Assignment 5: Part (A) The Dine Corporation is both a producer and a user

Assignment 5: Part (A) The Dine Corporation is both a producer and a user of brass couplings. The firm operates 220 days a year and uses the couplings at a steady rate of 50 per day. u = 50. Coupling can be produced at rate of 200 per day. p=200. Annual storage cost is $1 per coupling, H=1, and machine setup cost is $35 per run, S=35. Since there are 220 days per year and u is equal to 50, therefore yearly demand is 50(220), D= 11000 Determine the economic run size. Approximately how many runs per year will there be? Compute the maximum inventory level. Determine the cycle time, run time and pure consumption time. Compute the total cost

Production, Consumption, Inventory

Production, Consumption, Inventory

EPQ: One period and One year p-u u One Period One Year

EPQ: One period and One year p-u u One Period One Year

Imax, Ordering Cost and Carrying Cost I max

Imax, Ordering Cost and Carrying Cost I max

EPQ : Optimal Q

EPQ : Optimal Q

The Problem The Dine Corporation is both a producer and a user of brass

The Problem The Dine Corporation is both a producer and a user of brass couplings. The firm operates 220 days a year and uses the couplings at a steady rate of 50 per day. u = 50. Coupling can be produced at rate of 200 per day. p=200. Annual storage cost is $1 per coupling, H=1, and machine setup cost is $35 per run, S=35. Since there are 220 days per year and u is equal to 50, therefore yearly demand is 50(220), D= 11000 Determine the economic run size. Approximately how many runs per year will there be? Compute the maximum inventory level. Determine the cycle time, run time and pure consumption time. Compute the total cost

EPQ and # of Runs u =50, p=200, H=1, S=35, D= 11000 Determine the

EPQ and # of Runs u =50, p=200, H=1, S=35, D= 11000 Determine the economic run size. Approximately how many runs per year will there be? D/Q = 11000/1013 = 10. 85

Run Time How much do we produce each time? Q How long does it

Run Time How much do we produce each time? Q How long does it take to produce Q? d 1 What is our production rate per day? p Run Time? Q = pd 1 1013 = 200 d 1 d 1= 1013/200 = 5. 0 p-u d 1 I max d 2 u

Maximum Inventory ? At what rate inventory is accumulated? p-u For how long? d

Maximum Inventory ? At what rate inventory is accumulated? p-u For how long? d 1 What is the maximum inventory? IMax = (p-u)d 1 IMax = (200 -50)(5. 06) = 759 I max p-u d 1 d 2 u

Pure Consumption Time What is the Maximum inventory? IMax How long does it take

Pure Consumption Time What is the Maximum inventory? IMax How long does it take to consume IMax ? d 2 At which rate Imax is consumed for d 2 days u Imax = ud 2 759 = 50 d 2 = 15. 18 I max p-u d 1 d 2 u

Cycle Time, Total Cost Cycle Time ? d 1 + d 2 = 5.

Cycle Time, Total Cost Cycle Time ? d 1 + d 2 = 5. 06 + 15. 18 = 20. 24 Total Cost ? TC = H(IMax/2) + S(D/Q) TC = 1(759/2) + 35 (11000/1013) TC = 379. 5 + 379. 5 = 759

Assignment 4: Part (B) (a) : If average demand per day is 20 units

Assignment 4: Part (B) (a) : If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss=0, compute ROP? (b): If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. SS=70, compute ROP? (c) : If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute ss (d) : If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss (e) : If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute ss

Demand Forecast, and Lead Times Re-Order Point (ROP) in periodic inventory control is the

Demand Forecast, and Lead Times Re-Order Point (ROP) in periodic inventory control is the beginning of each period. (ROP) in perpetual inventory control is the inventory level equal to the demand during the lead time plus a safety stock to cover demand variability. Lead Time is the time interval from placing an order until receiving the order. If there were no variations in demand, and demand was really constant; the ss is zero and ROP is when inventory on hand is equal to the average demand during lead time.

ROP; Fixed d, Fixed LT, Zero SS (a) : If average demand per day

ROP; Fixed d, Fixed LT, Zero SS (a) : If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock. ss = 0 What is ROP? ROP = demand during lead time + ss ROP = demand during lead time Demand during lead time = (lead time) × (demand per unit of time) Demand during lead time = 20 × 10 = 200

ROP; Fixed d, Fixed LT, Positive SS Problem 4(b): If average demand per day

ROP; Fixed d, Fixed LT, Positive SS Problem 4(b): If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. ss = 70 What is ROP = demand during lead time + ss Demand during lead time = 200 ss = 70 ROP = 200+70 = 270

