) - fragile or complex items

AWAKE TCC 4 crane: loads and heights Max. load 7. 5 t Max. height

AWAKE TCC 4 crane: loads and heights Max. load 7. 5 t Max. height 3. 6 m Max. load 5 t Max. height 3. 4 m Max. height of rotated cathode exchange carrier 3. 3 m 1. 575 m Beam height

Versions and comparison • 3 layout versions in model, named after orientation of first

Versions and comparison • 3 layout versions in model, named after orientation of first e-source: • Diagonal • Parallel “compact” • Parallel “liberty” • Several parameters are used to compare the different versions • • Plasma cell longitudinal shift w. r. t. run 1 = Delta. P Length wave guides e-sources = Lw 1, Lw 2 Accessibility of equipment in TCC 4 (800 mm free space for access or evacuation) Transfer area in upstream TCC 4 (crane to trailer) Transport possibilities out from TCC 4 (as in previous slides) Independence from SPS during AWAKE installation Various (rotated cathode, . . . )

La diagonale Version 1: First e-source is placed diagonally Delta. P=30 m Current position

La diagonale Version 1: First e-source is placed diagonally Delta. P=30 m Current position MAGNET MBXFD PLASMA CELL RF GUN 2 RF GUN 1

0. 5 m passage only, unless rotated cathode exchange carrier Each red box =

0. 5 m passage only, unless rotated cathode exchange carrier Each red box = passage with w=0. 8 m, h=2 m La diagonale 1. 25 m H=2 m Reach of overhead crane (5 t-7. 5 t) There is very little free space in upstream TCC 4. Most but not all equipment is accessible via 0. 8 m-wide passage. There is virtually no space for additional equipment.

Reach of overhead crane (5 t-7. 5 t) Free area for transfer of object

Reach of overhead crane (5 t-7. 5 t) Free area for transfer of object from crane to trailer is ~1. 5 m 2 La diagonale

La diagonale 7. 9 m 12 m 4. 8 m Length waveguides E-source 1

La diagonale 7. 9 m 12 m 4. 8 m Length waveguides E-source 1 = 2+4. 8+12 + extra (2) = 20. 8 m = Lw 1 Length waveguides E-source 2 = 4. 8 + 12 + 7. 9 + extra (2) = 26. 7 m = Lw 2 2 m

Version 2: First e-source is placed parallel to second, compact version La Parallèle Compacte

Version 2: First e-source is placed parallel to second, compact version La Parallèle Compacte Delta. P=35 m Current position MAGNET MBXFD PLASMA CELL RF GUN 2 RF GUN 1

La Parallèle Compacte Limit crane 5 T 0. 8 m H=2 m Limit crane

La Parallèle Compacte Limit crane 5 T 0. 8 m H=2 m Limit crane 7. 5 T 0. 8 m H=2 m 0. 8 m Sheath height=2. 2 m There is still some free space in upstream TCC 4 (width ˜ 1. 2 m). In general, all equipment is easily accessible, 1. 25 m H=2 m

ROTATED CATHODE Passage 800 mm Reach of overhead crane (5 t-7. 5 t) La

ROTATED CATHODE Passage 800 mm Reach of overhead crane (5 t-7. 5 t) La Parallèle Compacte

Reach of overhead crane (5 t-7. 5 t) Free area for transfer of object

Reach of overhead crane (5 t-7. 5 t) Free area for transfer of object from crane to trailer: Max. width ~0. 9 m La Parallèle Compacte

DISTANCE RF GUN - MODULATOR La Parallèle Compacte 13. 7 m 12 m 4.

