API 17 J B K L 1 L
API 17 J, B, K, L 1, L 2 Flexible Pipe Standardization API C 2 / SC 17: 2017 Winter Status Report. Houston, TX Reporting Chair Krassy Doynov, Ph. D. , Exxon. Mobil Production Company
Scope of Work and Status STANDARD NAME PUBLISHED Recommended practice for flexible pipe API RP 17 B 2 -May-2014 ISO 13628 -11 19 -Sep-2006 to be updated 2018 HOLD API Spec 17 J 2 -May-2014 4 th edition API Spec 17 K 1 -Nov-2005 ISO 13628 -10 1 -Oct-2005 Specification for flexible pipe ancillary equipment API Spec 17 L 1 23 -Nov-2015 ISO 13628 -16 Recommended practice for flexible pipe ancillary equipment API RP 17 L 2 5 -March-2013 ISO 13628 -17 HOLD API 17 TR 2 1 -Jun-2003 to be updated 2018/2019 Specification for Unbonded Flexible Pipe Specification for Bonded Flexible Pipe The Ageing of PA-11 in Flexible Pipes STATUS 2 Q 2017 3 rd edition HOLD to be updated 2019
Status of JIP for the update of API 17 TR 2 “The Ageing of PA-11 in Flexible Pipes” • SOW is to provide Guidelines for Qualification of Polyamides (PA 11, PA 12, …) in Flexible Pipes based on collecting field experience and integrity issues, and standardizing test procedures and acceptance criteria after performing round robin tests to ensure reproducibility. • Steering Committee meeting held on November 8 th and 9 th, 2016. • Round robin tests on PA 11 and PA 12 at different test labs completed. Test scatter is being compared, and results - analyzed for reproducibility. • 9 JIP Participants: Exxon. Mobil, GE Oil&Gas, Evonik, NOV Flexibles, Woodside, Petro. Bras, Total, Arkema, 4 Subsea. JIP Manager – 4 Subsea Norway. • K. Doynov will submit SRRR form for revision to 17 TR 2, upon JIP completion in 2017/2018.
Status of API 17 K (ISO 13628 -10 - on hold) • API 17 K (upcoming 3 rd edition) ballot opened on Dec-7, 2016 and will close on Feb-1, 2017. • Ballot was delayed with 4 -to-5 months due to conducting material- and mid-scale testing to verify FAT test acceptance criterion for seawater intake bonded pipes – a new application added to API 17 K. • API ballot comments to be addressed in 2 Q 17; and the new 3 rd edition published in 3 Q 17. • Project Summary: o o o Duration – 2. 5 years (January 2015 - May 2017); 5 F 2 F meetings of FPTG = 3 * Houston + 1 * Oslo/Norway + 1 * Pau/France; F 2 F meeting attendance – between 13 and 22 SMEs; Participating companies – up to 28; Participating SMEs – up to 45; Project Champion: Gergely Szekely of Conti. Tech: leading manufacturing task group, testing, and providing organizational and technical support. • API 17 K updates based on synergies with the latest revisions of API 17 J, 17 B, 17 L 1, 17 L 2 and pulling Industry lessons learned since 2005: o Pressure and temperature definitions, o System design philosophy, load classes, load conditions, design load effects, design methodology verification, pipe and end fitting design acceptance criteria, storage and operating bend radii; o Material qualification and matching testing standards – with new details on non-metallic reinforcement materials and elastomers; o Manufacturing control updates; o Repair procedures validated with test data; o Documentation requirements specified; o FAT: new tests and test procedure updates for SWI application and bonded pipe constructions with non-metallic reinforcement components; o Purchasing guidelines and pipe data sheet update.
Status of API 17 L 1, L 2 (ISO/FDIS 13628 -16, 17 – on hold) • The revision of API 17 L 1 and L 2 is planned to be kicked off in 2 H 17 – after publishing the 3 rd edition of API 17 K. • The SOW will to address: 135 Monogram comments (un-auditable areas), Technip’s 31 technical comments received in 2014, and recent Industry Lessons Learned between 2012 and 2016. • Anticipated Project duration – 2 years.