Safety Stock and ROP Risk of a stockout Service level Probability of no stockout

Safety Stock and ROP Risk of a stockout Service level Probability of no stockout ROP Average demand Quantity Safety stock 0 z z-scale Each Normal variable x is associated with a standard Normal Variable z x is Normal (Average x , Standard Deviation x) z is Normal (0, 1) There is a table for z which tells us a) Given any probability of not exceeding z. What is the value of z b) Given any value for z. What is the probability of not exceeding z

Common z Values Risk of a stockout Service level Probability of no stockout ROP

Common z Values Risk of a stockout Service level Probability of no stockout ROP Average demand Safety stock 0 Risk. 1. 05. 01 Service level. 9. 95. 99 Quantity z z value 1. 28 1. 65 2. 33 z-scale

Relationship between z and Normal Variable x Risk of a stockout Service level Probability

Relationship between z and Normal Variable x Risk of a stockout Service level Probability of no stockout ROP Average demand Quantity Safety stock 0 z z-scale z = (x-Average x)/(Standard Deviation of x) x = Average x +z (Standard Deviation of x) μ = Average x x = μ +z σ σ = Standard Deviation of x Risk. 1. 05. 01 Service level. 9. 95. 99 z value 1. 28 1. 65 2. 33

Relationship between z and Normal Variable ROP Risk of a stockout Service level Probability

Relationship between z and Normal Variable ROP Risk of a stockout Service level Probability of no stockout ROP Average demand Quantity Safety stock 0 z z-scale LTD = Lead Time Demand ROP = Average LTD +z (Standard Deviation of LTD) ROP = Average LTD +ss ss = z (Standard Deviation of LTD)

Safety Stock and ROP Risk of a stockout Service level Probability of no stockout

Safety Stock and ROP Risk of a stockout Service level Probability of no stockout ROP Average demand Quantity Safety stock 0 z z-scale Risk Service level z value. 1. 9 1. 28. 05. 95 1. 65. 01. 99 2. 33 ss = z × (standard deviation of demand during lead time)

ROP; total demand during lead time is variable (c) : If average demand during

ROP; total demand during lead time is variable (c) : If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. • Compute ROP at 90% service level. • Compute SS Service level Risk of a stockout Probability of no stockout Expected demand ROP Safety stock x

ROP; total demand during lead time is variable Service level Risk of a stockout

ROP; total demand during lead time is variable Service level Risk of a stockout Probability of no stockout z Risk. 1. 05. 01 Service level z value. 9 1. 28. 95 1. 65. 99 2. 33

ROP; total demand during lead time is variable z = 1. 28 z =

ROP; total demand during lead time is variable z = 1. 28 z = (X- μ )/σ X= μ +z σ μ = 200 σ = 25 X= 200+ 1. 28 × 25 X= 200 + 32 ROP = 232 SS = 32

ROP; Variable d, Fixed LT (d) : If average demand per day is 20

ROP; Variable d, Fixed LT (d) : If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. • Compute ROP at 90% service level. • Compute SS

ROP; Variable d, Fixed LT Previous Problem If average demand during the lead time

ROP; Variable d, Fixed LT Previous Problem If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. • Compute ROP at 90% service level. • Compute SS This Problem If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. • Compute ROP at 90% service level. • Compute SS If we can transform this problem into the previous problem, then we are done, because we already know how to solve the previous problem.

ROP; Variable d, Fixed LT If average demand per day is 20 units and

ROP; Variable d, Fixed LT If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. • Compute ROP at 90% service level. • Compute SS What is the average demand during the lead time What is standard deviation of demand during lead time

Demand During Lead Time If demand is variable and Lead time is fixed

Demand During Lead Time If demand is variable and Lead time is fixed

ROP; Variable d, Fixed LT

ROP; Variable d, Fixed LT

Now it is transformed into our previous problem where total demand during lead time

Now it is transformed into our previous problem where total demand during lead time is variable The average demand during the lead time is 320 and the standard deviation of demand during the lead time is 20. • Compute ROP at 90% service level. • Compute SS Service level Risk of a stockout Probability of no stockout Expected demand ROP Safety stock x

ROP; Variable d, Fixed LT z = 1. 28 z = (X- μ )/σ

ROP; Variable d, Fixed LT z = 1. 28 z = (X- μ )/σ X= μ +z σ μ = 320 σ = 20 X= 320+ 1. 28 × 20 X= 320 + 25. 6 X= 320 + 26 ROP = 346 SS = 26

Demand Fixed, Lead Time variable If lead time is variable and demand is fixed

Demand Fixed, Lead Time variable If lead time is variable and demand is fixed

Lead Time Variable, Demand fixed e) Demand of sand is fixed and is 50

Lead Time Variable, Demand fixed e) Demand of sand is fixed and is 50 tons per week. The average lead time is 2 weeks. Standard deviation of lead time is. 5 week. Assuming that the management is willing to accept a risk no more that 10%. Compute ROP and SS. Acceptable risk; 10% z = 1. 28