DISTANCE RF GUN - MODULATOR La Parallèle Compacte 13. 7 m 12 m 4. 8 m Length waveguides E-source 1 = 2+4. 8+12 + extra (2) = 20. 8 m = Lw 1 Length waveguides E-source 2 = 4. 8 + 12 + 13. 7 + extra (2) = 32. 5 m = Lw 2 2 m

La Parallèle Liberté Version 3: First e-source is placed parallel to second, but shifted

La Parallèle Liberté Version 3: First e-source is placed parallel to second, but shifted 5 m downstream to leave TSG 41 passage « liberty » version Delta P= 40 m Current position MAGNET MBXFD PLASMA CELL RF GUN 2 RF GUN 1

La Parallèle Liberté Limit crane 5 T 0. 8 m H=2 m Limit crane

La Parallèle Liberté Limit crane 5 T 0. 8 m H=2 m Limit crane 7. 5 T 7 m 1. 25 m H=2 m 1. 3 m 5. 4 m 2. 8 m 0. 8 m H=2 m 1. 4 m 5 m FREE SPACE in upstream TCC 4. In general, all equipment is easily accessible, easy to work on or move around. There is still space available for additional equipment

La Parallèle Liberté ROTATED CATHODE Reach of overhead crane (5 t-7. 5 t) Free

La Parallèle Liberté ROTATED CATHODE Reach of overhead crane (5 t-7. 5 t) Free area for transfer of object from crane to trailer: Max. width - 1. 7 m upstream of e-source - 1. 2 m upstream of MB 190 s - 0. 9 m next to MB 190 s

2. 1 m 1. 8 m 1 m An updated configuration of the 4

2. 1 m 1. 8 m 1 m An updated configuration of the 4 Klystrons allows a free passage of 1 m-1. 2 m width (depending on length), from TCC 4 to TAG 41 (transport independent from SPS operation), while still fulfilling Klystron handling requirements

DISTANCE RF GUN - MODULATOR La Parallèle Liberté 13. 7 m 17 m 4.

DISTANCE RF GUN - MODULATOR La Parallèle Liberté 13. 7 m 17 m 4. 8 m Length waveguides E-source 1 = 2+4. 8+17 + extra (2) = 25. 8 m = Lw 1 Length waveguides E-source 2 = 4. 8 + 17 + 13. 7 + extra (2) = 37. 5 m = Lw 2 2 m

Summary table Parameter Diagonal Compact Liberty Run 1 Delta. P 30 m 35 m

Summary table Parameter Diagonal Compact Liberty Run 1 Delta. P 30 m 35 m 40 m 0 WL 1 & WL 2 20. 8 m & 26. 7 m 20. 8 & 32. 5 m 25. 8 & 37. 5 m <10 m Accessibility equipment and free space in TCC 4 Limited, no margin Good Very Good Transfer area in TCC 4 Very small OK but narrow Large Very large Transport from/to TCC 4 Mainly via TT 41 (L<12 m, width<1. 2 m) (*) Mainly via TT 41 (L<12 m, Either via TT 41 (L<12 m, width<1. 2 m) (*) width<1. 2 m) or TCV 4 (L<8 m, width<1. 1 m) Same Independence from SPS (during installation) NO (*) YES (max. width ~1. 1 m) YES (max. width 1. 2 m) Other Maybe rotated cathode Can maybe keep current p+beam configuration? Rotated cathode S 2 Probably extra p+beam elements - (*) except for small and light items (L<1 m, width<1. 1 m, weight<200 kg tbc), they may pass via TT 43 and TCV 4 - but 30%slope!

Conclusion • The preferred version from the points of safety, flexibility, installation, future operation,

Conclusion • The preferred version from the points of safety, flexibility, installation, future operation, and more is the 3 rd version • The other versions will cause much longer installation times (link to SPS) and little to no flexibility during the design phase or later during operation. Also: • The EN-HE transport expert will become more involved in integration study. • A few dimensions/weights need to be checked, but will not have a significant influence. Next: evaluate feasibility, costs, schedule constraints of the preferred version: - Check effect on proton beam line for 40 m shift. Is a study of new design needed? Cost? - Verify whether waveguide lengths are feasible, same for rotated cathode. Cost? - …. (there’s surely more)