Status of API 17 J & 17 B Revision (ISO 13628 -2 &11 – on hold) • Update API 17 B with edits identified during the 17 K Project to align with new API 17 K. Estimated duration is 3 -6 months. • NOTE: 17 B is the RP supporting both the 17 J Spec and 17 K Spec
MEMBERSHIP: 17 K Flexible Pipe Task Group 1 Wayne Morris 2 Roger Hagen 3 Svein Are Løtveit 4 Nils Gunnar Viko 5 Christoffer Nilsen-Aas 6 Roberto Biollo 7 Emilien Rulence 8 Francois Migeon 9 Aymeric David 10 Gergely Szekely 11 Tibor Nagy 12 István Grepaly 13 Jorge Suarez 14 Kam Zandiyeh 15 Jo Wiggers 16 Don Johnson 17 Krassy Doynov 18 Richard Shepherd 19 1 3 M dwjohnson@etainc. org 23 24 25 26 27 28 29 30 30 31 32 33 34 35 36 37 38 39 40 Francois-Regis Pionetti Giaccobi Stephane Cyrille Mengeot Sunil Dutt Jesus Arrieche Ludovic Assier Vincent Lagarrigue Jean-Noel Vincent David Ponchon Remi Morvan Shankar Bhat Naiquan Ye Benjamin Biausser Charles B Paton Jan Berger Sarah Abercrombie Terje Peder Stavang Rune Haakonsen Torgrim Andersen Krassimir. Doynov@Exxonmobil. com 41 Andy Thompson 26 rsmailhome@gmail. com david. barnard@clearwaterfpc. com 42 Yu Xian Hong 27 Erik. Bendiksen@nov. com 43 Yang Peng 27 45 Kent Caveny 28 wkmorris 1@mmm. com roger. hagen@mmm. com loet@4 subsea. com 2 3 4 nils. gunnar. viko@4 subsea. com christoffer. nilsen-aas@4 subsea. com BASSI OFFSHORE roberto. biollo@bassioffshore. eu emilien. rulence@bureauveritas. com Bureau Veritas Marine francois. migeon@bureauveritas. com & Offshore aymeric. david@bureauveritas. com 4 Subsea gergely. szekely@fluid. contitech. hu 5 Conti. Tech Rubber Tibor. Nagy@fluid. contitech. hu istvan. grepaly@fluid. contitech. hu 6 DNV-GL 7 Dunlop Oil & Marine 8 ETA 9 Exxon. Mobil David Barnard 10 Clearwater FPC 20 Erik Bendiksen 11 NOV Flexibles 21 Trond Sundby 22 Langøy Morten Andre 12 Jorge. A. Suarez@dnvgl. com Kam. Zandiyeh@fluid. contitech. co. uk Jo. Wiggers@fluid. contitech. co. uk Petroleum Safety trond-e. sundby@ptil. no Authority Morten. Langoy@ptil. no 13 SAIPEM Francois-Regis. PIONETTI@saipem-sa. com Stephane. GIACCOBI@saipem. com Cyrille. MENGEOT@saipem. com 14 Technip 15 TOTAL 16 17 18 19 20 21 22 23 24 25 sdutt@technip. com jarrieche@technip. com ludovic. assier@total. com Vincent. Lagarrigue@trelleborg. com Trelleborg Industrie Jean-Noel. Vincent@trelleborg. com SAS Wood Group Kenny INTECSEA MARINTEK SBM Offshore Shell Evonik Weatherford Statoil Kongsberg Oil&Gas david. ponchon@trelleborg. com Remi. Morvan@woodgroupkenny. com Shankar. Bhat@intecsea. com Naiquan. Ye@marintek. sintef. no Benjamin. Biausser@sbmoffshore. com charles. paton@shell. com jan. berger@evonik. com sarah. abercrombie@weatherford. com tps@statoil. com rune. haakonsen@kogt. kongsberg. com torgrim. andersen@kogt. kongsberg. com Techflow Flexibles Ltd andy. thompson@tff. uk. com Techflow Flexibles yuxianhong@yuelongchina. com Yantai Techflow Flexibles yangpeng@yuelongchina. com Yantai Kent Caveny Services kcservllc@comcast. net LLC
UPDATED TARGET DATES FOR NWI AND DELIVERABLES • API 17 K - New 3 rd edition to be published no later than 3 Q 2017. • API 17 B - 17 K based update to be kicked off in 2 H 2017 after publishing API 17 K • API 17 L 1&L 2 - Revision process to be kicked off in 2 H 2017 after publishing API 17 K • API 17 TR 2 - K. Doynov to submit SRRR form, after 17 TR 2 JIP completion ~ 2018
FUTURE MEETINGS & RESOURCE NEEDS PLANS FOR FUTURE FPTG MEETINGS 1 -2 Q 2016: Addressing API SPEC 17 K Ballot Comments via FPTG teleconferences in RESOURCE NEEDS 2 Q 2017: API editorial help for 3 rd edition of API 17 K
- Slides: 9