AV Project Management Using Info. Comm Standards Tom Kehr, CTS-D, CTS-I, ISF-C, LEED Green Associate Senior Staff Instructor Info. Comm International © 2013 Info. Comm International 1
Objectives • To use a framework for AV project planning, execution and closure • To be familiar with project planning tools and AV standard documentation © 2013 Info. Comm International 2
Obvious? • • • © 2013 Info. Comm International Yes It’s back to basics It’s picking up tips It’s getting in shape Are you the player or the coach? 3
On Time – On Budget • Why don’t our projects end? • Why do we keep going back? • I’m losing money on this © 2013 Info. Comm International 4
The End Starts At The Beginning • What are expectations? – What the stakeholder thinks they are getting from the designer and integrator – What the designer thinks they told the customer and integrator – What the integrator thinks the designer and stakeholder wants and needs © 2013 Info. Comm International 5
PM Process Definitions (Lifecycle) Initiation © 2013 Info. Comm International Preparation Execution/ Control Close 6
So What Did You Agree To Do? • • • Scope of Work Quality of Work Time Line Price Terms and Conditions © 2013 Info. Comm International 7
Project Elements / Constraints Optimize project outcome by managing constraints Quality is impacted by all elements Cost ≠ Price © 2013 Info. Comm International 8
Improving Performance • • Requires a repeatable structure Requires industry standard documents Requires transparency Requires a check list © 2013 Info. Comm International 9
Project Comparison © 2013 Info. Comm International 10
Standards Guide © 2013 Info. Comm International 11
Standards Guide for AV Systems Design and Coordination Processes • Guide for documenting AV projects • Guide for coordinating with other trades • Method for setting expectations © 2013 Info. Comm International 12
Standards Guide I. Project Planning and Coordination Meetings II. Program Phase (alternatively, Briefing Phase or Concept Design Phase) A. Needs Analysis B. Program Report III. Design Phase A. Architectural and Infrastructure Requirements 1. Architectural and Interior Design 2. Electrical 3. Workmanship and Technique 4. Acoustical 5. Information Technology (IT) B. AV System Documents 1. Bid Specifications Part 1 – General Part 2 – Products Part 3 – Execution 2. Design Drawings 3. Facilities Drawings 4. System Drawings IV. Construction Phase A. Construction Drawings B. Facilities Drawings C. System Drawings D. Reference Documentation E. Testing and Acceptance F. Project Closeout © 2013 Info. Comm International 13
What are the Parts? • • • Scope, Purpose, and Application Referenced Publications Definitions Requirements Verification Appendix © 2013 Info. Comm International 14
Scope - Purpose – Application • Provides a method for documentation • Provides a recognition and method of coordinating with other disciplines and trades • Provides a practical guideline for verifying cross trade responsibilities © 2013 Info. Comm International 15
Method For Documentation • • • Project Planning & Coordination Program Phase Design Phase Construction Phase Verification © 2013 Info. Comm International 16
Exceptions © 2013 Info. Comm International 17
Guide Requirements Section • The largest portion of the document • Describes in detail all aspects of the design process from project planning to a verified completed project Planning and Coordination Construction Phase Requirements Program Phase Design Phase © 2013 Info. Comm International 18
Planning & Coord Meetings • Schedule of meetings – Dates and times – Length and location • Meeting members – Who is on the list? – Who is not on the list? • Agenda for meetings © 2013 Info. Comm International 19
Establishing a Governance Structure • • • Who do you need to make happy? Managing expectations Stakeholder relationships Conflict and Escalation How are you doing? © 2013 Info. Comm International 20
Program Phase • Needs analysis • Program report Needs Applications Tasks Functions and Features © 2013 Info. Comm International 21
Design Phase • Architectural and interior design • AV System Documents © 2013 Info. Comm International 22
Program and Design Phases • • • Gather Information Needs Analysis Site Survey Recommend Changes & Create Scope Determine AV Solution Components Design AV Solution © 2013 Info. Comm International 23
Construction Phase • • • Construction drawings Facilities drawings System Drawings Reference Documentation Testing and acceptance Project closeout © 2013 Info. Comm International 24
Verification • All trades coordination and expectations • Provides responsibility check list • Avoids planning and delivery holes • Creates better understanding amongst client, GC, and trade partners © 2013 Info. Comm International 25
Who Will Manage The Project • • • Technician Designer Sales manager Consultant Customer Project manager © 2013 Info. Comm International 26
Roles And Perspectives • Technicians / Engineers – – – Seeks optimal solutions Strives for precision Deals with things Focuses on processes Reactionary problem solving – Works with immutable laws – Succeeds individually © 2013 Info. Comm International • Project Manager – Seeks pragmatic decisions – Strives for accuracy – Deals with people – Focuses on outcomes – Proactive planning – Works with situational rules – Succeeds through others 27
Making A Timeline • You have what needs to be done • How long will it take? • Break it down • Create milestones • Assign people © 2013 Info. Comm International 28
Risk Response Planning Strategies • Threats • Opportunities • Strategies – – Avoidance Transference Mitigation Acceptance © 2013 Info. Comm International 29
© 2013 Info. Comm International 30
Work Breakdown Structure AV Production System Audio Lighting Rigging Video Display Support General Session Intro Microphones Mixer Amplifiers Loudspeakers P&D ENG Cam BOH Dynamic Cabling FOH Scaffold Talent Mic BOH Condenser Power Monitors Stands Cabling What is the required result? Specific, measurable, verifiable, unambiguous © 2013 Info. Comm International 31
Logic Network Diagram © 2013 Info. Comm International 32
Estimate – Effort & Duration • Time to complete the task? • Aggregate time to complete the task? © 2013 Info. Comm International 33
Mature Display of a Project Schedule Hiding or Padding 5 days / 2 days 7 days shown Mature Use of Uncertainty and Reserves 5 days 6 days 5 days shown 6 days shown © 2013 Info. Comm International 6 days / 2 days 8 days shown 2 days mitigation 4 days uncertainty 22 days planned 4 days reserve 26 days actual 26 days planned 24 days actual 34
Work Schedule © 2013 Info. Comm International 35
Labor • • • Jurisdiction Work Rules Scales within scales Premium time Penalties Payroll © 2013 Info. Comm International 36
Event Closure • What did we do well? Take the time to Look Back and Learn Preparation Phase Executing & Controlling Phase Closing Phase What could we have done better? What were the key events for each phase? © 2013 Info. Comm International 37
How Will This Affect Me? • • • Project quality will be improved Coordination with other trades will be improved Costs will be reduced Expectations will be met Stress will be reduced © 2013 Info. Comm International 38
Project Completion When you finished doing all the things that you said you would do. © 2013 Info. Comm International 39
© 2013 Info. Comm International 40